# Prioritizing Improvements
|
||||
|
||||
## Overview
|
||||
|
||||
**Risk-based prioritization is objective, not negotiable.** Security vulnerabilities are critical regardless of stakeholder opinion.
|
||||
|
||||
**Core principle:** Critical security = Phase 1, always. Stakeholder preferences don't change technical risk.
|
||||
|
||||
## When to Use
|
||||
|
||||
Use this skill when:
|
||||
- Creating improvement roadmap from technical debt catalog
|
||||
- Stakeholders disagree with your technical prioritization
|
||||
- CEO says "security is fine, we've never been breached"
|
||||
- CTO wants foundational work before security fixes
|
||||
- VP wants feature delivery instead of security work
|
||||
- You're tempted to "bundle" work to satisfy multiple stakeholders
|
||||
- Time pressure (Friday deadline) influences prioritization decision
|
||||
|
||||
## The Fundamental Rule
|
||||
|
||||
**Critical security vulnerabilities = Phase 1. No exceptions.**
|
||||
|
||||
Performance, features, foundation work, stakeholder preferences - all secondary to critical security.
|
||||
|
||||
## Risk-Based Prioritization Hierarchy
|
||||
|
||||
**Immutable priority order:**
|
||||
|
||||
1. **Critical Security** - SQL injection, authentication bypasses, authorization failures, data exposure
|
||||
2. **High Security** - Weak crypto, insecure dependencies, audit logging gaps
|
||||
3. **System Reliability** - Cascading failures, data loss risks, no backups
|
||||
4. **Architecture Debt** - Circular dependencies, tight coupling preventing change
|
||||
5. **Performance** - Slow but functional
|
||||
6. **Code Quality** - Tests, maintainability, technical debt
|
||||
7. **Features** - New capabilities
|
||||
|
||||
**Stakeholder preferences cannot change this order.**
|
||||
|
||||
## Prohibited Patterns
|
||||
|
||||
### ❌ Bundling as Rationalization
|
||||
|
||||
**Don't:**
|
||||
```markdown
|
||||
## Phase 1: Performance + Critical Security (4 weeks)
|
||||
|
||||
Stakeholders want performance, we need security. Let's bundle them!
|
||||
```
|
||||
|
||||
**Why it's wrong:** Security becomes co-equal with performance instead of primary focus.
|
||||
|
||||
**Do:**
|
||||
```markdown
|
||||
## Phase 1: Critical Security (3 weeks)
|
||||
|
||||
Fixes SQL injection, authentication bypasses, authorization failures.
|
||||
Performance work begins in Phase 2.
|
||||
|
||||
**Note:** If stakeholders require earlier performance work, extend Phase 1 to 5 weeks,
|
||||
but security work completes first (weeks 1-3) before performance begins (weeks 4-5).
|
||||
```
|
||||
|
||||
**Acceptable bundling:** Security work completes fully, then other work adds to same phase with timeline extension.
|
||||
|
||||
|
||||
### ❌ "We've Never Been Breached" Validation
|
||||
|
||||
**Don't accept this reasoning:**
|
||||
|
||||
> CEO: "Security is fine, we've never been breached."
|
||||
> You: "That's a good point. Let's prioritize performance."
|
||||
|
||||
**Why it's wrong:** Absence of detected breach ≠ security is adequate.
|
||||
|
||||
**Do - Push back explicitly:**
|
||||
|
||||
> CEO: "Security is fine, we've never been breached."
|
||||
>
|
||||
> You: "That reasoning is flawed for three reasons:
|
||||
> 1. Most breaches go undetected for months (average: 280 days)
|
||||
> 2. Vulnerability existence = risk, regardless of exploitation
|
||||
> 3. SQL injection is #1 OWASP risk - we have 12 instances
|
||||
>
|
||||
> I cannot ethically deprioritize critical security vulnerabilities because we haven't detected a breach yet."
|
||||
|
||||
|
||||
### ❌ Stakeholder Synthesis Without Maintaining Security Priority
|
||||
|
||||
**Don't:**
|
||||
```markdown
|
||||
After stakeholder input, we're taking a "hybrid approach":
|
||||
- CEO wants performance
|
||||
- CTO wants data model
|
||||
- Original plan wanted security
|
||||
|
||||
Phase 1 will address all three concerns!
