name: decomposing-plans
|
||
description: Use after writing-plans to decompose monolithic plan into individual task files and identify tasks that can run in parallel (up to 2 subagents simultaneously)
|
||
allowed-tools: [Read, Write, Bash]
|
||
---
|
||
|
||
# Decomposing Plans for Parallel Execution
|
||
|
||
Run immediately after `/write-plan` to break monolithic plan into task files and identify parallelization opportunities.
|
||
|
||
**Core principle:** Individual task files save context + parallel batches save time = efficient execution
|
||
|
||
## When to Use
|
||
|
||
Use after `/write-plan` when you have a monolithic implementation plan and want to:
|
||
- Split it into individual task files (saves context tokens for subagents)
|
||
- Identify which tasks can run in parallel (up to 2 simultaneous subagents)
|
||
- Prepare for parallel-subagent-driven-development
|
||
|
||
## Prerequisites
|
||
|
||
**REQUIRED:** Must have monolithic plan file at `docs/plans/YYYY-MM-DD-<feature-name>.md`
|
||
|
||
## The Process
|
||
|
||
### Step 1: Locate Plan File
|
||
|
||
User provides plan file path, or find most recent:
|
||
```bash
|
||
ls -t docs/plans/*.md | head -1
|
||
```
|
||
|
||
### Step 2: Run Decomposition Script
|
||
|
||
Execute Python helper script:
|
||
```bash
|
||
python superpowers/skills/decomposing-plans/decompose-plan.py <plan-file>
|
||
```
|
||
|
||
**Script does:**
|
||
1. Parses monolithic plan to extract tasks
|
||
2. Analyzes dependencies (file-based and task-based)
|
||
3. Identifies parallel batches (max 2 tasks at once)
|
||
4. Creates individual task files
|
||
5. Generates manifest.json
|
||
6. Reports statistics
|
||
|
||
### Step 3: Review Generated Files
|
||
|
||
Check output directory `docs/plans/tasks/<plan-name>/`:
|
||
- Individual task files: `<feature>-task-NN.md`
|
||
- Execution manifest: `<feature>-manifest.json`
|
||
|
||
**Example structure:**
|
||
```
|
||
docs/plans/
|
||
├── 2025-01-18-user-auth.md # Monolithic plan
|
||
└── tasks/
|
||
└── 2025-01-18-user-auth/ # Plan-specific subfolder
|
||
├── user-auth-task-01.md
|
||
├── user-auth-task-02.md
|
||
├── user-auth-task-03.md
|
||
└── user-auth-manifest.json
|
||
```
|
||
|
||
### Step 4: Verify Task Decomposition
|
||
|
||
Read a few task files to verify:
|
||
- Tasks are correctly extracted
|
||
- Dependencies are accurate
|
||
- Files to modify are identified
|
||
- Verification checklists are present
|
||
|
||
### Step 5: Review Manifest
|
||
|
||
Read `<feature>-manifest.json` to verify:
|
||
- Parallel batches make sense
|
||
- No conflicting tasks in same batch
|
||
- Dependencies are correct
|
||
|
||
### Step 6: Adjust if Needed
|
||
|
||
If decomposition needs adjustment:
|
||
- Manually edit task files
|
||
- Manually edit manifest.json parallel_batches array
|
||
- Update dependencies if needed
|
||
|
||
### Step 7: Announce Results
|
||
|
||
Tell the user:
|
||
```
|
||
✅ Plan decomposed successfully!
|
||
|
||
Total tasks: N
|
||
Parallel batches: M
|
||
- Pairs (2 parallel): X
|
||
- Sequential: Y
|
||
Estimated speedup: Z%
|
||
|
||
Task files: docs/plans/tasks/<plan-name>/<feature>-task-*.md
|
||
Manifest: docs/plans/tasks/<plan-name>/<feature>-manifest.json
|
||
|
||
Next: Use parallel-subagent-driven-development skill
|
||
```
|
||
|
||
## Task File Format
|
||
|
||
Each task file created:
|
||
|
||
```markdown
|
||
# Task NN: [Task Name]
|
||
|
||
## Dependencies
|
||
- Previous tasks: [list or "none"]
|
||
- Must complete before: [list or "none"]
|
||
|
||
## Parallelizable
|
||
- Can run in parallel with: [task numbers or "none"]
|
||
|
||
## Implementation
|
||
|
||
[Exact steps from monolithic plan for THIS task only]
|
||
|
||
## Files to Modify
|
||
- path/to/file1.ts
|
||
- path/to/file2.ts
|
||
|
||
## Verification Checklist
|
||
- [ ] Implementation complete
|
||
- [ ] Tests written (TDD - test first!)
