Behavior-Over-Time Graphs
When to Use This Skill
Use behavior-over-time (BOT) graphs when:
- Predicting future states: "What will customer count be in 6 months?"
- Comparing scenarios: "With intervention vs without intervention"
- Communicating urgency: "Look how fast debt is growing!"
- Demonstrating time-to-crisis: "We have 14 months before capacity saturated"
- Validating models: Overlay actual vs predicted behavior
- Explaining delays: "Why solutions take 3 months to show results"
Don't use BOT graphs when:
- You don't know the structure yet → Start with causal loop diagram (CLD)
- You need to show feedback loops → Use CLD with polarity markers
- You want current state only (no trajectory) → Use stock-flow diagram
- Data too uncertain to plot → Use qualitative archetype analysis
- Audience needs WHY not WHEN → Use CLD to show causal logic
Key insight: BOT graphs answer "What happens over time?" with concrete numbers and dates. Use them AFTER you've mapped structure (CLD) and calculated values (stock-flow), to communicate dynamics visually.
The 7-Step Construction Process
Build BOT graphs systematically. Never jump to the final graph without validating each step.
Step 1: Identify What to Plot (Stock vs Flow)
Rule: BOT graphs typically show STOCKS (accumulated quantities), not flows (rates).
Why: Stakeholders care about "How bad is the problem?" (stock level) more than "How fast is it changing?" (flow rate).
Test: Can you measure this at a single instant without reference to time?
- YES → Stock (plot it)
- NO → Flow (consider plotting the stock it affects instead)
Examples:
- ✅ Plot: Customer Count (stock)
- ❌ Not: Customer Acquisition Rate (flow) - unless specifically analyzing flow behavior
- ✅ Plot: Bug Backlog (stock)
- ❌ Not: Bug Arrival Rate (flow)
- ✅ Plot: Technical Debt Points (stock)
- ❌ Not: Debt Accumulation Rate (flow)
Exception: Plot flows when analyzing flow behavior itself (e.g., "Development Velocity over time")
Step 2: Determine Time Scale (Granularity and Range)
Two decisions: How fine-grained? How far forward?
Granularity (X-axis intervals):
- Hourly: Real-time monitoring, very fast dynamics
- Daily: Operational metrics (deployments, incidents)
- Weekly: Sprint-level analysis
- Monthly: Business metrics (MRR, customer count)
- Quarterly: Strategic planning
- Yearly: Long-term trends
Decision criteria:
- Match measurement frequency (if customers tracked monthly, use monthly)
- Show intervention timeframe (if intervention monthly, don't use yearly)
- Avoid unnecessary noise (daily SaaS revenue too volatile, use monthly)
Range (how far forward to project):
Rule of thumb: Show 2-3× the time constant of the system
Time constant (τ) = Time for system to reach ~63% of equilibrium (from stocks-and-flows-modeling)
Examples:
- Customer growth τ = 8 months → Plot 16-24 months
- Bug backlog τ = 2 weeks → Plot 4-6 weeks
- Technical debt τ = infinity (unbounded) → Plot until crisis or intervention
Practical:
- Show intervention point + outcome period (decide at month 3, show months 0-12)
- Include phase transitions (growth → crisis → stabilization)
- Don't over-extend (24 months for 2-week problem dilutes insight)
Step 3: Calculate Values (Using Stock-Flow Equations)
Never eyeball the curve. Calculate stock levels using formal equations from stocks-and-flows-modeling.
Standard formula:
Stock(t+1) = Stock(t) + Δt × (Inflow - Outflow)
Process:
- Identify initial condition: Stock(0) = ?
- Calculate flows for each time period
- Apply formula iteratively
- Verify units: Stock in [X], Flows in [X/time], Δt in [time]
- Validate: Does equilibrium match calculation? (Set Inflow = Outflow)
Example - Bug Backlog:
Backlog(0) = 50 bugs
Inflow = 30 bugs/month (constant)
Outflow = 0.8 × Velocity (bugs/month, stock-dependent)
Velocity = 40 points/sprint, 2 sprints/month
Month 0: 50 bugs
Month 1: 50 + (30 - 0.8×40×2) = 50 + (30 - 64) = 16 bugs
Month 2: 16 + (30 - 0.8×40×2) = -18 bugs → Floor at 0 bugs
Equilibrium: Inflow < Outflow, backlog drains to 0
Common mistake: Guessing values instead of calculating. If stakeholders question, you must defend with math.
