@@ -0,0 +1,171 @@
|
||||
{
|
||||
"name": "Roadmap Backcast Evaluator",
|
||||
"description": "Evaluates backcasting roadmaps for target clarity, milestone sequencing, dependency mapping, critical path identification, and feasibility assessment",
|
||||
"criteria": [
|
||||
{
|
||||
"name": "Target Outcome Specificity",
|
||||
"weight": 1.4,
|
||||
"scale": {
|
||||
"1": "Vague target ('launch product', 'improve system') with no date or success criteria",
|
||||
"2": "Target has date but outcome unclear or unmeasurable ('product better', 'customers happy')",
|
||||
"3": "Target somewhat specific with date (e.g., 'launch by Q1') but missing quantifiable success criteria",
|
||||
"4": "Specific measurable target with fixed date (e.g., '1000 customers by Jan 31, 2025') and clear criteria",
|
||||
"5": "Exemplary: Precise measurable outcome with fixed date, quantified success criteria (conversion rates, NPS, revenue), constraints documented (budget, scope, quality), strategic importance articulated"
|
||||
}
|
||||
},
|
||||
{
|
||||
"name": "Milestone Quality and Sequencing",
|
||||
"weight": 1.5,
|
||||
"scale": {
|
||||
"1": "No milestones or milestones are activities ('working on X') not deliverables",
|
||||
"2": "Milestones listed but not sequenced, vague deliverables, missing key checkpoints",
|
||||
"3": "5-10 milestones identified working backward, deliverables stated but some vague, basic sequencing",
|
||||
"4": "Clear milestones with specific deliverables, logically sequenced backward from target, owners assigned, durations estimated",
|
||||
"5": "Exemplary: 5-10 milestones with verifiable deliverables (not activities), precise backward sequencing using 'what must be true before' logic, each with owner/duration/prerequisites, milestones align to natural project phases, no missing critical checkpoints"
|
||||
}
|
||||
},
|
||||
{
|
||||
"name": "Dependency Mapping Completeness",
|
||||
"weight": 1.4,
|
||||
"scale": {
|
||||
"1": "No dependencies identified or implicit assumptions only",
|
||||
"2": "Some dependencies noted but incomplete, no distinction between sequential/parallel",
|
||||
"3": "Major dependencies mapped, sequential vs parallel identified, some gaps in upstream/downstream links",
|
||||
"4": "Comprehensive dependency mapping, clear prerequisites and enabled tasks for each milestone, parallel workstreams identified",
|
||||
"5": "Exemplary: All dependencies explicitly mapped (sequential, parallel, converging, diverging), dependency graph or table provided, handoff requirements specified, coordination points identified, external dependencies flagged with extra buffer"
|
||||
}
|
||||
},
|
||||
{
|
||||
"name": "Critical Path Identification",
|
||||
"weight": 1.5,
|
||||
"scale": {
|
||||
"1": "No critical path identified or not understood",
|
||||
"2": "Critical path mentioned but incorrectly identified or not validated",
|
||||
"3": "Critical path identified (longest dependent chain) but slack on non-critical tasks not calculated",
|
||||
"4": "Critical path correctly identified with duration, non-critical paths have slack calculated",
|
||||
"5": "Exemplary: Critical path precisely identified using CPM (forward/backward pass), slack calculated for all milestones, critical vs non-critical clearly distinguished, management strategy for critical path defined (monitoring, buffer allocation, acceleration options)"
|
||||
}
|
||||
},
|
||||
{
|
||||
"name": "Buffer and Risk Management",
|
||||
"weight": 1.3,
|
||||
"scale": {
|
||||
"1": "No buffers included, optimistic estimates only",
|
||||
"2": "Generic buffer mentioned ('add some extra time') but not quantified or placed",
|
||||
"3": "Buffers added (e.g., 20%) but uniform across all tasks regardless of uncertainty",
|
||||
"4": "Risk-appropriate buffers (20-30% for moderate, 40%+ for high uncertainty), placed on critical path",
|
||||
"5": "Exemplary: Buffers calibrated by uncertainty (10-50% range), PERT or 3-point estimates used, project buffer vs feeding buffers distinguished (CCPM), risk register with mitigation/contingency plans, triggers for re-planning defined, buffer consumption monitoring plan"
|
||||
}
|
||||
},
|
||||
{
|
||||
"name": "Feasibility Assessment Rigor",
|
||||
"weight": 1.4,
|
||||
"scale": {
|
||||
"1": "No feasibility check, assumed possible without analysis",
|
||||
"2": "Basic comparison (target date vs today) but no buffer, resource constraints, or risk consideration",
|
||||
"3": "Feasibility assessed (available time vs required time) with buffer, but resource/scope constraints not addressed",
|
||||
"4": "Rigorous feasibility: time + buffer + resource constraints + scope, verdict (feasible/tight/infeasible) with clear reasoning",
|
||||
