description: sprint-plan
|
||||
allowed-tools: Bash, Read, Edit, Write, Glob, Grep
|
||||
---
|
||||
|
||||
# sprint-plan
|
||||
|
||||
Intelligent sprint planning with capacity-based story selection, dependency validation, and velocity forecasting.
|
||||
|
||||
## Prompt
|
||||
|
||||
ROLE: Sprint Planner
|
||||
|
||||
OBJECTIVE
|
||||
Create a data-driven sprint plan by analyzing backlog priorities, agent capacity, historical velocity, and dependency chains. Ensure realistic commitments that respect WIP limits and Definition of Ready criteria.
|
||||
|
||||
INPUTS
|
||||
- SPRINT=<sprint-id> — Sprint identifier (e.g., "Sprint-42", "2025-W43")
|
||||
- DURATION=<days> — Sprint duration in days (default: 10, typical 2-week sprint)
|
||||
- AGENTS=<agent-list> — Comma-separated agents to plan for (default: all active agents)
|
||||
- MODE=<suggest|commit> — "suggest" shows preview, "commit" updates status.json (default: suggest)
|
||||
- FOCUS_EPIC=<epic-id> — Optionally focus on specific epic
|
||||
|
||||
KNOWLEDGE LOADING (run first, silently)
|
||||
Read in order:
|
||||
1. docs/09-agents/status.json — Current state, WIP, agent assignments
|
||||
2. docs/09-agents/bus/log.jsonl — Historical velocity data (completed stories with timestamps)
|
||||
3. docs/08-project/backlog.md — Priority order for stories
|
||||
4. docs/08-project/roadmap.md — Strategic priorities
|
||||
5. docs/08-project/milestones.md — Deadline constraints
|
||||
6. docs/05-epics/*.md — Epic priorities and goals
|
||||
7. docs/06-stories/**/US-*.md — Story details, AC, estimates
|
||||
8. docs/03-decisions/adr-*.md — Recent ADRs that might spawn stories
|
||||
|
||||
SPRINT PLANNING PHASES
|
||||
|
||||
## Phase 1: Current State Analysis
|
||||
|
||||
### Agent Capacity Assessment
|
||||
```bash
|
||||
# Calculate available capacity per agent
|
||||
|
||||
echo "=== Current Agent Status ==="
|
||||
|
||||
for agent in AG-UI AG-API AG-CI AG-DEVOPS MENTOR; do
|
||||
in_progress=$(jq -r ".stories | to_entries[] | select(.value.owner==\"$agent\") | select(.value.status==\"in-progress\") | .key" docs/09-agents/status.json | wc -l)
|
||||
in_review=$(jq -r ".stories | to_entries[] | select(.value.owner==\"$agent\") | select(.value.status==\"in-review\") | .key" docs/09-agents/status.json | wc -l)
|
||||
|
||||
# WIP limit is 2
|
||||
available=$((2 - in_progress))
|
||||
|
||||
echo "$agent: $in_progress in-progress, $in_review in-review → $available slots available"
|
||||
|
||||
# If agent has in-review stories, they might free up soon
|
||||
if [ "$in_review" -gt 0 ]; then
|
||||
echo " ⚠️ $in_review stories in review may complete soon (add conditional capacity)"
|
||||
fi
|
||||
done
|
||||
```
|
||||
|
||||
### Backlog Health Check
|
||||
```bash
|
||||
# Count ready stories (meet Definition of Ready)
|
||||
ready_count=$(jq -r '.stories | to_entries[] | select(.value.status=="ready") | .key' docs/09-agents/status.json | wc -l)
|
||||
|
||||
echo "Ready stories in backlog: $ready_count"
|