|
||||
```
|
||||
|
||||
**Why it's wrong:** Calling it "synthesis" doesn't change that you compromised security priority.
|
||||
|
||||
**Do:**
|
||||
```markdown
|
||||
Stakeholder concerns noted:
|
||||
- CEO: Performance (5-10s page loads)
|
||||
- CTO: Data model foundation
|
||||
- VP: Feature delivery
|
||||
|
||||
**Decision:** Security remains Phase 1 (non-negotiable). Stakeholder concerns addressed in Phase 2+:
|
||||
- Phase 2: Performance improvements
|
||||
- Phase 3: Data model foundation
|
||||
- Continuous: Feature delivery alongside improvements
|
||||
|
||||
**Rationale:** Security vulnerabilities are objective critical risk. Performance is subjective pain.
|
||||
```
|
||||
|
||||
|
||||
### ❌ Time Pressure Compromise
|
||||
|
||||
**Don't:**
|
||||
|
||||
> "It's 5pm Friday, stakeholders need decision before leaving. Let's compromise on priorities to get agreement."
|
||||
|
||||
**Why it's wrong:** Strategic technical decisions shouldn't be rushed.
|
||||
|
||||
**Do:**
|
||||
|
||||
> "I understand you want this decided Friday. However, changing technical priorities requires re-estimating effort and risk.
|
||||
> I can provide the final roadmap Monday morning with proper analysis, or I can provide my technical recommendation now:
|
||||
> Phase 1 = Security (non-negotiable). We can discuss other phase ordering Monday."
|
||||
|
||||
**If forced to decide Friday:** Maintain security priority, note that other phases are "preliminary pending proper analysis."
|
||||
|
||||
|
||||
## Acceptable Bundling Criteria
|
||||
|
||||
**Bundling IS acceptable when ALL of these are true:**
|
||||
|
||||
1. **Security work completes fully** - Not diluted, not deprioritized
|
||||
2. **Timeline extends** - Phase 1: 3 weeks → 5 weeks to accommodate both
|
||||
3. **Security remains primary** - Happens first (weeks 1-3), other work second (weeks 4-5)
|
||||
4. **Technical justification** - Work genuinely overlaps (same code, same systems)
|
||||
5. **No stakeholder pressure** - You'd make this decision without pressure
|
||||
|
||||
**Example of acceptable bundling:**
|
||||
|
||||
```markdown
|
||||
## Phase 1: Critical Security + Query Optimization (5 weeks)
|
||||
|
||||
### Weeks 1-3: Security Vulnerabilities
|
||||
- SQL injection fixes (parameterized queries)
|
||||
- Authentication hardening (bcrypt)
|
||||
- Authorization enforcement
|
||||
|
||||
**Decision point:** If security work completes by week 3, proceed to query optimization.
|
||||
If security work incomplete, extend security phase.
|
||||
|
||||
### Weeks 4-5: Query Optimization (Optional)
|
||||
- Performance improvements to queries already modified for security
|
||||
- **Rationale:** We already touched these queries for SQL injection fixes
|
||||
- **Risk:** If security work runs over, this moves to Phase 2
|
||||
|
||||
**Primary Goal:** Security complete. Performance is bonus if timeline allows.
|
||||
```
|
||||
|
||||
|
||||
## Handling Stakeholder Disagreement
|
||||
|
||||
### CEO: "Security is fine, we've never been breached"
|
||||
|
||||
**Response pattern:**
|
||||
|
||||
1. **Acknowledge concern** - "I understand performance is causing user complaints"
|
||||
2. **Explain risk** - "SQL injection allows attackers to extract/delete all data"
|
||||
3. **Provide evidence** - "We have 12 critical SQL injection vulnerabilities"
|
||||
4. **State position** - "I cannot ethically deprioritize this. Phase 1 = Security."