Step 4: Select Graph Type
Decision tree:
Is the data continuous or discrete?
- Continuous (smooth accumulation) → Line graph ✓ (default)
- Discrete (step changes) → Step function
Do you want to emphasize magnitude?
- YES → Area chart (fills area under line)
- NO → Line graph
Are you comparing discrete time periods?
- YES → Bar chart
- NO → Line graph
Examples:
- Customer growth over time: Line graph (continuous accumulation)
- Headcount changes (hire whole people): Step function (discrete jumps)
- Quarterly revenue comparison: Bar chart (discrete periods)
- Technical debt accumulation: Area chart or Line (either works, area emphasizes magnitude)
Default: When unsure, use line graph. It's the most versatile and widely understood.
Step 5: Choose Scale (Y-Axis Range)
The 70-80% Rule: Maximum value in your data should occupy 70-80% of the Y-axis range.
Formula:
Y_max = Data_max / 0.75
Example:
- Data maximum: 60 debt points
- Y-axis max: 60 / 0.75 = 80 points ✓
Why 70-80%?
- Provides visual buffer (not cramped at top)
- Makes growth impactful (not tiny slope in vast space)
- Industry standard for clear visualization
Common mistakes:
- ❌ Y-axis = 120 when data max = 60 (only 50% occupied, wastes space)
- ❌ Y-axis = 65 when data max = 60 (92% occupied, cramped, hard to see trend)
- ✅ Y-axis = 80 when data max = 60 (75% occupied, perfect)
When to start Y-axis at non-zero:
- Use 0 baseline when showing absolute change (customer count growth 0 → 7,000)
- Use non-zero when showing small variations around large baseline (server uptime 98.5% → 99.2%)
- Warning: Non-zero baselines can mislead. If using, annotate clearly.
Logarithmic scale:
- Use when data spans multiple orders of magnitude (1 → 1,000 → 1,000,000)
- Use when exponential growth makes linear scale unreadable
- Always label "logarithmic scale" explicitly
Step 6: Add Annotations (Events, Phases, Thresholds)
Annotations reveal WHY the curve behaves the way it does.
Types of annotations:
1. Event markers (vertical lines at intervention points):
│
↓
[INTERVENTION]
- Product launch, infrastructure investment, policy change
- Mark the TIME of the decision/event
2. Phase labels (text for regions):
[GROWTH PHASE] [CRISIS] [STABILIZATION]
- Mark distinct system behaviors over time periods
3. Threshold lines (horizontal lines for critical values):
─────────────── Capacity Limit (100 customers/month)
─────────────── Crisis Threshold (200 bugs)
- Show when system crosses critical boundaries
4. Annotations density limit: Max 5-7 annotations per graph
- More than 7 → Cluttered, unreadable
- If you need more, split into multiple graphs
Placement:
- Events: Vertical line at X position, label above or below
- Phases: Text box or bracket spanning time period
- Thresholds: Horizontal line with label at end or middle
Priority: Annotate the 3 most important events/thresholds, not everything.
Step 7: Validate (Quality Checklist)
Before presenting any BOT graph, check:
✅ Units clearly labeled on both axes?
- Y-axis: "Technical Debt (story points)"
- X-axis: "Time (months)"
✅ Scale follows 70-80% rule?
- Data_max / Y_max between 0.70 and 0.80?
✅ Time range shows full story?
- Intervention point + enough time to see outcome?
- Shows equilibrium or steady state if system reaches it?
✅ Annotations clear and not cluttered?
- ≤7 annotations total?
- Labels don't overlap?
✅ Graph type appropriate for data?
- Continuous data → Line
- Discrete changes → Step function
- Time period comparison → Bar
✅ Readable at presentation size?
- Can you read axis labels from 10 feet away?
- Are data lines thick enough?
✅ Validated against stock-flow calculations?
- Do plotted values match your calculated spreadsheet?
- Did you verify equilibrium point?
✅ Comparison method clear (if multiple scenarios)?
- Different line styles (solid vs dashed)?
- Legend shows which line is which?
If any check fails, FIX before presenting. Wrong scale or missing units destroys credibility.