||||
|
||||
# Check for blocked stories that might unblock during sprint
|
||||
blocked_count=$(jq -r '.stories | to_entries[] | select(.value.status=="blocked") | .key' docs/09-agents/status.json | wc -l)
|
||||
|
||||
echo "Blocked stories (may unblock): $blocked_count"
|
||||
```
|
||||
|
||||
## Phase 2: Historical Velocity Calculation
|
||||
|
||||
### Calculate Team Velocity (last 3 sprints or 30 days)
|
||||
```bash
|
||||
# Parse bus/log.jsonl for completed stories with timestamps
|
||||
thirty_days_ago=$(date -u -d '30 days ago' +%Y-%m-%dT%H:%M:%S 2>/dev/null || date -u -v-30d +%Y-%m-%dT%H:%M:%S 2>/dev/null)
|
||||
|
||||
# Extract story completion events
|
||||
grep '"type":"status"' docs/09-agents/bus/log.jsonl | grep '"done"' | while read -r line; do
|
||||
ts=$(echo "$line" | jq -r '.ts')
|
||||
story=$(echo "$line" | jq -r '.story')
|
||||
|
||||
# Check if within last 30 days
|
||||
if [[ "$ts" > "$thirty_days_ago" ]]; then
|
||||
# Get story estimate
|
||||
estimate=$(jq -r ".stories[\"$story\"].estimate" docs/09-agents/status.json 2>/dev/null)
|
||||
echo "$story|$estimate|$ts"
|
||||
fi
|
||||
done > /tmp/completed_stories.txt
|
||||
|
||||
# Sum estimates (convert "0.5d", "1d", "2d" to numeric)
|
||||
total_days=0
|
||||
count=0
|
||||
|
||||
while IFS='|' read -r story estimate ts; do
|
||||
# Extract numeric value
|
||||
days=$(echo "$estimate" | grep -oE '[0-9.]+')
|
||||
total_days=$(echo "$total_days + $days" | bc)
|
||||
count=$((count + 1))
|
||||
done < /tmp/completed_stories.txt
|
||||
|
||||
if [ "$count" -gt 0 ]; then
|
||||
velocity=$(echo "scale=1; $total_days / 30 * ${DURATION:-10}" | bc)
|
||||
echo "Historical velocity: $total_days days completed in last 30 days"
|
||||
echo "Projected capacity for ${DURATION:-10}-day sprint: ${velocity} days"
|
||||
else
|
||||
echo "⚠️ No historical data. Using default capacity: 1 story per agent per sprint"
|
||||
velocity="N/A"
|
||||
fi
|
||||
```
|
||||
|
||||
### Agent-Specific Velocity
|
||||
```bash
|
||||
# Calculate velocity per agent (for more accurate planning)
|
||||
|
||||
for agent in AG-UI AG-API AG-CI AG-DEVOPS; do
|
||||
agent_total=0
|
||||
|
||||
while IFS='|' read -r story estimate ts; do
|
||||
owner=$(jq -r ".stories[\"$story\"].owner" docs/09-agents/status.json 2>/dev/null)
|
||||
|
||||
if [ "$owner" == "$agent" ]; then
|
||||
days=$(echo "$estimate" | grep -oE '[0-9.]+')
|
||||
agent_total=$(echo "$agent_total + $days" | bc)
|
||||
fi
|
||||
done < /tmp/completed_stories.txt
|
||||
|
||||
if [ $(echo "$agent_total > 0" | bc) -eq 1 ]; then
|
||||
agent_velocity=$(echo "scale=1; $agent_total / 30 * ${DURATION:-10}" | bc)
|
||||
echo "$agent velocity: ${agent_velocity} days per ${DURATION:-10}-day sprint"
|
||||
fi
|
||||
done
|
||||
```
|
||||
|
||||
## Phase 3: Story Selection & Prioritization
|
||||
|
||||
### Selection Criteria (in priority order)
|
||||
1. **Must be "ready" status** (Definition of Ready met)
|
||||
2. **Dependencies resolved** (all deps have status="done")