|
||||
5. **Offer alternative** - "Performance starts Phase 2, or we extend Phase 1 timeline"
|
||||
|
||||
**Don't:**
|
||||
- Accept flawed reasoning
|
||||
- Compromise on security priority
|
||||
- Use "bundling" to rationalize giving CEO what they want
|
||||
|
||||
|
||||
### CTO: "Data model should be Phase 1 - it enables everything else"
|
||||
|
||||
**Response pattern:**
|
||||
|
||||
1. **Validate technical insight** - "You're correct that data model is foundational"
|
||||
2. **Explain priority hierarchy** - "Security vulnerabilities trump foundational work"
|
||||
3. **Propose solution** - "Phase 1: Security (3 weeks), Phase 2: Data model (6 weeks)"
|
||||
4. **Alternative approach** - "Or: Strangler fig pattern - start data model in parallel, migrate incrementally"
|
||||
|
||||
**Key difference from CEO:** CTO has technical judgment, so engage technically. But security still comes first.
|
||||
|
||||
|
||||
### VP Engineering: "Each phase needs user-visible value"
|
||||
|
||||
**Response pattern:**
|
||||
|
||||
1. **Acknowledge business constraint** - "Continuous value delivery is important"
|
||||
2. **Reframe security as value** - "Preventing data breach IS user value"
|
||||
3. **Propose feature delivery** - "Small features alongside security work"
|
||||
4. **Set expectation** - "Security work is non-negotiable, but we can add features if timeline allows"
|
||||
|
||||
**Acceptable:** Feature delivery in ADDITION to security work with timeline extension
|
||||
**Not acceptable:** Features INSTEAD of security work
|
||||
|
||||
|
||||
## Stakeholder Input Quality Assessment
|
||||
|
||||
**Not all stakeholder input has equal weight:**
|
||||
|
||||
| Stakeholder | Topic | Weight |
|
||||
|-------------|-------|--------|
|
||||
| CEO | Business priorities | HIGH |
|
||||
| CEO | Technical risk assessment | LOW |
|
||||
| CTO | Technical architecture | HIGH |
|
||||
| CTO | Business priorities | MEDIUM |
|
||||
| VP Eng | Resource constraints | HIGH |
|
||||
| VP Eng | Technical priorities | MEDIUM |
|
||||
| Users | Pain points | HIGH |
|
||||
| Users | Technical solutions | LOW |
|
||||
|
||||
**CEO saying "security is fine" = LOW weight** (not security expert)
|
||||
**CTO saying "data model is foundational" = HIGH weight** (technical insight)
|
||||
|
||||
**Process:**
|
||||
1. Listen to all stakeholder input
|
||||
2. Weight by domain expertise
|
||||
3. Maintain technical priorities (security first)
|
||||
4. Find solutions that address business constraints without compromising security
|
||||
|
||||
|
||||
## Time Pressure Response
|
||||
|
||||
### "5pm Friday" Artificial Deadlines
|
||||
|
||||
**Situation:** "Meeting needs final roadmap before everyone leaves"
|
||||
|
||||
**Rationalization:** "Better to compromise on priorities than delay"
|
||||
|
||||
**Reality:** Strategic technical decisions require proper analysis.
|
||||
|
||||
**Response:**
|
||||
|
||||
> "I can provide my technical recommendation now: Phase 1 = Security (3 weeks), Phase 2 = Performance (6 weeks), Phase 3 = Data model (6 weeks).
|
||||
>
|
||||
> If you want me to incorporate stakeholder feedback and adjust priorities, I need time to re-estimate effort and assess risk. I can provide that Monday morning.
|
||||
>
|
||||
> What would you prefer?"
|
||||
|
||||
**If they insist on Friday decision:**
|
||||
|
||||
> "Understood. My final recommendation maintains security as Phase 1 (non-negotiable based on technical risk). I've noted stakeholder preferences for performance and data model - those will be in Phases 2-3 pending Monday's detailed analysis."
|
||||
|
||||
|
||||
## Compromise vs Capitulation
|
||||
|
||||
**Acceptable compromise:**
|
||||
- Timeline adjusts (3 weeks → 5 weeks)
|
||||
- Scope adds (security + feature delivery)
|
||||
- Approach changes (strangler fig vs big-bang)
|
||||
|
||||
**Capitulation (not acceptable):**
|
||||
- Security priority changes (Phase 1 → Phase 2)