ASCII/Text Visualization Standards
Character set for text-based graphs:
│ ─ ┌ ┐ └ ┘ ╱ ╲ ● ○ ▲ ▼ ┼ ├ ┤
Axis notation:
Y-Axis Label (units)
│
80│
│
60│
│
40│
│
20│
│
0└───┬───┬───┬───┬───┬───┬───
0 2 4 6 8 10 12
X-Axis Label (units)
Data line styles:
- Solid line: ─── (primary scenario, baseline)
- Dashed line: ╌╌╌ or - - - (alternative scenario, comparison)
- Markers: ● (data points), ▲ (intervention), ▼ (crisis event)
Multiple scenarios on same graph:
80│ ┌───●─── Scenario A (solid)
│ ┌─○┤
60│ ╌─┘ │ ○╌╌╌ Scenario B (dashed)
│ ╌─┘ │
40│ ╌─┘ │
│╌─┘ │
20│ │
└──────────────┼──────────
0 3 6 9 12 months
▲
INTERVENTION
Spacing and readability:
- Leave 2-3 character spaces between axis ticks
- Align numbers right-justified on Y-axis
- Keep X-axis labels centered under tick marks
Template (copy and modify):
[Y-AXIS LABEL] (units)
│
MAX│
│
75%│ ┌───
│ ┌─┘
50%│ ┌─┘
│ ┌─┘
25%│ ┌─┘
│ ┌─┘
0 └───┬───┬───┬───┬───┬───┬───
0 1 2 3 4 5 6
[X-AXIS LABEL] (units)
Multi-Variable Framework
When you need to plot multiple variables, choose strategy systematically:
Strategy 1: Dual Y-Axis (Same Graph, Two Scales)
When to use:
- ✅ Variables have causal relationship (team size drives velocity)
- ✅ Different units (engineers vs story points)
- ✅ Similar time dynamics (both change over same period)
- ✅ Viewer needs to see correlation visually
Example: Team Size (left axis: engineers) + Velocity (right axis: points/sprint)
Limitations:
- Hard in ASCII (need clear labeling)
- Max 2 variables (more is confusing)
Strategy 2: Separate Panels (Stacked, Shared X-Axis)
When to use:
- ✅ Variables from different domains (technical vs human)
- ✅ Very different scales (0-100 bugs vs 1-10 morale)
- ✅ Want independent Y-axes for clarity
- ✅ More than 2 variables
Example:
Bug Backlog (bugs)
200│ ╱───
│ ╱──
100│╱──
0 └───────────
Morale (1-10)
10│────╲
│ ╲
5 │ ──╲
0 └───────────
0 3 6 months
Benefit: Each variable has appropriate scale, viewer can cross-reference via shared time axis
Strategy 3: Normalized 0-100% (Same Scale)
When to use:
- ✅ Relative trends matter more than absolute values
- ✅ Comparing variables with very different units
- ✅ Showing patterns, not magnitudes
Example: Customer % vs Revenue % vs Team % (all normalized to 0-100%)
Warning: Loses actionability. "Customer % = 75%" doesn't tell stakeholder "we have 7,500 customers."
Use sparingly: Only when pattern visualization is the goal, not decision-making.