|
||||
3. **Backlog priority** (from backlog.md or roadmap.md)
|
||||
4. **Epic alignment** (if FOCUS_EPIC specified, prioritize that epic)
|
||||
5. **Milestone deadlines** (check milestones.md for urgent items)
|
||||
6. **Team capacity** (don't exceed calculated velocity)
|
||||
7. **Agent balance** (distribute work evenly across agents)
|
||||
|
||||
### Story Selection Algorithm
|
||||
```bash
|
||||
# Extract all ready stories
|
||||
jq -r '.stories | to_entries[] | select(.value.status=="ready") |
|
||||
"\(.key)|\(.value.owner)|\(.value.estimate)|\(.value.epic // \"none\")|\(.value.deps // [] | join(\",\"))"' \
|
||||
docs/09-agents/status.json > /tmp/ready_stories.txt
|
||||
|
||||
# Filter by dependencies (must be resolved)
|
||||
while IFS='|' read -r story owner estimate epic deps; do
|
||||
blocked=false
|
||||
|
||||
if [ -n "$deps" ]; then
|
||||
IFS=',' read -ra DEP_ARRAY <<< "$deps"
|
||||
for dep in "${DEP_ARRAY[@]}"; do
|
||||
dep_status=$(jq -r ".stories[\"$dep\"].status" docs/09-agents/status.json 2>/dev/null)
|
||||
if [ "$dep_status" != "done" ]; then
|
||||
blocked=true
|
||||
break
|
||||
fi
|
||||
done
|
||||
fi
|
||||
|
||||
# If not blocked, eligible for sprint
|
||||
if [ "$blocked" == "false" ]; then
|
||||
# Check if agent has capacity
|
||||
in_progress=$(jq -r ".stories | to_entries[] | select(.value.owner==\"$owner\") | select(.value.status==\"in-progress\") | .key" docs/09-agents/status.json | wc -l)
|
||||
|
||||
if [ "$in_progress" -lt 2 ]; then
|
||||
echo "$story|$owner|$estimate|$epic|eligible"
|
||||
else
|
||||
echo "$story|$owner|$estimate|$epic|waiting-for-capacity"
|
||||
fi
|
||||
else
|
||||
echo "$story|$owner|$estimate|$epic|blocked"
|
||||
fi
|
||||
done < /tmp/ready_stories.txt > /tmp/eligible_stories.txt
|
||||
```
|
||||
|
||||
### Backlog Priority Matching
|
||||
```bash
|
||||
# Read backlog.md to get priority order
|
||||
if [ -f docs/08-project/backlog.md ]; then
|
||||
# Extract story IDs in order of appearance
|
||||
grep -oE 'US-[0-9]{4}' docs/08-project/backlog.md > /tmp/backlog_order.txt
|
||||
|
||||
# Match with eligible stories
|
||||
while read -r story_id; do
|
||||
grep "^${story_id}|" /tmp/eligible_stories.txt
|
||||
done < /tmp/backlog_order.txt > /tmp/prioritized_stories.txt
|
||||
else
|
||||
# No backlog.md, use status.json order
|
||||
cat /tmp/eligible_stories.txt > /tmp/prioritized_stories.txt
|
||||
fi
|
||||
```
|
||||
|
||||
### Capacity-Based Selection
|
||||
```bash
|
||||
# Select stories until capacity is reached
|
||||
capacity_days=${velocity:-10} # Default to sprint duration if no historical data
|
||||
committed_days=0
|
||||
|
||||
echo "=== Sprint Story Selection ==="
|
||||
echo "Target capacity: ${capacity_days} days"
|
||||
echo ""
|
||||
|
||||
while IFS='|' read -r story owner estimate epic status; do
|
||||
# Extract numeric estimate
|
||||
days=$(echo "$estimate" | grep -oE '[0-9.]+' || echo "1")
|
||||
|
||||
# Check if adding this story exceeds capacity
|