|
||
- [ ] All tests pass
|
||
- [ ] Lint/type check clean
|
||
- [ ] Code review requested
|
||
- [ ] Code review passed
|
||
```
|
||
|
||
## Manifest Format
|
||
|
||
```json
|
||
{
|
||
"plan": "docs/plans/2025-01-18-feature.md",
|
||
"feature": "feature-name",
|
||
"created": "2025-01-18T10:00:00Z",
|
||
"total_tasks": 5,
|
||
"tasks": [
|
||
{
|
||
"id": 1,
|
||
"title": "Implement user model",
|
||
"file": "docs/plans/tasks/feature-task-01.md",
|
||
"dependencies": [],
|
||
"blocks": [3],
|
||
"files": ["src/models/user.ts"],
|
||
"status": "pending"
|
||
},
|
||
{
|
||
"id": 2,
|
||
"title": "Implement logger",
|
||
"file": "docs/plans/tasks/feature-task-02.md",
|
||
"dependencies": [],
|
||
"blocks": [],
|
||
"files": ["src/utils/logger.ts"],
|
||
"status": "pending"
|
||
},
|
||
{
|
||
"id": 3,
|
||
"title": "Add user validation",
|
||
"file": "docs/plans/tasks/feature-task-03.md",
|
||
"dependencies": [1],
|
||
"blocks": [],
|
||
"files": ["src/models/user.ts"],
|
||
"status": "pending"
|
||
}
|
||
],
|
||
"parallel_batches": [
|
||
[1, 2], // Tasks 1 and 2 can run together
|
||
[3] // Task 3 must wait for task 1
|
||
]
|
||
}
|
||
```
|
||
|
||
## Dependency Analysis
|
||
|
||
**Script analyzes three types of dependencies:**
|
||
|
||
### 1. Explicit Task Dependencies
|
||
If task content mentions "after task N" or "depends on task N":
|
||
```
|
||
Task 3: "After task 1 completes, add validation..."
|
||
→ Task 3 depends on Task 1
|
||
```
|
||
|
||
### 2. File-Based Dependencies
|
||
If tasks modify the same file:
|
||
```
|
||
Task 1: Modifies src/models/user.ts
|
||
Task 3: Modifies src/models/user.ts
|
||
→ Task 3 depends on Task 1 (sequential)
|
||
```
|
||
|
||
### 3. Default Sequential
|
||
Unless marked "independent" or "parallel", tasks depend on previous task:
|
||
```
|
||
Task 1: ...
|
||
Task 2: (no explicit dependency mentioned)
|
||
→ Task 2 depends on Task 1
|
||
```
|
||
|
||
## Parallel Batch Identification
|
||
|
||
**Algorithm:**
|
||
1. Find tasks with no unsatisfied dependencies
|
||
2. Group up to 2 tasks that:
|
||
- Have no mutual dependencies
|
||
- Don't modify same files
|
||
- Don't block each other
|
||
3. Create batch
|
||
4. Repeat until all tasks scheduled
|
||
|
||
**Max 2 tasks per batch** (constraint for code review quality)
|
||
|
||
## Benefits
|
||
|
||
### Context Savings
|
||
- Before: Each subagent reads ~5000 tokens (monolithic plan)
|
||
- After: Each subagent reads ~500 tokens (task file)
|
||
- **90% context reduction per subagent**
|
||
|
||
### Time Savings
|
||
- Before: 5 tasks × 10 min = 50 min
|
||
- After: 3 batches × 10 min = 30 min (if 2 parallel pairs)
|
||
- **40% time reduction for parallelizable plans**
|
||
|
||
### Clarity
|
||
- Each subagent has focused, bounded scope
|
||
- Clear verification checklist per task
|
||
- No confusion about which task to implement
|
||
|
||
## Red Flags
|
||
|
||
**Never:**
|
||
- Skip running the decomposition script (manual decomposition error-prone)
|
||
- Proceed with decomposed plan without reviewing manifest
|
||
- Ignore dependency conflicts flagged by script
|
||
- Skip verifying parallel batches make sense
|
||
|
||
**If script fails:**
|
||
- Check plan file format (needs clear task sections)
|
||
- Verify plan has recognizable task markers ("## Task N:", etc.)
|
||
- Manually create task files if plan format is unusual
|
||
- Report issue for script improvement
|
||
|
||
## Integration
|
||
|
||
**Required prerequisite:**
|
||
- **writing-plans** - REQUIRED: Creates monolithic plan that this skill decomposes
|
||
|
||
**This skill enables:**
|
||
- **parallel-subagent-driven-development** - REQUIRED NEXT: Executes the decomposed plan with parallel subagents
|
||
|
||
**Alternative workflow:**
|
||
- **subagent-driven-development** - Use if you DON'T want parallel execution (works with monolithic plan)
|
||
|
||
## Example Output
|
||
|
||
```bash
|
||
$ python superpowers/skills/decomposing-plans/decompose-plan.py docs/plans/2025-01-18-user-auth.md
|
||
|
||
📖 Reading plan: docs/plans/2025-01-18-user-auth.md
|
||
✓ Found 5 tasks
|
||
|
||
🔍 Analyzing dependencies...