Decision Matrix:
| Variables | Strategy | Example |
|---|---|---|
| 2 related, different units | Dual Y-axis | Team Size + Velocity |
| 3+ from different domains | Separate panels | Bugs + Morale + Debt |
| Need pattern, not magnitude | Normalized 0-100% | Multi-metric dashboard |
| 2 same units | Single axis, overlay | Scenario A vs B customers |
Comparison Strategies
Showing "with intervention vs without intervention":
Method 1: Overlay (Same Graph)
Best for:
- Similar scales (both scenarios fit 70-80% rule on same Y-axis)
- Direct visual comparison
- 2-3 scenarios maximum
Technique:
- Solid line = Baseline
- Dashed line = Alternative
- Markers differentiate: ● vs ○
- Legend shows which is which
Example:
7000│ ○╌╌╌ With Investment (+5%)
│ ╌─┤
6000│ ╌─┘ │ ●── Baseline
│ ╌─┘ ●─┘
5000│ ╌─┘ ●─┘
│ ╌──●─┘
4000│●─┘
Method 2: Side-by-Side (Separate Graphs)
Best for:
- Different scales (Scenario A: 0-100, Scenario B: 0-500)
- Many scenarios (4+)
- Independent analysis
Technique:
- Graph 1: Scenario A
- Graph 2: Scenario B
- Shared time axis
- Separate Y-axis scales
Use: When overlay would be cluttered or scales incompatible
Method 3: Stacked Panels (Vertically Aligned)
Best for:
- Showing multiple aspects of same scenario
- Different variables (customers, revenue, cost)
- Aligned time for cross-reference
Technique:
- Panel 1: Primary metric
- Panel 2: Secondary metric
- Panel 3: Tertiary metric
- Shared X-axis, independent Y-axes
Phase/Region Marking
Showing "crisis zone" or "stable region":
Technique 1: Vertical bands (time periods):
│ [GROWTH] [CRISIS] [STABLE]
│ ╱──────╲ ──────────
│ ╱ ╲
│╱ ╲────────
└─────────────────────
0 3 6 9 12
Technique 2: Horizontal regions (threshold bands):
│ ───────── 200 bugs ←─── CRISIS THRESHOLD
│ ╱──────
│ ╱── [SAFE ZONE]
│╱──
└────────
Technique 3: Text labels with brackets:
│ ╱──────
│ ╱── └──[Peak: Crisis Mode]
│╱──
└─────
When to use:
- Complex dynamics with distinct phases (growth, plateau, decline)
- Critical thresholds (capacity limits, SLA boundaries)
- Multi-phase interventions (before, during, after)
Common Mistakes Catalog
1. Y-Axis Too Large
Mistake:
120│
│ ┌───── (Data only reaches 60)
60│ ┌─┘
│ ╱
0 └──────────
Problem: Wastes 50% of space, minimizes visual impact Fix: Apply 70-80% rule → Y-max = 80
2. Y-Axis Too Small
Mistake:
65│┌───────── (Data hits 60, cramped!)
│││
60││
└──────
Problem: Exaggerates tiny changes, looks volatile Fix: Provide 20-30% buffer above max value
3. Missing Units on Axes
Mistake:
│ "Technical Debt" ← What units? Story points? Hours? $$?
└── "Time" ← Days? Weeks? Months?
Fix: Always label with units: "Technical Debt (story points)", "Time (months)"
4. Time Range Too Short
Mistake: Showing months 0-3 when intervention at month 3 (cuts off outcome) Fix: Extend to month 6-12 to show result of intervention
5. Time Range Too Long
Mistake: Showing 24 months for 2-week bug fix project (dilutes insight) Fix: Match time range to problem scale (weeks for bugs, months for customers, years for strategy)
6. Too Many Annotations
Mistake: 15 labels, arrows, boxes → Unreadable clutter Fix: Limit to 5-7 most important events/thresholds
7. Wrong Graph Type
Mistake: Bar chart for continuous accumulation (treats smooth growth as discrete jumps) Fix: Use line graph for continuous, step function for discrete, bar for period comparison
8. Misleading Non-Zero Baseline
Mistake:
99.5│ ╱─── (Looks like 10× growth!)
│ ╱
99.0│╱
Reality: 99.0% → 99.5% is only +0.5% absolute change Fix: Either use 0 baseline OR annotate "Y-axis starts at 99%" prominently
9. Overlaying Incompatible Scales
Mistake: Plotting Customers (0-10,000) and Revenue ($0-$100) on same Y-axis without dual-axis Fix: Use dual Y-axis (left: customers, right: revenue) or separate panels
10. Missing Key Events
Mistake: Curve changes slope at month 6, no annotation explaining why Fix: Mark event: "▲ Infrastructure Investment" at month 6
Audience Adaptation Template
Create different versions for different audiences systematically.