||||
new_total=$(echo "$committed_days + $days" | bc)
|
||||
|
||||
if [ $(echo "$new_total <= $capacity_days" | bc) -eq 1 ]; then
|
||||
echo "✅ $story ($estimate) - $owner - Epic: $epic"
|
||||
committed_days=$new_total
|
||||
else
|
||||
echo "⚠️ Capacity reached. Remaining stories in backlog:"
|
||||
echo " $story ($estimate) - $owner - Epic: $epic [deferred]"
|
||||
fi
|
||||
done < /tmp/prioritized_stories.txt
|
||||
```
|
||||
|
||||
## Phase 4: Risk Assessment
|
||||
|
||||
### Dependency Chain Analysis
|
||||
```bash
|
||||
# For each selected story, check dependency depth
|
||||
echo ""
|
||||
echo "=== Dependency Risk Assessment ==="
|
||||
|
||||
# Warn if selected stories have complex dependency chains
|
||||
grep "^✅" /tmp/sprint_selection.txt | while read -r line; do
|
||||
story=$(echo "$line" | grep -oE 'US-[0-9]{4}')
|
||||
|
||||
# Check if other stories depend on this one
|
||||
dependents=$(jq -r ".stories | to_entries[] | select(.value.deps) | select(.value.deps | index(\"$story\")) | .key" docs/09-agents/status.json)
|
||||
|
||||
if [ -n "$dependents" ]; then
|
||||
dep_count=$(echo "$dependents" | wc -l)
|
||||
echo "⚠️ $story is blocking $dep_count other stories: $dependents"
|
||||
echo " → Prioritize completion to unblock others"
|
||||
fi
|
||||
done
|
||||
```
|
||||
|
||||
### Cross-Agent Coordination Check
|
||||
```bash
|
||||
# Identify stories requiring AG-API + AG-UI coordination
|
||||
echo ""
|
||||
echo "=== Cross-Agent Coordination ==="
|
||||
|
||||
ag_ui_stories=$(grep "^✅" /tmp/sprint_selection.txt | grep "AG-UI" | grep -oE 'US-[0-9]{4}')
|
||||
ag_api_stories=$(grep "^✅" /tmp/sprint_selection.txt | grep "AG-API" | grep -oE 'US-[0-9]{4}')
|
||||
|
||||
if [ -n "$ag_ui_stories" ] && [ -n "$ag_api_stories" ]; then
|
||||
echo "Sprint includes both AG-UI and AG-API work:"
|
||||
echo "AG-UI stories: $ag_ui_stories"
|
||||
echo "AG-API stories: $ag_api_stories"
|
||||
echo ""
|
||||
echo "💡 Tip: Sequence AG-API stories first to avoid blocking AG-UI"
|
||||
fi
|
||||
```
|
||||
|
||||
### Stale Epic Check
|
||||
```bash
|
||||
# Warn if sprint is mixing old and new epics
|
||||
echo ""
|
||||
echo "=== Epic Freshness Check ==="
|
||||
|
||||
grep "^✅" /tmp/sprint_selection.txt | grep -oE 'Epic: EP-[0-9]{4}' | sort -u | while read -r epic_line; do
|
||||
epic=$(echo "$epic_line" | grep -oE 'EP-[0-9]{4}')
|
||||
|
||||
if [ -f "docs/05-epics/${epic}.md" ]; then
|
||||
created=$(grep "^created:" "docs/05-epics/${epic}.md" | head -n1 | awk '{print $2}')
|
||||
echo "$epic created on $created"
|
||||
fi
|
||||
done
|
||||
```
|
||||
|
||||
## Phase 5: Sprint Commitment (if MODE=commit)
|
||||
|
||||
If MODE=commit, update status.json with sprint metadata:
|
||||
|
||||
```bash
|
||||
# Add sprint field to selected stories
|
||||
jq '.stories |= with_entries(
|
||||
if (.key | IN("US-0042", "US-0043", "US-0045")) then
|
||||
.value.sprint = "Sprint-42" |
|
||||
.value.sprint_committed = "2025-10-22T00:00:00Z"
|
||||
else
|
||||
.
