# Decomposition & Reconstruction: Advanced Methodology
|
||
|
||
## Workflow
|
||
|
||
Copy this checklist for complex decomposition scenarios:
|
||
|
||
```
|
||
Advanced Decomposition Progress:
|
||
- [ ] Step 1: Apply hierarchical decomposition techniques
|
||
- [ ] Step 2: Build and analyze dependency graphs
|
||
- [ ] Step 3: Perform critical path analysis
|
||
- [ ] Step 4: Use advanced property measurement
|
||
- [ ] Step 5: Apply optimization algorithms
|
||
```
|
||
|
||
**Step 1: Apply hierarchical decomposition techniques** - Multi-level decomposition with consistent abstraction levels. See [1. Hierarchical Decomposition](#1-hierarchical-decomposition).
|
||
|
||
**Step 2: Build and analyze dependency graphs** - Visualize and analyze component relationships. See [2. Dependency Graph Analysis](#2-dependency-graph-analysis).
|
||
|
||
**Step 3: Perform critical path analysis** - Identify bottlenecks using PERT/CPM. See [3. Critical Path Analysis](#3-critical-path-analysis).
|
||
|
||
**Step 4: Use advanced property measurement** - Rigorous measurement and statistical analysis. See [4. Advanced Property Measurement](#4-advanced-property-measurement).
|
||
|
||
**Step 5: Apply optimization algorithms** - Systematic reconstruction approaches. See [5. Optimization Algorithms](#5-optimization-algorithms).
|
||
|
||
---
|
||
|
||
## 1. Hierarchical Decomposition
|
||
|
||
### Multi-Level Decomposition Strategy
|
||
|
||
Break into levels: L0 (System) → L1 (3-7 subsystems) → L2 (3-7 components each) → L3+ (only if needed). Stop when component is atomic or further breakdown doesn't help goal.
|
||
|
||
**Abstraction consistency:** All components at same level should be at same abstraction type (e.g., all architectural components, not mixing "API Service" with "user login function").
|
||
|
||
**Template:**
|
||
```
|
||
System → Subsystem A → Component A.1, A.2, A.3
|
||
→ Subsystem B → Component B.1, B.2
|
||
→ Subsystem C → Component C.1 (atomic)
|
||
```
|
||
|
||
Document WHY decomposed to this level and WHY stopped.
|
||
|
||
---
|
||
|
||
## 2. Dependency Graph Analysis
|
||
|
||
### Building Dependency Graphs
|
||
|
||
**Nodes:** Components (from decomposition)
|
||
**Edges:** Relationships (dependency, data flow, control flow, etc.)
|
||
**Direction:** Arrow shows dependency direction (A → B means A depends on B)
|
||
|
||
**Example:**
|
||
|
||
```
|
||
Frontend → API Service → Database
|
||
↓
|
||
Cache
|
||
↓
|
||
Message Queue
|
||
```
|
||
|
||
### Graph Properties
|
||
|
||
**Strongly Connected Components (SCCs):** Circular dependencies (A → B → C → A). Problematic for isolation. Use Tarjan's algorithm.
