name: pre-dev-task-breakdown
|
|
description: |
|
|
Gate 7: Implementation tasks - value-driven decomposition into working increments
|
|
that deliver measurable user value.
|
|
|
|
trigger: |
|
|
- PRD passed Gate 1 (required)
|
|
- TRD passed Gate 3 (required)
|
|
- All Large Track gates passed (if applicable)
|
|
- Ready to create sprint/iteration tasks
|
|
|
|
skip_when: |
|
|
- PRD or TRD not validated → complete earlier gates
|
|
- Tasks already exist → proceed to Subtask Creation
|
|
- Trivial change → direct implementation
|
|
|
|
sequence:
|
|
after: [pre-dev-trd-creation, pre-dev-dependency-map]
|
|
before: [pre-dev-subtask-creation, executing-plans]
|
|
---
|
|
|
|
# Task Breakdown - Value-Driven Decomposition
|
|
|
|
## Foundational Principle
|
|
|
|
**Every task must deliver working software that provides measurable user value.**
|
|
|
|
Creating technical-only or oversized tasks creates:
|
|
- Work that doesn't ship until "everything is done"
|
|
- Teams working on pieces that don't integrate
|
|
- No early validation of value or technical approach
|
|
- Waterfall development disguised as iterative process
|
|
|
|
**Tasks answer**: What working increment will be delivered?
|
|
**Tasks never answer**: How to implement that increment (that's Subtasks).
|
|
|
|
## When to Use This Skill
|
|
|
|
Use this skill when:
|
|
- PRD has passed Gate 1 validation (REQUIRED)
|
|
- TRD has passed Gate 3 validation (REQUIRED)
|
|
- Feature Map has passed Gate 2 validation (OPTIONAL - use if exists)
|
|
- API Design has passed Gate 4 validation (OPTIONAL - use if exists)
|
|
- Data Model has passed Gate 5 validation (OPTIONAL - use if exists)
|
|
- Dependency Map has passed Gate 6 validation (OPTIONAL - use if exists)
|
|
- About to break down work for sprints/iterations
|
|
- Tempted to create "Setup Infrastructure" as a task
|
|
- Asked to estimate or plan implementation work
|
|
- Before creating subtasks
|
|
|
|
## Mandatory Workflow
|
|
|
|
### Phase 1: Task Identification (Inputs Required)
|
|
|
|
**Required Inputs:**
|
|
1. **Approved PRD** (Gate 1 passed) - business requirements and priorities (REQUIRED - check `docs/pre-dev/<feature-name>/prd.md`)
|
|
2. **Approved TRD** (Gate 3 passed) - architecture patterns documented (REQUIRED - check `docs/pre-dev/<feature-name>/trd.md`)
|
|
|
|
**Optional Inputs (use if exists for richer context):**
|
|
3. **Approved Feature Map** (Gate 2 passed) - feature relationships mapped (check `docs/pre-dev/<feature-name>/feature-map.md`)
|
|
4. **Approved API Design** (Gate 4 passed) - contracts specified (check `docs/pre-dev/<feature-name>/api-design.md`)
|
|
5. **Approved Data Model** (Gate 5 passed) - data structures defined (check `docs/pre-dev/<feature-name>/data-model.md`)
|
|
6. **Approved Dependency Map** (Gate 6 passed) - tech stack locked (check `docs/pre-dev/<feature-name>/dependency-map.md`)
|
|
|
|
**Analysis:**
|
|
7. **Identify value streams** - what delivers user value first?
|
|
|
|
### Phase 2: Decomposition
|
|
For each TRD component or PRD feature:
|
|
1. **Define deliverable** - what working software ships?
|
|
2. **Set success criteria** - how do we know it's done?
|
|
3. **Map dependencies** - what must exist first?
|
|
4. **Estimate effort** - T-shirt size (S/M/L/XL, max is XL = 2 weeks)
|
|
5. **Plan testing** - how will we verify it works?
|
|
6. **Identify risks** - what could go wrong?
|
|
|
|
### Phase 3: Gate 7 Validation
|
|
**MANDATORY CHECKPOINT** - Must pass before proceeding to Subtasks:
|
|
- [ ] All TRD components covered by tasks
|
|
- [ ] Every task delivers working software
|
|
- [ ] Each task has measurable success criteria
|
|
- [ ] Dependencies are correctly mapped
|
|
- [ ] No task exceeds 2 weeks effort (XL max)
|
|
- [ ] Testing strategy defined for each task
|
|
- [ ] Risks identified with mitigations
|
|
- [ ] Delivery sequence optimizes value
|
|
|
|
## Explicit Rules
|
|
|
|
### ✅ DO Include in Tasks
|
|
- Task ID, title, type (Foundation/Feature/Integration/Polish)
|
|
- Deliverable: What working software ships?