|
||||
end
|
||||
)' docs/09-agents/status.json > /tmp/status_updated.json
|
||||
|
||||
# Diff preview
|
||||
diff -u docs/09-agents/status.json /tmp/status_updated.json
|
||||
|
||||
# Ask for confirmation
|
||||
echo ""
|
||||
echo "Update status.json with sprint commitments? (YES/NO)"
|
||||
# Wait for user input
|
||||
```
|
||||
|
||||
### Create Sprint Milestone
|
||||
```bash
|
||||
# Update milestones.md with sprint
|
||||
sprint_end=$(date -u -d '+10 days' +%Y-%m-%d 2>/dev/null || date -u -v+10d +%Y-%m-%d 2>/dev/null)
|
||||
|
||||
cat >> docs/08-project/milestones.md <<EOF
|
||||
|
||||
## ${SPRINT:-Sprint} (${sprint_end})
|
||||
|
||||
**Stories**: ${committed_count} stories, ${committed_days} estimated days
|
||||
**Team Capacity**: ${velocity} days (based on historical velocity)
|
||||
|
||||
**Committed Stories**:
|
||||
$(grep "^✅" /tmp/sprint_selection.txt)
|
||||
|
||||
**Sprint Goals**:
|
||||
- [Fill in sprint goals based on epic alignment]
|
||||
|
||||
**Risks**:
|
||||
- [Identify from dependency and coordination analysis]
|
||||
|
||||
**Definition of Done**:
|
||||
- All stories merged to main
|
||||
- CI passing
|
||||
- Documentation updated
|
||||
- Demo prepared
|
||||
|
||||
EOF
|
||||
```
|
||||
|
||||
### Bus Message
|
||||
```bash
|
||||
# Append sprint planning bus message
|
||||
cat >> docs/09-agents/bus/log.jsonl <<EOF
|
||||
{"ts":"$(date -u +%Y-%m-%dT%H:%M:%S)Z","from":"EPIC-PLANNER","type":"sprint-planned","text":"${SPRINT:-Sprint} planned: ${committed_count} stories, ${committed_days} days estimated, ends ${sprint_end}"}
|
||||
EOF
|
||||
```
|
||||
|
||||
OUTPUT FORMAT
|
||||
|
||||
```
|
||||
📅 Sprint Planning Report
|
||||
=========================
|
||||
Sprint: ${SPRINT}
|
||||
Duration: ${DURATION} days
|
||||
Mode: ${MODE}
|
||||
Generated: <timestamp>
|
||||
|
||||
📊 CAPACITY ANALYSIS
|
||||
--------------------
|
||||
Historical Velocity (last 30 days):
|
||||
- Team: ${velocity} days per ${DURATION}-day sprint
|
||||
- AG-UI: X days
|
||||
- AG-API: X days
|
||||
- AG-CI: X days
|
||||
- AG-DEVOPS: X days
|
||||
|
||||
Current Agent Status:
|
||||
AG-UI: 1/2 slots filled (1 available)
|
||||
AG-API: 2/2 slots filled (at capacity, but 1 in review)
|
||||
AG-CI: 0/2 slots filled (2 available)
|
||||
AG-DEVOPS: 1/2 slots filled (1 available)
|
||||
|
||||
Total Available Capacity: ~X days
|
||||
|
||||
📋 BACKLOG STATUS
|
||||
-----------------
|
||||
Ready stories: X
|
||||
Blocked stories: X (may unblock during sprint)
|
||||
Eligible for sprint: X
|
||||
|
||||
✅ RECOMMENDED SPRINT COMMITMENT
|
||||
--------------------------------
|
||||
Committed: X stories, Y.Z estimated days (Y% of capacity)
|
||||
|
||||
1. US-0042 (1d) - AG-UI - Epic: EP-0010 [Priority: High]
|
||||
"User login form with validation"
|
||||
Dependencies: None ✅
|
||||
Risk: None
|
||||
|
||||
2. US-0043 (0.5d) - AG-API - Epic: EP-0010 [Priority: High]
|
||||
"POST /auth/login endpoint"
|
||||
Dependencies: None ✅
|
||||
Risk: Blocks US-0042 → Schedule first ⚠️
|
||||
|
||||
3. US-0045 (2d) - AG-UI - Epic: EP-0011 [Priority: Medium]
|
||||
"User profile page"
|
||||
Dependencies: US-0044 (done) ✅