Technical Version (Engineers, Analysts)
Language:
- Use precise terms: "Equilibrium", "Time constant", "Stock-dependent outflow"
- Show equations:
Debt(t+1) = Debt(t) + 15 - 5 - Include units: "story points", "bugs/week"
Detail level:
- All calculations shown
- Validation checks documented
- Alternative scenarios with sensitivity analysis
- Limitations and assumptions listed
Visual complexity:
- Multi-panel graphs acceptable
- Dual Y-axes if needed
- Detailed annotations (formulas, thresholds)
Focus: HOW and WHY (mechanics, validation, replication)
Executive Version (Board, C-Suite)
Language:
- Use business terms: "Debt stabilizes", "Crisis trajectory", "ROI"
- Hide equations (show result only)
- Use business units: "% of team capacity", "months to crisis"
Detail level:
- Key insights only (no intermediate calculations)
- Single clear recommendation
- ROI or cost-benefit comparison
- Risk framing ("Without action, we reach crisis in 6 months")
Visual complexity:
- Single clean graph (not multi-panel)
- Simple annotations (plain English, no jargon)
- Clear comparison (with vs without intervention)
Focus: WHAT and SO WHAT (outcomes, decisions, impact)
General Audience (Team, Stakeholders)
Language:
- Minimal jargon
- Clear labels ("Bug Count", not "Defect Density")
- Intuitive units (days/months, not time constants)
Detail level:
- Enough to understand trend, not full derivation
- Key events marked
- Why it matters explained in one sentence
Visual complexity:
- Simple line graph
- 3-5 annotations maximum
- Pattern should be obvious (up, down, stable)
Focus: UNDERSTANDING (what's happening, why it matters)
Systematic Translation Process:
| Aspect | Technical | Executive | General |
|---|---|---|---|
| Language | Equilibrium, τ, ΔS | Stabilizes, timeline, change | Levels off, when, difference |
| Detail | All calculations | Key insights | Main pattern |
| Visual | Multi-panel, dual-axis | Single clean graph | Simple line |
| Equations | Show formulas | Hide formulas | Hide formulas |
| Units | Precise (story points) | Business (% capacity) | Intuitive (days) |
| Focus | How/Why | What/So What | What/Why it matters |
Process: Create technical version first (complete), then simplify for executive/general by removing detail and translating language.
Integration with Other Skills
BOT + Stock-Flow Modeling
Workflow:
- Stock-Flow: Build equations, calculate values, find equilibrium
- BOT Graph: Visualize those values over time
- BOT Graph: Show trajectory toward (or away from) equilibrium
Example: Stock-flow calculates "Bug backlog drains to 0 in 4 weeks", BOT graph shows the decline curve
BOT + Causal Loop Diagrams
Workflow:
- CLD: Map feedback loops, identify reinforcing vs balancing
- Stock-Flow: Quantify the stocks and flows in loops
- BOT Graph: Show how loops create growth, decline, or oscillation over time
Example: CLD shows "Debt → Slow Velocity → Pressure → Shortcuts → Debt (R loop)", BOT graph shows exponential debt growth
BOT + System Archetypes
Workflow:
- Archetype: Recognize pattern (Fixes that Fail, Escalation)
- Stock-Flow: Model the specific instance
- BOT Graph: Show characteristic behavior (symptom relief then return worse)
Example: "Fixes that Fail" archetype → BOT shows quick fix working temporarily (months 1-3), then problem returning worse (months 4-6)
BOT + Leverage Points
Workflow:
- Leverage Points: Identify intervention options (parameter vs structure change)
- Stock-Flow: Model each intervention's impact
- BOT Graph: Compare scenarios visually (intervention A vs B vs do nothing)
Example: BOT shows "Hiring (Level 12): Small improvement, Quality (Level 10): Reaches equilibrium"
Complete Workflow:
- Unknown problem → Start with Causal Loop Diagram (map structure)
- Familiar pattern → Match to System Archetype (leverage known interventions)
- Need numbers → Build Stock-Flow Model (quantify stocks, flows, equilibrium)
- Show dynamics → Create BOT Graph (visualize trajectory over time)
- Choose intervention → Apply Leverage Points (rank options)
- Communicate decision → Use BOT Graph + Leverage Points (show impact of choice)
BOT graphs are communication and prediction tools - use them AFTER structure (CLD) and calculation (Stock-Flow) to show "what happens over time."
Red Flags: Rationalizations to Resist
"I can eyeball the curve"
Reality: Intuition fails on non-linear dynamics, delays, equilibrium points.
Counter:
- Exponential growth looks slow until it's not (then it's too late)
- Delays create overshoot your intuition won't predict
- Equilibrium isn't obvious (is it at 5,000 customers or 20,000?)
Test: Sketch your intuitive curve, then calculate. If they match, calculation was quick confirmation. If they don't, your intuition would have misled stakeholders.