|
|
- User value: What can users do after this?
|
|
- Technical value: What does this enable?
|
|
- Success criteria (testable, measurable)
|
|
- Dependencies (blocks/requires/optional)
|
|
- Effort estimate (S/M/L/XL with points)
|
|
- Testing strategy (unit/integration/e2e)
|
|
- Risk identification with mitigations
|
|
- Definition of Done checklist
|
|
|
|
### ❌ NEVER Include in Tasks
|
|
- Implementation details (file paths, code examples)
|
|
- Step-by-step instructions (those go in subtasks)
|
|
- Technical-only tasks with no user value
|
|
- Tasks exceeding 2 weeks effort (break them down)
|
|
- Vague success criteria ("improve performance")
|
|
- Missing dependency information
|
|
- Undefined testing approach
|
|
|
|
### Task Sizing Rules
|
|
1. **Small (S)**: 1-3 points, 1-3 days, single component
|
|
2. **Medium (M)**: 5-8 points, 3-5 days, few dependencies
|
|
3. **Large (L)**: 13 points, 1-2 weeks, multiple components
|
|
4. **XL (over 2 weeks)**: BREAK IT DOWN - too large to be atomic
|
|
|
|
### Value Delivery Rules
|
|
1. **Foundation tasks** enable other work (database setup, core services)
|
|
2. **Feature tasks** deliver user-facing capabilities
|
|
3. **Integration tasks** connect to external systems
|
|
4. **Polish tasks** optimize or enhance (nice-to-have)
|
|
|
|
## Rationalization Table
|
|
|
|
| Excuse | Reality |
|
|
|--------|---------|
|
|
| "This 3-week task is fine" | Tasks >2 weeks hide complexity. Break it down. |
|
|
| "Setup tasks don't need value" | Setup enables value. Define what it enables. |
|
|
| "Success criteria are obvious" | Obvious to you ≠ testable. Document explicitly. |
|
|
| "Dependencies will be clear later" | Later is too late. Map them now. |
|
|
| "We don't need detailed estimates" | Without estimates, no planning possible. Size them. |
|
|
| "Technical tasks can skip user value" | Even infrastructure enables users. Define the connection. |
|
|
| "Testing strategy can be decided during" | Testing affects design. Plan it upfront. |
|
|
| "Risks aren't relevant at task level" | Risks compound across tasks. Identify them early. |
|
|
| "DoD is the same for all tasks" | Different tasks need different criteria. Specify. |
|
|
| "We can combine multiple features" | Combining hides value delivery. Keep tasks focused. |
|
|
|
|
## Red Flags - STOP
|
|
|
|
If you catch yourself writing any of these in a task, **STOP**:
|
|
|
|
- Task estimates over 2 weeks
|
|
- Tasks named "Setup X" without defining what X enables
|
|
- Success criteria like "works" or "complete" (not measurable)
|
|
- No dependencies listed (every task depends on something)
|
|
- No testing strategy (how will you verify?)
|
|
- "Technical debt" as a task type (debt reduction must deliver value)
|
|
- Vague deliverables ("improve", "optimize", "refactor")