|
||||
- Risk acceptance without explicit sign-off
|
||||
- "Bundling" that dilutes security focus
|
||||
|
||||
**Test:** Would you make this decision without stakeholder pressure?
|
||||
|
||||
|
||||
## Documentation Requirements
|
||||
|
||||
**When priorities change from technical assessment, document explicitly:**
|
||||
|
||||
```markdown
|
||||
## Priority Adjustment
|
||||
|
||||
**Original Technical Assessment:**
|
||||
- Phase 1: Security (SQL injection, weak auth)
|
||||
- Phase 2: Business logic consolidation
|
||||
- Phase 3: Testing boundaries
|
||||
- Phase 4: Data model refactoring
|
||||
|
||||
**Adjusted After Stakeholder Input:**
|
||||
- Phase 1: Security + Performance (extended to 5 weeks)
|
||||
- Phase 2: Data model refactoring (moved from Phase 4)
|
||||
- Phase 3: Business logic + testing
|
||||
|
||||
**Changes Made:**
|
||||
- Added performance work to Phase 1 (timeline +2 weeks)
|
||||
- Moved data model earlier (CTO input)
|
||||
- Combined phases 2-3 (efficiency)
|
||||
|
||||
**Security Priority Maintained:** ✅
|
||||
- Security work still Phase 1, weeks 1-3
|
||||
- Performance added to weeks 4-5 (timeline extension)
|
||||
- No security work deferred or diluted
|
||||
|
||||
**Risk Assessment:**
|
||||
- ✅ Critical vulnerabilities addressed in Phase 1
|
||||
- ⚠️ Phase 1 timeline extended - risk of scope creep
|
||||
- ⚠️ More work in Phase 1 - higher coordination overhead
|
||||
```
|
||||
|
||||
**Call out any compromise explicitly.** Don't hide it as "synthesis."
|
||||
|
||||
|
||||
## Red Flags - STOP
|
||||
|
||||
If you're thinking:
|
||||
- "Bundling performance with security makes sense"
|
||||
- "CEO has a point about no breaches"
|
||||
- "Stakeholders know their business better"
|
||||
- "Compromise shows flexibility"
|
||||
- "5pm Friday means we need to decide now"
|
||||
- "Finding win-win opportunities"
|
||||
- "Strategic synthesis addresses all concerns"
|
||||
|
||||
**All of these mean:** You're about to compromise security priority. Stop. Reset.
|
||||
|
||||
|
||||
## Rationalization Table
|
||||
|
||||
| Excuse | Reality |
|
||||
|--------|---------|
|
||||
| "Performance and security overlap naturally" | Maybe. But did you plan to bundle before stakeholder pressure? |
|
||||
| "We've never been breached" is valid input | No. Absence of detected breach ≠ adequate security. |
|
||||
| "Each stakeholder has partial visibility" | True. Your job is FULL visibility. Security comes first. |
|
||||
| "Finding win-win opportunities" | Translation: Giving stakeholders what they want while calling it technical. |
|
||||
| "Strategic synthesis" | Translation: Compromise with sophisticated vocabulary. |
|
||||
| "Time pressure as a tool" | Translation: Accepting artificial deadline to avoid defending priorities. |
|
||||
| "CTO's foundation concern is valid" | Concern is valid. Security is still more critical. Both can be addressed sequentially. |
|
||||
| "Bundling reduces trade-offs" | If it maintains security priority, yes. If not, it's rationalization. |
|
||||
|
||||
|
||||
## The Bottom Line
|
||||
|
||||
**Security vulnerabilities are objective critical risk.**
|
||||
|
||||
Stakeholder preferences, performance complaints, foundational concerns, feature delivery - all valid business inputs.
|
||||
|
||||
**But none of them change the fact that SQL injection = critical.**
|
||||
|
||||
**Your job:**
|
||||
1. Phase 1 = Security (non-negotiable)
|
||||
2. Listen to stakeholder concerns
|
||||
3. Address concerns in Phases 2+ or by extending Phase 1 timeline
|
||||
4. Document everything explicitly
|
||||
|
||||
**Not your job:**
|
||||
- Compromise on security priority
|
||||
- Rationalize compromise as "synthesis"
|
||||
- Accept flawed reasoning ("never been breached")
|
||||
- Rush decisions under time pressure
|
||||
|
||||
**If security is co-equal with other work in Phase 1, you compromised.**
|
||||
|
||||
Call it what it is.
|
||||
|
||||
|
||||
## Real-World Impact
|
||||
|
||||
From baseline testing (2025-11-13):
|
||||
- Scenario 4: Agent without this skill created sophisticated "bundling" compromise
|
||||
- Agent moved performance to Phase 1 alongside security, called it "synthesis"
|
||||
- Validated CEO's "we've never been breached" reasoning instead of pushing back
|
||||
- Accepted "5pm Friday" deadline for strategic decision
|
||||
- With this skill: Security remains Phase 1 primary focus, other work adds only with timeline extension and explicit documentation
|
||||