|
||
Task 1: No dependencies
|
||
Task 2: No dependencies
|
||
Task 3: Depends on task 1 (file conflict: src/models/user.ts)
|
||
Task 4: Depends on task 3
|
||
Task 5: No dependencies
|
||
|
||
⚡ Identifying parallelization opportunities...
|
||
Batch 1: Tasks 1, 2 (parallel)
|
||
Batch 2: Tasks 3, 5 (parallel)
|
||
Batch 3: Task 4 (sequential)
|
||
|
||
📝 Writing 5 task files to docs/plans/tasks/2025-01-18-user-auth/
|
||
✓ user-auth-task-01.md
|
||
✓ user-auth-task-02.md
|
||
✓ user-auth-task-03.md
|
||
✓ user-auth-task-04.md
|
||
✓ user-auth-task-05.md
|
||
|
||
📋 Writing execution manifest...
|
||
✓ user-auth-manifest.json
|
||
|
||
============================================================
|
||
✅ Plan decomposition complete!
|
||
============================================================
|
||
Total tasks: 5
|
||
Parallel batches: 3
|
||
- Pairs (2 parallel): 2
|
||
- Sequential: 1
|
||
Estimated speedup: 40.0%
|
||
|
||
Manifest: docs/plans/tasks/2025-01-18-user-auth/user-auth-manifest.json
|
||
|
||
Next: Use parallel-subagent-driven-development skill
|
||
```
|
||
|
||
## Troubleshooting
|
||
|
||
### Script Can't Parse Tasks
|
||
|
||
**Problem:** Script reports "Found 0 tasks"
|
||
|
||
**Solutions:**
|
||
1. Check plan format - needs clear task markers:
|
||
- `## Task 1: Title`
|
||
- `## 1. Title`
|
||
- `**Task 1:** Title`
|
||
2. Manually add task markers if plan uses different format
|
||
3. Run script with `--verbose` for debug output
|
||
|
||
### Incorrect Dependencies
|
||
|
||
**Problem:** Script identifies wrong dependencies
|
||
|
||
**Solutions:**
|
||
1. Review manifest.json parallel_batches
|
||
2. Manually edit manifest to fix dependencies
|
||
3. Add explicit dependency markers in plan ("depends on task N")
|
||
|
||
### Too Conservative (Too Many Sequential)
|
||
|
||
**Problem:** Script creates too many sequential batches
|
||
|
||
**Solutions:**
|
||
1. Mark tasks as "independent" in plan text
|
||
2. Manually edit manifest parallel_batches to add parallelization
|
||
3. Verify file paths are correctly extracted
|
||
|
||
## Next Steps
|
||
|
||
After decomposition:
|
||
1. Review task files for accuracy
|
||
2. Review manifest for correct dependencies
|
||
3. Announce results to user
|
||
4. Proceed to parallel-subagent-driven-development skill
|
||
|
||
## After Decomposition
|
||
|
||
After decomposition completes successfully, prompt user:
|
||
|
||
```
|
||
Plan decomposed into X tasks across Y parallel batches.
|
||
|
||
Manifest: `docs/plans/tasks/YYYY-MM-DD-<feature>/manifest.json`
|
||
Tasks: `docs/plans/tasks/YYYY-MM-DD-<feature>/<task-files>`
|
||
|
||
Options:
|
||
A) Review the plan with plan-review
|
||
B) Execute immediately with parallel-subagent-driven-development
|
||
C) Save and exit (resume later with /cc:resume)
|
||
|
||
Choose: (A/B/C)
|
||
```
|
||
|
||
**If user chooses A:**
|
||
- Invoke `plan-review` skill
|
||
- After review completes and plan approved
|
||
- Return to this prompt (offer B or C)
|
||
|
||
**If user chooses B:**
|
||
- Proceed directly to `parallel-subagent-driven-development` skill
|
||
- Begin executing tasks in parallel batches
|
||
|
||
**If user chooses C:**
|
||
- Invoke `state-persistence` skill to save execution checkpoint
|
||
- Save as `YYYY-MM-DD-<feature>-execution.md` with:
|
||
- Plan reference and manifest location
|
||
- Status: ready to execute, 0 tasks complete
|
||
- Next step: Resume with `/cc:resume` and execute
|
||
- Exit workflow after save completes
|