name: decomposing-plans
description: Use after writing-plans to decompose monolithic plan into individual task files and identify tasks that can run in parallel (up to 2 subagents simultaneously)
allowed-tools: [Read, Write, Bash]
---
# Decomposing Plans for Parallel Execution
Run immediately after `/write-plan` to break monolithic plan into task files and identify parallelization opportunities.
**Core principle:** Individual task files save context + parallel batches save time = efficient execution
## When to Use
Use after `/write-plan` when you have a monolithic implementation plan and want to:
- Split it into individual task files (saves context tokens for subagents)
- Identify which tasks can run in parallel (up to 2 simultaneous subagents)
- Prepare for parallel-subagent-driven-development
## Prerequisites
**REQUIRED:** Must have monolithic plan file at `docs/plans/YYYY-MM-DD-<feature-name>.md`
## The Process
### Step 1: Locate Plan File
User provides plan file path, or find most recent:
```bash
ls -t docs/plans/*.md | head -1
```
### Step 2: Run Decomposition Script
Execute Python helper script:
```bash
python superpowers/skills/decomposing-plans/decompose-plan.py <plan-file>
```
**Script does:**
1. Parses monolithic plan to extract tasks
2. Analyzes dependencies (file-based and task-based)
3. Identifies parallel batches (max 2 tasks at once)
4. Creates individual task files
5. Generates manifest.json
6. Reports statistics
### Step 3: Review Generated Files
Check output directory `docs/plans/tasks/<plan-name>/`:
- Individual task files: `<feature>-task-NN.md`
- Execution manifest: `<feature>-manifest.json`
**Example structure:**
```
docs/plans/
├── 2025-01-18-user-auth.md # Monolithic plan
└── tasks/
└── 2025-01-18-user-auth/ # Plan-specific subfolder
├── user-auth-task-01.md
├── user-auth-task-02.md
├── user-auth-task-03.md
└── user-auth-manifest.json
```
### Step 4: Verify Task Decomposition
Read a few task files to verify:
- Tasks are correctly extracted
- Dependencies are accurate
- Files to modify are identified
- Verification checklists are present
### Step 5: Review Manifest
Read `<feature>-manifest.json` to verify:
- Parallel batches make sense
- No conflicting tasks in same batch
- Dependencies are correct
### Step 6: Adjust if Needed
If decomposition needs adjustment:
- Manually edit task files
- Manually edit manifest.json parallel_batches array
- Update dependencies if needed
### Step 7: Announce Results
Tell the user:
```
✅ Plan decomposed successfully!
Total tasks: N
Parallel batches: M
- Pairs (2 parallel): X
- Sequential: Y
Estimated speedup: Z%
Task files: docs/plans/tasks/<plan-name>/<feature>-task-*.md
Manifest: docs/plans/tasks/<plan-name>/<feature>-manifest.json
Next: Use parallel-subagent-driven-development skill
```
## Task File Format
Each task file created:
```markdown
# Task NN: [Task Name]
## Dependencies
- Previous tasks: [list or "none"]
- Must complete before: [list or "none"]
## Parallelizable
- Can run in parallel with: [task numbers or "none"]
## Implementation
[Exact steps from monolithic plan for THIS task only]
## Files to Modify
- path/to/file1.ts
- path/to/file2.ts
## Verification Checklist
- [ ] Implementation complete
- [ ] Tests written (TDD - test first!)
- [ ] All tests pass
- [ ] Lint/type check clean
- [ ] Code review requested
- [ ] Code review passed
```
## Manifest Format
```json
{
"plan": "docs/plans/2025-01-18-feature.md",
"feature": "feature-name",
"created": "2025-01-18T10:00:00Z",
"total_tasks": 5,
"tasks": [
{
"id": 1,
"title": "Implement user model",
"file": "docs/plans/tasks/feature-task-01.md",
"dependencies": [],
"blocks": [3],
"files": ["src/models/user.ts"],
"status": "pending"
},
{
"id": 2,
"title": "Implement logger",
"file": "docs/plans/tasks/feature-task-02.md",
"dependencies": [],
"blocks": [],
"files": ["src/utils/logger.ts"],
"status": "pending"
},
{
"id": 3,
"title": "Add user validation",
"file": "docs/plans/tasks/feature-task-03.md",
"dependencies": [1],
"blocks": [],
"files": ["src/models/user.ts"],
"status": "pending"
}
],
"parallel_batches": [
[1, 2], // Tasks 1 and 2 can run together
[3] // Task 3 must wait for task 1
]
}
```
## Dependency Analysis
**Script analyzes three types of dependencies:**
### 1. Explicit Task Dependencies
If task content mentions "after task N" or "depends on task N":
```
Task 3: "After task 1 completes, add validation..."
→ Task 3 depends on Task 1
```
### 2. File-Based Dependencies
If tasks modify the same file:
```
Task 1: Modifies src/models/user.ts
Task 3: Modifies src/models/user.ts
→ Task 3 depends on Task 1 (sequential)
```
### 3. Default Sequential
Unless marked "independent" or "parallel", tasks depend on previous task:
```
Task 1: ...