|
||
|
||
**Topological Ordering:** Linear order where edges point forward (only if acyclic). Reveals safe build/deploy order.
|
||
|
||
**Critical Path:** Longest weighted path, determines minimum completion time. Bottleneck for optimization.
|
||
|
||
### Dependency Analysis
|
||
|
||
**Forward:** "If I change X, what breaks?" (BFS from X outgoing)
|
||
**Backward:** "What must work for X to function?" (BFS from X incoming)
|
||
**Transitive Reduction:** Remove redundant edges to simplify visualization.
|
||
|
||
---
|
||
|
||
## 3. Critical Path Analysis
|
||
|
||
### PERT/CPM (Program Evaluation and Review Technique / Critical Path Method)
|
||
|
||
**Use case:** System with sequential stages, need to identify time bottlenecks
|
||
|
||
**Inputs:**
|
||
- Components with estimated duration
|
||
- Dependencies between components
|
||
|
||
**Process:**
|
||
|
||
**Step 1: Build dependency graph with durations**
|
||
|
||
```
|
||
A (3h) → B (5h) → D (2h)
|
||
A (3h) → C (4h) → D (2h)
|
||
```
|
||
|
||
**Step 2: Calculate earliest start time (EST) for each component**
|
||
|
||
EST(node) = max(EST(predecessor) + duration(predecessor)) for all predecessors
|
||
|
||
**Example:**
|
||
- EST(A) = 0
|
||
- EST(B) = EST(A) + duration(A) = 0 + 3 = 3h
|
||
- EST(C) = EST(A) + duration(A) = 0 + 3 = 3h
|
||
- EST(D) = max(EST(B) + duration(B), EST(C) + duration(C)) = max(3+5, 3+4) = 8h
|
||
|
||
**Step 3: Calculate latest finish time (LFT) working backwards**
|
||
|
||
LFT(node) = min(LFT(successor) - duration(node)) for all successors
|
||
|
||
**Example (working backwards from D):**
|
||
- LFT(D) = project deadline (say 10h)
|
||
- LFT(B) = LFT(D) - duration(B) = 10 - 5 = 5h
|
||
- LFT(C) = LFT(D) - duration(C) = 10 - 4 = 6h
|
||
- LFT(A) = min(LFT(B) - duration(A), LFT(C) - duration(A)) = min(5-3, 6-3) = 2h
|
||
|
||
**Step 4: Calculate slack (float)**
|
||
|
||
Slack(node) = LFT(node) - EST(node) - duration(node)
|
||
|
||
**Example:**
|
||
- Slack(A) = 2 - 0 - 3 = -1h (on critical path, negative slack means delay)
|
||
- Slack(B) = 5 - 3 - 5 = -3h (critical)
|
||
- Slack(C) = 6 - 3 - 4 = -1h (has some float)
|
||
- Slack(D) = 10 - 8 - 2 = 0 (critical)
|
||
|
||
**Step 5: Identify critical path**
|
||
|
||
Components with zero (or minimum) slack form the critical path.
|
||
|
||
**Critical path:** A → B → D (total 10h)
|
||
|
||
**Optimization insight:** Only optimizing B will reduce total time. Optimizing C (non-critical) won't help.
|
||
|
||
### Handling Uncertainty (PERT Estimates)
|
||
|
||
When durations are uncertain, use three-point estimates:
|
||
|
||
- **Optimistic (O):** Best case
|
||
- **Most Likely (M):** Expected case
|
||
- **Pessimistic (P):** Worst case
|
||
|
||
**Expected duration:** E = (O + 4M + P) / 6
|
||
|
||
**Standard deviation:** σ = (P - O) / 6
|
||
|
||
**Example:**
|
||
- Component A: O=2h, M=3h, P=8h
|
||
- Expected: E = (2 + 4×3 + 8) / 6 = 3.67h
|
||
- Std dev: σ = (8 - 2) / 6 = 1h
|
||
|
||
**Use expected durations for critical path analysis, report confidence intervals**
|
||
|
||
---
|
||
|
||
## 4. Advanced Property Measurement
|
||
|
||
### Quantitative vs Qualitative Properties
|
||
|
||
**Quantitative (measurable):**
|
||
- Latency (ms), throughput (req/s), cost ($/month), lines of code, error rate (%)
|
||
- **Measurement:** Use APM tools, profilers, logs, benchmarks
|
||
- **Reporting:** Mean, median, p95, p99, min, max, std dev
|
||
|
||
**Qualitative (subjective):**
|
||
- Code readability, maintainability, user experience, team morale
|
||
- **Measurement:** Use rating scales (1-10), comparative ranking, surveys
|
||
- **Reporting:** Mode, distribution, outliers
|
||
|
||
### Statistical Rigor
|
||
|
||
**For quantitative measurements:**
|
||
|
||
**1. Multiple samples:** Don't rely on single measurement
|
||
- Run benchmark 10+ times, report distribution
|
||
- Example: Latency = 250ms ± 50ms (mean ± std dev, n=20)
|
||
|
||
**2. Control for confounds:** Isolate what you're measuring
|
||
- Example: Measure DB query time with same dataset, same load, same hardware
|
||
|
||
**3. Statistical significance:** Determine if difference is real or noise
|
||
- Use t-test or ANOVA to compare means
|
||
- Report p-value (p < 0.05 typically considered significant)
|
||
|
||
**For qualitative measurements:**
|
||
|
||
**1. Multiple raters:** Reduce individual bias
|
||
- Have 3+ people rate complexity independently, average scores
|
||
|
||
**2. Calibration:** Define rating scale clearly
|
||
- Example: Complexity 1="< 50 LOC, no dependencies", 10=">1000 LOC, 20+ dependencies"
