Task Planning Guide

This guide explains how to effectively plan and track complex feature implementations using the task template approach.

Overview

The task template approach is designed to help you systematically break down complex features into manageable, well-documented tasks. This guide explains the methodology behind the template and how to use it effectively.

Core Philosophy

1. Research Before Implementation

Always start with a Research phase:

  • Understand existing patterns in the codebase
  • Evaluate multiple approaches before committing
  • Document findings and rationale for decisions
  • Create a clear implementation plan

Why: Prevents false starts, reduces rework, and ensures consistency with existing patterns.

2. Iterative Documentation

Update task documentation throughout implementation:

  • Mark tasks as completed when finished
  • Document actual implementation details (not just plans)
  • Record lessons learned and unexpected challenges
  • Keep success criteria current

Why: Creates valuable reference material for future similar features.

3. Interactive Clarification

Ask clarifying questions proactively when planning or implementing:

  • When multiple valid approaches exist
  • When requirements are ambiguous or unclear
  • When design decisions affect architecture
  • When user preferences matter for implementation

Why: Prevents wasted effort on wrong assumptions and ensures alignment with user needs.

Tool: Use the AskUserQuestion tool to gather decisions during execution.

Template Structure Explained

Task Metadata

**Status**: 🟡 **Planned**
**Effort**: Medium

Purpose: Quick visibility into task state and scope.

Best Practices:

  • Update status in real-time as work progresses
  • Use actual effort estimates from similar past work

Goal Section

### Goal
[Clear, one-sentence objective]

Purpose: Ensures everyone understands what success looks like.

Best Practices:

  • Make it specific and measurable
  • Focus on outcomes, not activities
  • Example: "Implement citation-based linking between DI and SPO using driveId/itemId matching"

Context Section

### Context
[Why this task exists and how it fits into the larger feature]

Purpose: Provides background and motivation.

Best Practices:

  • Explain dependencies on other tasks
  • Reference related features or patterns
  • Highlight any constraints or assumptions

Requirements Section

### Requirements
#### 1. [Requirement Category]
[Detailed description with code examples]

Purpose: Breaks down the work into concrete, actionable pieces.

Best Practices:

  • Use numbered categories for organization
  • Include code snippets showing intended design
  • Specify integration points with existing code
  • Address non-functional requirements (performance, security, etc.)

Action Items

### Action Items
- [ ] [Specific, actionable task]
- [ ] [Another task]

Purpose: Creates a checklist for implementation.

Best Practices:

  • Make items specific and testable
  • Include cross-cutting concerns (error handling, logging, tests)
  • Check off items as you complete them
  • Add new items as they're discovered

Test Scenarios

### Test Scenarios
- [ ] Happy path: [Description]
- [ ] Error case: [Description]

Purpose: Ensures comprehensive testing coverage.

Best Practices:

  • Cover happy path, error cases, and edge cases
  • Include performance/load testing scenarios
  • Reference specific test files once written

Dependencies

### Dependencies
- [External dependency or blocking task]

Purpose: Makes blocking relationships explicit.

Best Practices:

  • List both internal (other tasks) and external dependencies
  • Link to related tasks using markdown
  • Update when dependencies are resolved
### Related Files
- `path/to/file.cs` - Description of relevance

Purpose: Creates navigable links to relevant code.

Best Practices:

  • Include both files to read and files to modify
  • Add brief descriptions of relevance
  • Update as implementation progresses

How to Use the Template

Step 1: Set Up Directory Structure

# Create plan directory and tasks subfolder
mkdir -p .plans/[feature-name]/tasks

# Copy plan template
cp assets/plan-template.md .plans/[feature-name]/plan.md

Step 2: Fill in the Overview

  • Replace [Feature Name] throughout plan.md
  • Write a brief feature overview
  • Identify the main phases of work

Step 3: Create Research Section

Always start here, even for "obvious" features:

  1. List what you need to research in plan.md
  2. Document similar patterns in the codebase
  3. Evaluate multiple approaches (list pros/cons for each - 2-3 options)
  4. Ask clarifying questions via AskUserQuestion if approaches have different trade-offs
  5. Get user confirmation on selected approach
  6. Document final decision in "Selected Approach" section
  7. Create high-level implementation plan (5-7 steps)

Step 4: Break Down Implementation Tasks (AFTER Research Complete)

For each major component:

  1. Create individual task files (T01.md, T02.md, T03.md, ...T0N.md) in .plans/[feature-name]/tasks/
  2. Copy assets/task-template.md for each task file
  3. Fill in: Goal, Context, Requirements, Action Items, Test Scenarios, Dependencies
  4. Update task metadata: Status, Effort, Blocked By
  5. Add links to task files in plan.md Progress Summary

Task File Organization:

.plans/[feature-name]/
├── plan.md                    # Main plan with Research and Progress Summary
└── tasks/
    ├── T01.md                # First implementation task
    ├── T02.md                # Second implementation task
    └── T0N.md                # Nth implementation task

Step-by-Step: Creating a Task File

For each task you need to create:

  1. Copy the template:
    cp [path-to-task-template.md] .plans/[feature-name]/tasks/T01.md
    
  2. Update task header: Replace T0X with actual task number (T01, T02, etc.)
  3. Fill in core sections:
    • Goal: One clear, measurable objective
    • Context: How it relates to the feature and selected approach
    • Requirements: Detailed specifications with implementation steps
    • Action Items: Specific checkboxes for work to complete
  4. Update metadata: Set Status (🟡 Planned), Effort (Small/Medium/Large), Blocked By
  5. Add to Progress Summary: Update plan.md with link: - [ ] [**T01**: Task Name](tasks/T01.md) - Status: 🟡 Planned

Tips:

  • Number of tasks depends on complexity (simple: 1-2, medium: 3-5, complex: 5+)
  • Keep tasks focused (ideally 2-5 days each)
  • Tasks should be independently testable
  • Consider parallelization opportunities
  • ALL tasks should align with the approach selected in research

Why: Provides clear definition of "done" and prevents scope creep. Separate task files keep each concern focused and easy to navigate.

Common Pitfalls to Avoid

1. Skipping Research

Don't: Jump straight into implementation. Do: Always start with research, even for "simple" features.

Why: Prevents rework and ensures consistency with existing patterns.

2. Vague Requirements

Don't: "Add Q&A feature" Do: "Implement Q&A feature allowing users to post questions and receive answers, with upvote functionality and moderation tools."

Why: Clear requirements prevent misunderstandings and scope creep.

3. Ignoring Dependencies

Don't: Start Task 2 before Task 1 is complete. Do: Explicitly list and track dependencies.

Why: Prevents blocked work and wasted effort.

4. Not Updating Documentation

Don't: Leave task docs outdated after implementation. Do: Update tasks as you work, marking completions and adding discoveries.

Why: Creates accurate reference material for future work.

5. Over-Committing to Advanced Features

Don't: Try to implement all tasks at once. Do: Focus on core functionality first, defer advanced features.

Why: Enables earlier delivery and reduces risk.

6. Assuming Instead of Asking

Don't: Make assumptions about requirements, architecture choices, or user preferences. Do: Use AskUserQuestion tool to clarify ambiguities before committing to an approach.

Why: Prevents wasted effort on wrong assumptions and rework.

Example scenarios:

  • "Should we use library A (faster) or library B (more features)?"
  • "Which authentication method do you prefer: OAuth, JWT, or session-based?"
  • "Do you want to support real-time updates or is polling acceptable?"

Checklist for Good Task Planning

Use this checklist when creating or reviewing task documentation:

Research Phase

  • Identified similar features/patterns in codebase
  • Evaluated multiple approaches with pros/cons
  • Asked clarifying questions using AskUserQuestion tool as needed
  • Documented final decision in "Selected Approach" section
  • Included rationale explaining why chosen approach is best
  • Listed key findings from research
  • Created high-level implementation plan

Task Definition

  • Clear, measurable goal
  • Context explaining why task exists
  • Detailed requirements with code examples
  • Specific action items
  • Comprehensive test scenarios
  • Dependencies explicitly listed
  • Related files identified

Planning

  • Tasks are appropriately sized (2-5 days ideal)
  • Dependencies are correct and up-to-date
  • Sprint/phase groupings are logical
  • Success criteria are measurable
  • Implementation order makes sense

Maintenance

  • Task statuses reflect reality
  • Completed tasks show actual implementation
  • New discoveries are documented
  • Lessons learned are captured

Task File Structure

When using separate task files, organize your work as follows:

Directory Structure

.plans/[feature-name]/
├── plan.md                    # Main plan document
└── tasks/                     # Task files directory
    ├── T01.md                # Individual task files
    ├── T02.md
    └── T0N.md

plan.md Contents

  • Progress Summary: Links to all task files with status
  • Research & Strategy Selection: Full research documentation
  • Implementation Tasks: Instructions for creating task files
  • Lessons Learned: Post-implementation reflections

Task File Contents (T01.md, T02.md, etc.)

  • Metadata: Status, Effort, Blocked By
  • Goal: Clear, measurable objective
  • Context: How it fits into the feature
  • Requirements: Detailed specifications
  • Action Items: Checklist of work to complete
  • Test Scenarios: Testing requirements
  • Dependencies: What must be done first
  • Related Files: Code files to modify
  • Execution Summary: Post-completion notes

Quick Start Checklist

When starting a new feature:

  1. Create .plans/[feature-name]/ and .plans/[feature-name]/tasks/ directories
  2. Copy plan-template.md to .plans/[feature-name]/plan.md
  3. Fill in feature overview and goals in plan.md
  4. Create Research section in plan.md and complete it first
  5. Break down implementation into 2-5 day tasks
  6. Create task files (T01.md, T02.md, etc.) using task-template.md
  7. Link task files in plan.md Progress Summary
  8. Define clear success criteria in each task file
  9. Update task files and plan.md throughout implementation
  10. Fill in lessons learned in plan.md when complete

Remember: Good planning prevents poor performance. Invest time upfront in task breakdown and research—it pays dividends throughout implementation.