|
|
- Missing Definition of Done
|
|
|
|
**When you catch yourself**: Refine the task until it's concrete, valuable, and testable.
|
|
|
|
## Gate 7 Validation Checklist
|
|
|
|
Before proceeding to Subtasks, verify:
|
|
|
|
**Task Completeness**:
|
|
- [ ] All TRD components have tasks covering them
|
|
- [ ] All PRD features have tasks delivering them
|
|
- [ ] Each task is appropriately sized (no XL+)
|
|
- [ ] Task boundaries are clear and logical
|
|
|
|
**Delivery Value**:
|
|
- [ ] Every task delivers working software
|
|
- [ ] User value is explicit (even for foundation)
|
|
- [ ] Technical value is clear (what it enables)
|
|
- [ ] Sequence optimizes value delivery
|
|
|
|
**Technical Clarity**:
|
|
- [ ] Success criteria are measurable and testable
|
|
- [ ] Dependencies are correctly mapped (blocks/requires)
|
|
- [ ] Testing approach is defined (unit/integration/e2e)
|
|
- [ ] Definition of Done is comprehensive
|
|
|
|
**Team Readiness**:
|
|
- [ ] Skills required match team capabilities
|
|
- [ ] Effort estimates are realistic (validated by similar past work)
|
|
- [ ] Capacity is available or planned
|
|
- [ ] Handoffs are minimized
|
|
|
|
**Risk Management**:
|
|
- [ ] Risks identified for each task
|
|
- [ ] Mitigations are defined
|
|
- [ ] High-risk tasks scheduled early
|
|
- [ ] Fallback plans exist
|
|
|
|
**Gate Result**:
|
|
- ✅ **PASS**: All checkboxes checked → Proceed to Subtasks (`pre-dev-subtask-creation`)
|
|
- ⚠️ **CONDITIONAL**: Refine oversized/vague tasks → Re-validate
|
|
- ❌ **FAIL**: Too many issues → Re-decompose
|
|
|
|
## Common Violations and Fixes
|
|
|
|
### Violation 1: Technical-Only Tasks
|
|
❌ **Wrong**:
|
|
```markdown
|
|
## T-001: Setup PostgreSQL Database
|
|
- Install PostgreSQL 16
|
|
- Configure connection pooling
|
|
- Create initial schema
|
|
```
|
|
|
|
✅ **Correct**:
|
|
```markdown
|
|
## T-001: User Data Persistence Foundation
|
|
|
|
### Deliverable
|
|
Working database layer that persists user accounts and supports authentication queries with <100ms latency.
|
|
|
|
### User Value
|
|
Enables user registration and login (T-002, T-003 depend on this).
|
|
|
|
### Technical Value
|
|
- Foundation for all data persistence
|
|
- Multi-tenant isolation strategy implemented
|
|
- Performance baseline established
|
|
|
|
### Success Criteria
|
|
- [ ] Users table created with multi-tenant schema
|
|
- [ ] Connection pooling configured (min 5, max 50 connections)
|
|
- [ ] Query performance <100ms for auth queries (verified with test data)
|
|
- [ ] Migrations framework operational
|
|
- [ ] Rollback procedures tested
|
|
|
|
### Dependencies
|
|
- **Blocks**: T-002 (Registration), T-003 (Login), T-004 (Permissions)
|
|
- **Requires**: Infrastructure (networking, compute)
|
|
- **Optional**: None
|
|
|
|
### Effort: Medium (M) - 5 points, 3-5 days
|
|
### Testing: Integration tests for queries, performance benchmarks
|
|
```
|
|
|
|
### Violation 2: Oversized Tasks
|
|
❌ **Wrong**:
|
|
```markdown
|
|
## T-005: Complete User Management System
|
|
- Registration, login, logout
|
|
- Profile management
|
|
- Password reset
|
|
- Email verification
|
|
- Two-factor authentication
|
|
- Session management
|
|
- Permissions system
|
|
|
|
Estimate: 6 weeks
|
|
```
|
|
|
|
✅ **Correct** (broken into multiple tasks):
|
|
```markdown
|
|
## T-005: Basic Authentication (Register + Login)
|
|
- Deliverable: Users can create accounts and log in with JWT tokens
|
|
- User Value: Access to personalized features
|
|
- Effort: Large (L) - 13 points, 1-2 weeks
|
|
- Dependencies: Requires T-001 (Database)
|
|
|
|
## T-006: Password Management (Reset + Email)
|
|
- Deliverable: Users can reset forgotten passwords via email
|
|
- User Value: Account recovery without support tickets
|
|
- Effort: Medium (M) - 8 points, 3-5 days
|
|
- Dependencies: Requires T-005, Email service configured
|
|
|
|
## T-007: Two-Factor Authentication
|
|
- Deliverable: Users can enable 2FA with TOTP
|
|
- User Value: Enhanced account security
|
|
- Effort: Medium (M) - 8 points, 3-5 days
|
|
- Dependencies: Requires T-005
|
|
|
|
## T-008: Permissions System
|
|
- Deliverable: Role-based access control operational
|
|
- User Value: Admin can assign roles, users have appropriate access
|
|
- Effort: Large (L) - 13 points, 1-2 weeks
|
|
- Dependencies: Requires T-005
|
|
```
|
|
|
|
### Violation 3: Vague Success Criteria
|
|
❌ **Wrong**:
|
|
```markdown
|
|
Success Criteria:
|
|
- [ ] Feature works
|
|
- [ ] Tests pass
|
|
- [ ] Code reviewed
|
|
```
|
|
|
|
✅ **Correct**:
|
|
```markdown
|
|
Success Criteria:
|
|
Functional:
|
|
- [ ] Users can upload files up to 100MB
|
|
- [ ] Supported formats: JPEG, PNG, PDF, DOCX
|
|
- [ ] Files stored with unique IDs, retrievable via API
|
|
- [ ] Upload progress shown to user
|
|
|
|
Technical:
|
|
- [ ] API response time <2s for uploads <10MB
|
|
- [ ] Files encrypted at rest with KMS
|
|
- [ ] Virus scanning completes before storage
|
|
|
|
Operational:
|
|
- [ ] Monitoring: Upload success rate >99.5%
|
|
- [ ] Logging: All upload attempts logged with user_id
|
|
- [ ] Alerts: Notify if success rate drops below 95%
|
|
|
|
Quality:
|
|
- [ ] Unit tests: 90%+ coverage for upload logic
|
|
- [ ] Integration tests: End-to-end upload scenarios
|
|
- [ ] Security: OWASP file upload best practices followed
|
|
```
|
|
|
|
## Task Template
|
|
|
|
Use this template for every task:
|
|
|
|
```markdown
|
|
## T-[XXX]: [Task Title - What It Delivers]
|
|
|
|
### Deliverable
|
|
[One sentence: What working software ships?]