|
||
|
||
**3. Inter-rater reliability:** Check if raters agree
|
||
- Calculate Cronbach's alpha or correlation coefficient
|
||
|
||
### Performance Profiling Techniques
|
||
|
||
**CPU Profiling:**
|
||
- Identify which components consume most CPU time
|
||
- Tools: perf, gprof, Chrome DevTools, Xcode Instruments
|
||
|
||
**Memory Profiling:**
|
||
- Identify which components allocate most memory or leak
|
||
- Tools: valgrind, heaptrack, Chrome DevTools, Instruments
|
||
|
||
**I/O Profiling:**
|
||
- Identify which components perform most disk/network I/O
|
||
- Tools: iotop, iostat, Network tab in DevTools
|
||
|
||
**Tracing:**
|
||
- Track execution flow through distributed systems
|
||
- Tools: OpenTelemetry, Jaeger, Zipkin, AWS X-Ray
|
||
|
||
**Result:** Component-level resource consumption data for bottleneck analysis
|
||
|
||
---
|
||
|
||
## 5. Optimization Algorithms
|
||
|
||
### Greedy Optimization
|
||
|
||
**Approach:** Optimize components in order of highest impact first
|
||
|
||
**Algorithm:**
|
||
1. Measure impact of optimizing each component (reduction in latency, cost, etc.)
|
||
2. Sort components by impact (descending)
|
||
3. Optimize highest-impact component
|
||
4. Re-measure, repeat until goal achieved or diminishing returns
|
||
|
||
**Example (latency optimization):**
|
||
- Components: A (100ms), B (500ms), C (50ms)
|
||
- Sort by impact: B (500ms), A (100ms), C (50ms)
|
||
- Optimize B first → Reduce to 200ms → Total latency improved by 300ms
|
||
- Re-measure, continue
|
||
|
||
**Advantage:** Fast, often gets 80% of benefit with 20% of effort
|
||
**Limitation:** May miss global optimum (e.g., removing B entirely better than optimizing B)
|
||
|
||
### Dynamic Programming Approach
|
||
|
||
**Approach:** Find optimal decomposition/reconstruction by exploring combinations
|
||
|
||
**Use case:** When multiple components interact, greedy may not find best solution
|
||
|
||
**Example (budget allocation):**
|
||
- Budget: $1000/month
|
||
- Components: A (improves UX, costs $400), B (reduces latency, costs $600), C (adds feature, costs $500)
|
||
- Constraint: Total cost ≤ $1000
|
||
- Goal: Maximize value
|
||
|
||
**Algorithm:**
|
||
1. Enumerate all feasible combinations: {A}, {B}, {C}, {A+B}, {A+C}, {B+C}
|
||
2. Calculate value and cost for each
|
||
3. Select combination with max value under budget constraint
|
||
|
||
**Result:** Optimal combination (may not be greedy choice)
|
||
|
||
### Constraint Satisfaction
|
||
|
||
**Approach:** Find reconstruction that satisfies all hard constraints
|
||
|
||
**Use case:** Multiple constraints (latency < 500ms AND cost < $500/month AND reliability > 99%)
|
||
|
||
**Formulation:**
|
||
- Variables: Component choices (use component A or B? Parallelize or serialize?)
|
||
- Domains: Possible values for each choice
|
||
- Constraints: Rules that must be satisfied
|
||
|
||
**Algorithm:** Backtracking search, constraint propagation
|
||
**Tools:** CSP solvers (Z3, MiniZinc)
|
||
|
||
### Sensitivity Analysis
|
||
|
||
**Goal:** Understand how sensitive reconstruction is to property estimates
|
||
|
||
**Process:**
|
||
1. Build reconstruction based on measured/estimated properties
|
||
2. Vary each property by ±X% (e.g., ±20%)
|
||
3. Re-run reconstruction
|
||
4. Identify which properties most affect outcome
|
||
|
||
**Example:**
|
||
- Baseline: Component A latency = 100ms → Optimize B
|
||
- Sensitivity: If A latency = 150ms → Optimize A instead
|
||
- **Conclusion:** Decision is sensitive to A's latency estimate, need better measurement
|
||
|
||
---
|
||
|
||
## 6. Advanced Reconstruction Patterns
|
||
|
||
### Caching & Memoization
|
||
|
||
**Pattern:** Add caching layer for frequently accessed components
|
||
|
||
**When:** Component is slow, accessed repeatedly, output deterministic
|
||
|
||
**Example:** Database query repeated 1000x/sec → Add Redis cache → 95% cache hit rate → 20× latency reduction
|
||
|
||
**Trade-offs:** Memory cost, cache invalidation complexity, eventual consistency
|
||
|
||
### Batch Processing
|
||
|
||
**Pattern:** Process items in batches instead of one-at-a-time
|
||
|
||
**When:** Per-item overhead is high, latency not critical
|
||
|
||
**Example:** Send 1000 individual emails (1s each, total 1000s) → Batch into groups of 100 → Send via batch API (10s per batch, total 100s)
|
||
|
||
**Trade-offs:** Increased latency for individual items, complexity in failure handling
|
||
|
||
### Asynchronous Processing
|