|
||||
Risk: None
|
||||
|
||||
4. US-0050 (1d) - AG-CI - Epic: EP-0012 [Priority: Medium]
|
||||
"Add E2E tests for auth flow"
|
||||
Dependencies: US-0042, US-0043 (both in this sprint) ⚠️
|
||||
Risk: Should be done AFTER US-0042 and US-0043 complete
|
||||
|
||||
⚠️ DEFERRED (capacity reached)
|
||||
-------------------------------
|
||||
5. US-0055 (1d) - AG-API - Epic: EP-0013
|
||||
"GET /user/settings endpoint"
|
||||
→ Move to next sprint or pick up if capacity frees up
|
||||
|
||||
🎯 SPRINT GOALS
|
||||
---------------
|
||||
(Based on epic distribution)
|
||||
1. Complete core authentication (EP-0010): 3 stories
|
||||
2. User profile foundation (EP-0011): 1 story
|
||||
3. Test coverage for auth (EP-0012): 1 story
|
||||
|
||||
⚠️ RISKS & DEPENDENCIES
|
||||
------------------------
|
||||
1. Cross-agent coordination required:
|
||||
- AG-API must complete US-0043 before AG-UI can finish US-0042
|
||||
- Suggest: AG-API prioritizes US-0043 in first 2 days
|
||||
|
||||
2. Test story (US-0050) depends on 2 sprint stories:
|
||||
- Schedule for end of sprint after US-0042 and US-0043 are done
|
||||
|
||||
3. AG-API at capacity:
|
||||
- Has 1 story in review (US-0038) likely to complete soon
|
||||
- If US-0038 completes early, can pick up deferred US-0055
|
||||
|
||||
💡 RECOMMENDATIONS
|
||||
------------------
|
||||
1. Sequence stories: US-0043 (AG-API) → US-0042 (AG-UI) → US-0050 (AG-CI)
|
||||
2. Daily standup focus: AG-API unblocking AG-UI (check /blockers)
|
||||
3. Mid-sprint checkpoint: Day 5 - assess if US-0055 can be added
|
||||
4. End-of-sprint: Run /AgileFlow:velocity to update historical data
|
||||
|
||||
📅 SPRINT TIMELINE
|
||||
------------------
|
||||
Start: <today>
|
||||
End: <sprint_end>
|
||||
Demo: <sprint_end - 1 day>
|
||||
|
||||
Definition of Done:
|
||||
✅ All stories merged to main
|
||||
✅ CI passing on main
|
||||
✅ Documentation updated
|
||||
✅ Demo prepared for stakeholders
|
||||
|
||||
Next Steps:
|
||||
${MODE == "suggest" && "1. Review commitment and run /AgileFlow:sprint-plan MODE=commit to finalize"}
|
||||
${MODE == "commit" && "1. ✅ Sprint committed! Stories updated in status.json"}
|
||||
2. Assign first stories: /AgileFlow:assign STORY=US-0043 (highest priority)
|
||||
3. Monitor progress: /AgileFlow:board
|
||||
4. Track blockers: /AgileFlow:blockers
|
||||
5. Sync to external systems: /AgileFlow:github-sync or /AgileFlow:notion
|
||||
```
|
||||
|
||||
RULES
|
||||
- Always calculate historical velocity before planning
|
||||
- Respect WIP limits (max 2 per agent)
|
||||
- Validate dependencies are resolved
|
||||
- Prioritize by backlog order, milestones, epic goals
|
||||
- Show diff before committing changes (MODE=commit)
|
||||
- Provide sequencing recommendations for dependent stories
|
||||
- Warn about cross-agent coordination needs
|
||||
- Suggest concrete next commands
|
||||
|
||||
FOLLOW-UP QUESTIONS
|
||||
After displaying plan, ask:
|
||||
- "Does this sprint commitment look reasonable?"
|
||||
- "Should I commit this plan (update status.json and milestones.md)?"
|
||||
- "Any stories you'd like to add/remove?"
|
||||