"Math takes too long"
Reality: 10 minutes of calculation vs months of wrong decisions.
Counter:
- Stock-flow calculation: 10-15 minutes in spreadsheet
- Drawing wrong curve: Stakeholders make $100K decisions based on it
- Wrong trajectory = wrong intervention = wasted resources
Test: Time to calculate vs cost of error. If error >$10K and decision not easily reversed, CALCULATE.
"Let's make it look dramatic for the board"
Reality: Manipulated graphs destroy credibility permanently.
Counter:
- Non-zero baseline tricks can be spotted (lost trust forever)
- Exaggerated Y-axis makes real data look silly when revealed
- Board members aren't stupid - they'll ask questions
Test: If your graph would look different with accurate scale, you're manipulating. Use honest scale, let the real data speak.
"Too many details, keep it clean"
Reality: "Clean" without context is ambiguous; "simple" ≠ "simplistic"
Counter:
- Removing intervention annotation: Now curve's slope change is mysterious
- Removing threshold: Now viewer doesn't know when crisis hits
- Removing units: Now "60" means nothing
Test: Can stakeholder make correct decision with this graph? If annotations are needed for that, they stay.
"It's obvious what will happen"
Reality: Equilibrium points, overshoot, phase transitions are NOT obvious.
Counter:
- "Obviously grows forever" → Actually stabilizes at equilibrium
- "Obviously stabilizes" → Actually oscillates due to delays
- "Obviously smooth curve" → Actually has crisis dip (infrastructure limit)
Test: Ask three people to sketch their mental model. If they draw different curves, it's NOT obvious. Model it.
"We don't have time to calculate"
Reality: Presenting wrong trajectory wastes everyone's time.
Counter:
- Meeting starts in 30 min → 15 min to calculate, 15 min to draw
- Presenting without calculation → "How did you get these numbers?" → Credibility lost
- Stakeholders make multi-month plans based on your graph → Worth getting right
Test: Is this graph for decision-making or just discussion? If decision-making, calculate. Always.
"The actual data won't match anyway"
Reality: Models predict DYNAMICS (trends), not exact values.
Counter:
- You're right absolute numbers may be off ±20%
- But DYNAMICS are accurate: "Growth then plateau" vs "Unbounded growth"
- Overlay actual data when available, refine model
- Imperfect model > no model > wrong intuition
Test: Model shows "stabilizes at 5,000-7,000 customers in 12-18 months" - even if exact is 6,200 customers at 14 months, you captured the right behavior for decision-making.
Summary
Behavior-over-time graphs visualize system dynamics over time:
7-step construction process:
- Identify what to plot (stocks, not flows)
- Determine time scale (granularity and range)
- Calculate values (using stock-flow equations)
- Select graph type (line, area, step, bar)
- Choose scale (70-80% rule)
- Add annotations (events, phases, thresholds, max 5-7)
- Validate (checklist before presenting)
ASCII standards:
- Consistent character set: │ ─ ┌ ┐ └ ┘ ╱ ╲ ● ○
- Clear axis labels with units
- Templates for common patterns
Key rules:
- 70-80% scale rule (data_max = 70-80% of Y-axis)
- 2-3× time constant for range
- <7 annotations maximum
- Always calculate, never eyeball
Multi-variable strategies:
- Dual Y-axis: Related variables, different units
- Separate panels: Different domains, independent scales
- Normalized: Pattern focus, not magnitude
Audience adaptation:
- Technical: All details, equations, validation
- Executive: Key insights, business language, ROI
- General: Main pattern, minimal jargon, why it matters
Integration:
- BOT + Stock-Flow: Calculate then visualize
- BOT + CLD: Structure then dynamics
- BOT + Archetypes: Pattern then trajectory
- BOT + Leverage Points: Compare interventions
Resist rationalizations:
- "Eyeball it" → Intuition fails on non-linear systems
- "No time" → 15 min calculation vs wrong decisions
- "Make it dramatic" → Manipulation destroys credibility
- "Keep it clean" → Context matters for decisions
- "It's obvious" → Equilibrium, overshoot, phases aren't obvious
The discipline: Calculate values, choose scale systematically, validate before presenting, adapt to audience.
The payoff: Show concrete predictions with timelines, compare scenarios visually, communicate urgency effectively, enable data-driven decisions.