||
|
||
**Pattern:** Decouple components using message queues
|
||
|
||
**When:** Component is slow but result not needed immediately
|
||
|
||
**Example:** User uploads video → Process synchronously (60s wait) → User unhappy
|
||
**Reconstruction:** User uploads → Queue processing → User sees "processing" → Email when done
|
||
|
||
**Trade-offs:** Complexity (need queue infrastructure), eventual consistency, harder to debug
|
||
|
||
### Load Balancing & Sharding
|
||
|
||
**Pattern:** Distribute load across multiple instances of a component
|
||
|
||
**When:** Component is bottleneck, can be parallelized, load is high
|
||
|
||
**Example:** Single DB handles 10K req/s, saturated → Shard by user ID → 10 DBs each handle 1K req/s
|
||
|
||
**Trade-offs:** Operational complexity, cross-shard queries expensive, rebalancing cost
|
||
|
||
### Circuit Breaker
|
||
|
||
**Pattern:** Fail fast when dependent component is down
|
||
|
||
**When:** Component depends on unreliable external service
|
||
|
||
**Example:** API calls external service → Service is down → API waits 30s per request → API becomes slow
|
||
**Reconstruction:** Add circuit breaker → Detect failures → Stop calling for 60s → Fail fast (< 1ms)
|
||
|
||
**Trade-offs:** Reduced functionality during outage, tuning thresholds (false positives vs negatives)
|
||
|
||
---
|
||
|
||
## 7. Failure Mode & Effects Analysis (FMEA)
|
||
|
||
### FMEA Process
|
||
|
||
**Goal:** Identify weaknesses and single points of failure in decomposed system
|
||
|
||
**Process:**
|
||
|
||
**Step 1: List all components**
|
||
|
||
**Step 2: For each component, identify failure modes**
|
||
- How can this component fail? (crash, slow, wrong output, security breach)
|
||
|
||
**Step 3: For each failure mode, assess:**
|
||
- **Severity (S):** Impact if failure occurs (1-10, 10 = catastrophic)
|
||
- **Occurrence (O):** Likelihood of failure (1-10, 10 = very likely)
|
||
- **Detection (D):** Ability to detect before impact (1-10, 10 = undetectable)
|
||
|
||
**Step 4: Calculate Risk Priority Number (RPN)**
|
||
RPN = S × O × D
|
||
|
||
**Step 5: Prioritize failures by RPN, design mitigations**
|
||
|
||
### Example
|
||
|
||
| Component | Failure Mode | S | O | D | RPN | Mitigation |
|
||
|-----------|--------------|---|---|---|-----|------------|
|
||
| Database | Crashes | 9 | 2 | 1 | 18 | Add replica, automatic failover |
|
||
| Cache | Stale data | 5 | 6 | 8 | 240 | Reduce TTL, add invalidation |
|
||
| API | DDoS attack | 8 | 4 | 3 | 96 | Add rate limiting, WAF |
|
||
|
||
**Highest RPN = 240 (Cache stale data)** → Address this first
|
||
|
||
### Mitigation Strategies
|
||
|
||
**Redundancy:** Multiple instances, failover
|
||
**Monitoring:** Early detection, alerting
|
||
**Graceful degradation:** Degrade functionality instead of total failure
|
||
**Rate limiting:** Prevent overload
|
||
**Input validation:** Prevent bad data cascading
|
||
**Circuit breakers:** Fail fast when dependencies down
|
||
|
||
---
|
||
|
||
## 8. Case Study Approach
|
||
|
||
### Comparative Analysis
|
||
|
||
Compare reconstruction alternatives in table format (Latency, Cost, Time, Risk, Maintainability). Make recommendation with rationale based on trade-offs.
|
||
|
||
### Iterative Refinement
|
||
|
||
If initial decomposition doesn't reveal insights, refine: go deeper in critical areas, switch decomposition strategy, add missing relationships. Re-run analysis. Stop when further refinement doesn't change recommendations.
|
||
|
||
---
|
||
|
||
## 9. Tool-Assisted Decomposition
|
||
|
||
**Static analysis:** CLOC, SonarQube (dependency graphs, complexity metrics)
|
||
**Dynamic analysis:** Flame graphs, perf, Chrome DevTools (CPU/memory/I/O), Jaeger/Zipkin (distributed tracing)
|
||
|
||
**Workflow:** Static analysis → Dynamic measurement → Manual validation → Combine quantitative + qualitative
|
||
|
||
**Caution:** Tools miss runtime dependencies, overestimate coupling, produce overwhelming detail. Use as guide, not truth.
|
||
|
||
---
|
||
|
||
## 10. Communication & Visualization
|
||
|
||
**Diagrams:** Hierarchy trees, dependency graphs (color-code critical path), property heatmaps, before/after comparisons
|
||
|
||
**Stakeholder views:**
|
||
- Executives: 1-page summary, key findings, business impact
|
||
- Engineers: Detailed breakdown, technical rationale, implementation
|
||
- Product/Business: UX impact, cost-benefit, timeline
|
||
|
||
Adapt depth to audience expertise.
|