|
|
|
|
### Scope
|
|
**Includes**:
|
|
- [Specific capability 1]
|
|
- [Specific capability 2]
|
|
- [Specific capability 3]
|
|
|
|
**Excludes** (future tasks):
|
|
- [Out of scope item 1] (T-YYY)
|
|
- [Out of scope item 2] (T-ZZZ)
|
|
|
|
### Success Criteria
|
|
- [ ] [Testable criterion 1]
|
|
- [ ] [Testable criterion 2]
|
|
- [ ] [Testable criterion 3]
|
|
|
|
### User Value
|
|
[What can users do after this that they couldn't before?]
|
|
|
|
### Technical Value
|
|
[What does this enable? What other tasks does this unblock?]
|
|
|
|
### Technical Components
|
|
From TRD:
|
|
- [Component 1]
|
|
- [Component 2]
|
|
|
|
From Dependencies:
|
|
- [Package/service 1]
|
|
- [Package/service 2]
|
|
|
|
### Dependencies
|
|
- **Blocks**: [Tasks that need this] (T-AAA, T-BBB)
|
|
- **Requires**: [Tasks that must complete first] (T-CCC)
|
|
- **Optional**: [Nice-to-haves] (T-DDD)
|
|
|
|
### Effort Estimate
|
|
- **Size**: [S/M/L/XL]
|
|
- **Points**: [1-3 / 5-8 / 13 / 21]
|
|
- **Duration**: [1-3 days / 3-5 days / 1-2 weeks]
|
|
- **Team**: [Backend / Frontend / Full-stack / etc.]
|
|
|
|
### Risks
|
|
**Risk 1: [Description]**
|
|
- Impact: [High/Medium/Low]
|
|
- Probability: [High/Medium/Low]
|
|
- Mitigation: [How we'll address it]
|
|
- Fallback: [Plan B if mitigation fails]
|
|
|
|
### Testing Strategy
|
|
- **Unit Tests**: [What logic to test]
|
|
- **Integration Tests**: [What APIs/components to test together]
|
|
- **E2E Tests**: [What user flows to test]
|
|
- **Performance Tests**: [What to benchmark]
|
|
- **Security Tests**: [What threats to validate against]
|
|
|
|
### Definition of Done
|
|
- [ ] Code complete and peer reviewed
|
|
- [ ] All tests passing (unit + integration + e2e)
|
|
- [ ] Documentation updated (API docs, README, etc.)