Task 2: (no explicit dependency mentioned)
→ Task 2 depends on Task 1
```
## Parallel Batch Identification
**Algorithm:**
1. Find tasks with no unsatisfied dependencies
2. Group up to 2 tasks that:
- Have no mutual dependencies
- Don't modify same files
- Don't block each other
3. Create batch
4. Repeat until all tasks scheduled
**Max 2 tasks per batch** (constraint for code review quality)
## Benefits
### Context Savings
- Before: Each subagent reads ~5000 tokens (monolithic plan)
- After: Each subagent reads ~500 tokens (task file)
- **90% context reduction per subagent**
### Time Savings
- Before: 5 tasks × 10 min = 50 min
- After: 3 batches × 10 min = 30 min (if 2 parallel pairs)
- **40% time reduction for parallelizable plans**
### Clarity
- Each subagent has focused, bounded scope
- Clear verification checklist per task
- No confusion about which task to implement
## Red Flags
**Never:**
- Skip running the decomposition script (manual decomposition error-prone)
- Proceed with decomposed plan without reviewing manifest
- Ignore dependency conflicts flagged by script
- Skip verifying parallel batches make sense
**If script fails:**
- Check plan file format (needs clear task sections)
- Verify plan has recognizable task markers ("## Task N:", etc.)
- Manually create task files if plan format is unusual
- Report issue for script improvement
## Integration
**Required prerequisite:**
- **writing-plans** - REQUIRED: Creates monolithic plan that this skill decomposes
**This skill enables:**
- **parallel-subagent-driven-development** - REQUIRED NEXT: Executes the decomposed plan with parallel subagents
**Alternative workflow:**
- **subagent-driven-development** - Use if you DON'T want parallel execution (works with monolithic plan)
## Example Output
```bash
$ python superpowers/skills/decomposing-plans/decompose-plan.py docs/plans/2025-01-18-user-auth.md
📖 Reading plan: docs/plans/2025-01-18-user-auth.md
✓ Found 5 tasks
🔍 Analyzing dependencies...
Task 1: No dependencies
Task 2: No dependencies
Task 3: Depends on task 1 (file conflict: src/models/user.ts)
Task 4: Depends on task 3
Task 5: No dependencies
⚡ Identifying parallelization opportunities...
Batch 1: Tasks 1, 2 (parallel)
Batch 2: Tasks 3, 5 (parallel)
Batch 3: Task 4 (sequential)
📝 Writing 5 task files to docs/plans/tasks/2025-01-18-user-auth/
✓ user-auth-task-01.md
✓ user-auth-task-02.md
✓ user-auth-task-03.md
✓ user-auth-task-04.md
✓ user-auth-task-05.md
📋 Writing execution manifest...
✓ user-auth-manifest.json
============================================================
✅ Plan decomposition complete!
============================================================
Total tasks: 5
Parallel batches: 3
- Pairs (2 parallel): 2
- Sequential: 1
Estimated speedup: 40.0%
Manifest: docs/plans/tasks/2025-01-18-user-auth/user-auth-manifest.json
Next: Use parallel-subagent-driven-development skill
```
## Troubleshooting
### Script Can't Parse Tasks
**Problem:** Script reports "Found 0 tasks"
**Solutions:**
1. Check plan format - needs clear task markers:
- `## Task 1: Title`
- `## 1. Title`
- `**Task 1:** Title`
2. Manually add task markers if plan uses different format
3. Run script with `--verbose` for debug output
### Incorrect Dependencies
**Problem:** Script identifies wrong dependencies
**Solutions:**
1. Review manifest.json parallel_batches
2. Manually edit manifest to fix dependencies
3. Add explicit dependency markers in plan ("depends on task N")
### Too Conservative (Too Many Sequential)
**Problem:** Script creates too many sequential batches
**Solutions:**
1. Mark tasks as "independent" in plan text
2. Manually edit manifest parallel_batches to add parallelization
3. Verify file paths are correctly extracted
## Next Steps
After decomposition:
1. Review task files for accuracy
2. Review manifest for correct dependencies
3. Announce results to user
4. Proceed to parallel-subagent-driven-development skill
## After Decomposition
After decomposition completes successfully, prompt user:
```
Plan decomposed into X tasks across Y parallel batches.
Manifest: `docs/plans/tasks/YYYY-MM-DD-<feature>/manifest.json`
Tasks: `docs/plans/tasks/YYYY-MM-DD-<feature>/<task-files>`
Options:
A) Review the plan with plan-review
B) Execute immediately with parallel-subagent-driven-development
C) Save and exit (resume later with /cc:resume)
Choose: (A/B/C)
```
**If user chooses A:**
- Invoke `plan-review` skill
- After review completes and plan approved
- Return to this prompt (offer B or C)
**If user chooses B:**
- Proceed directly to `parallel-subagent-driven-development` skill
- Begin executing tasks in parallel batches
**If user chooses C:**
- Invoke `state-persistence` skill to save execution checkpoint
- Save as `YYYY-MM-DD-<feature>-execution.md` with:
- Plan reference and manifest location
- Status: ready to execute, 0 tasks complete
- Next step: Resume with `/cc:resume` and execute
- Exit workflow after save completes