|
|
- [ ] Security scan clean (no high/critical issues)
|
|
- [ ] Performance targets met (benchmarks run)
|
|
- [ ] Deployed to staging environment
|
|
- [ ] Product owner acceptance received
|
|
- [ ] Monitoring/logging configured
|
|
```
|
|
|
|
## Delivery Sequencing
|
|
|
|
Optimize task order for value:
|
|
|
|
```yaml
|
|
Sprint 1 - Foundation:
|
|
Goal: Enable core workflows
|
|
Tasks:
|
|
- T-001: Database foundation (blocks all)
|
|
- T-002: Auth foundation (start, high value)
|
|
|
|
Sprint 2 - Core Features:
|
|
Goal: Ship minimum viable feature
|
|
Tasks:
|
|
- T-002: Auth foundation (complete)
|
|
- T-005: User dashboard (depends on T-002)
|
|
- T-010: Basic API endpoints (high value)
|
|
|
|
Sprint 3 - Enhancements:
|
|
Goal: Polish and extend
|
|
Tasks:
|
|
- T-006: Password reset (medium value)
|
|
- T-011: Advanced search (nice-to-have)
|
|
- T-015: Performance optimization (polish)
|
|
|
|
Critical Path: T-001 → T-002 → T-005 → T-010
|
|
Parallel Work: After T-001, T-003 and T-004 can run parallel to T-002
|
|
```
|
|
|
|
## Anti-Patterns to Avoid
|
|
|
|
❌ **Technical Debt Tasks**: "Refactor authentication" (no user value)
|
|
❌ **Giant Tasks**: 3+ week efforts (break them down)
|
|
❌ **Vague Tasks**: "Improve performance" (not measurable)
|
|
❌ **Sequential Bottlenecks**: Everything depends on one task
|
|
❌ **Missing Value**: Tasks that don't ship working software
|
|
|
|
✅ **Good Task Names**:
|
|
- "Users can register and log in with email" (clear value)
|
|
- "API responds in <500ms for 95th percentile" (measurable)
|
|
- "Admin dashboard shows real-time metrics" (working software)
|
|
|
|
## Confidence Scoring
|
|
|
|
Use this to adjust your interaction with the user:
|
|
|
|
```yaml
|
|
Confidence Factors:
|
|
Task Decomposition: [0-30]
|
|
- All tasks appropriately sized: 30
|
|
- Most tasks well-scoped: 20
|
|
- Tasks too large or vague: 10
|
|
|
|
Value Clarity: [0-25]
|
|
- Every task delivers working software: 25
|
|
- Most tasks have clear value: 15
|
|
- Value connections unclear: 5
|
|
|
|
Dependency Mapping: [0-25]
|
|
- All dependencies documented: 25
|
|
- Most dependencies clear: 15
|
|
- Dependencies ambiguous: 5
|
|
|
|
Estimation Quality: [0-20]
|
|
- Estimates based on past work: 20
|
|
- Reasonable educated guesses: 12
|
|
- Wild speculation: 5
|
|
|
|
Total: [0-100]
|
|
|
|
Action:
|
|
80+: Generate complete task breakdown autonomously
|
|
50-79: Present sizing options and sequences
|
|
<50: Ask about team velocity and complexity
|
|
```
|
|
|
|
## Output Location
|
|
|
|
**Always output to**: `docs/pre-development/tasks/tasks-[feature-name].md`
|
|
|
|
## After Task Breakdown Approval
|
|
|
|
1. ✅ Tasks become sprint backlog
|
|
2. 🎯 Use tasks as input for atomic subtasks (next phase: `pre-dev-subtask-creation`)
|
|
3. 📊 Track progress per task (not per subtask)
|
|
4. 🚫 No implementation yet - that's in subtasks
|
|
|
|
## Quality Self-Check
|
|
|
|
Before declaring task breakdown complete, verify:
|
|
- [ ] Every task delivers working software (not just "progress")
|
|
- [ ] All tasks have measurable success criteria
|
|
- [ ] Dependencies are mapped (blocks/requires/optional)
|
|
- [ ] Effort estimates are realistic (S/M/L/XL, no >2 weeks)
|
|
- [ ] Testing strategy defined for each task
|
|
- [ ] Risks identified with mitigations
|
|
- [ ] Definition of Done is comprehensive for each
|
|
- [ ] Delivery sequence optimizes value (high-value tasks early)
|
|
- [ ] No technical-only tasks without user connection
|
|
- [ ] Gate 7 validation checklist 100% complete
|
|
|
|
## The Bottom Line
|
|
|
|
**If you created tasks that don't deliver working software, rewrite them.**
|
|
|
|
Tasks are not technical activities. Tasks are working increments.
|
|
|
|
"Setup database" is not a task. "User data persists correctly" is a task.
|
|
"Implement OAuth" is not a task. "Users can log in with Google" is a task.
|
|
"Write tests" is not a task. Tests are part of Definition of Done for other tasks.
|
|
|
|
Every task must answer: **"What working software can I demo to users?"**
|
|
|
|
If you can't demo it, it's not a task. It's subtask implementation detail.
|
|
|
|
**Deliver value. Ship working software. Make tasks demoable.**
|