"5": "Exemplary: Comprehensive feasibility assessment including time/buffer/resources/scope/risks, Monte Carlo or probability analysis (P50/P80/P95), if infeasible clear options provided (extend deadline X weeks, reduce scope Y features, add resources $Z cost), trade-off analysis for options, honest assessment not wishful thinking"
|
||||
}
|
||||
},
|
||||
{
|
||||
"name": "Resource and Capacity Planning",
|
||||
"weight": 1.2,
|
||||
"scale": {
|
||||
"1": "No resource consideration, assumes unlimited capacity",
|
||||
"2": "Resources mentioned but not quantified (team size, budget, constraints)",
|
||||
"3": "Resource requirements estimated but not compared to available capacity, gaps not identified",
|
||||
"4": "Resource requirements vs available capacity analyzed, gaps identified with mitigation (hiring, contractors)",
|
||||
"5": "Exemplary: Resource loading chart showing demand over time, peak capacity vs available, over-allocation identified and resolved (resource leveling/smoothing), hiring/onboarding timeline factored into plan, budget allocated to milestones, resource constraints drive sequencing decisions"
|
||||
}
|
||||
},
|
||||
{
|
||||
"name": "Actionability and Communication",
|
||||
"weight": 1.1,
|
||||
"scale": {
|
||||
"1": "Theoretical roadmap with no execution plan, stakeholders unclear, no ownership",
|
||||
"2": "Some execution details but vague, ownership not assigned, communication plan missing",
|
||||
"3": "Milestones have owners, basic communication plan (updates), but escalation path and decision gates unclear",
|
||||
"4": "Actionable: owners assigned, communication cadence defined (weekly updates, milestone reviews), escalation path for delays",
|
||||
"5": "Exemplary: Complete execution plan with named owners for each milestone, stakeholder communication plan (who/what/when), Go/No-Go decision gates at key milestones, escalation paths (3-level), status dashboard defined, next steps to initiate roadmap clear (approvals, kickoff, resource allocation)"
|
||||
}
|
||||
}
|
||||
],
|
||||
"guidance": {
|
||||
"by_roadmap_type": {
|
||||
"product_launch": {
|
||||
"typical_milestones": "Requirements locked → Design finalized → MVP built → Feature complete → QA passed → Beta testing → GA launch",
|
||||
"critical_path_focus": "Design → Engineering → Testing (usually 60-70% of timeline)",
|
||||
"buffer_recommendation": "20-30% on engineering (unknowns), 20% on testing (bugs), 10-20% on beta (user feedback)",
|
||||
"red_flags": ["No feature freeze milestone", "Testing squeezed at end", "No beta period", "Scope creep not controlled"]
|
||||
},
|
||||
"compliance_deadline": {
|
||||
"typical_milestones": "Gap analysis → Remediation plan → Controls implemented → Policies updated → Internal audit → External audit passed",
|
||||
"critical_path_focus": "Gap analysis → Remediation → Audit validation",
|
||||
"buffer_recommendation": "40%+ (cannot miss regulatory deadline, audit findings may require rework)",
|
||||
"red_flags": ["<30% buffer (high risk of missing)", "No internal audit before external", "Remediation not sequenced by dependency"]
|
||||
},
|
||||
"strategic_transformation": {
|
||||
"typical_milestones": "Strategy approved → Pilot complete → Learnings applied → Phase 1 rollout → Phase 2 rollout → Full migration",
|
||||
"critical_path_focus": "Pilot and learning (foundation for scale)",
|
||||
"buffer_recommendation": "30%+ per phase (unknowns compound over time)",
|
||||
"red_flags": ["No pilot/learning phase", "Trying to scale without validation", "Organizational change management missing"]
|
||||
},
|
||||
"event_planning": {
|
||||
"typical_milestones": "Date announced → Venue booked → Speakers confirmed → Content ready → Rehearsal → Event day",
|
||||
"critical_path_focus": "Venue booking (long lead time), speaker coordination",
|
||||
"buffer_recommendation": "10-20% (hard deadline, less flexible)",
|
||||
"red_flags": ["Venue not secured early", "No rehearsal milestone", "Content creation squeezed at end"]
|
||||
}
|
||||
}
|
||||
},
|
||||
"common_failure_modes": {
|
||||
"optimistic_sequencing": {
|
||||
"symptom": "Assumes perfect handoffs, no rework, no blockers; 0% buffer",
|
||||
"root_cause": "Wishful thinking, pressure to say 'yes' to deadline, Hofstadter's Law ignored",
|
||||
"fix": "Add 20-30% buffer to estimates, use PERT 3-point estimates (optimistic/likely/pessimistic), review against historical data"
|
||||
},
|
||||
"missing_dependencies": {
|
||||
"symptom": "Tasks planned in parallel that actually require sequential completion, integration surprises",
|
||||
"root_cause": "Didn't ask 'what must be true before this starts?', assumed work is independent",
|
||||
"fix": "Explicit dependency mapping (prerequisite/enables table), review with technical leads, identify converging/diverging points"
|
||||
},
|
||||
"wrong_critical_path": {
|
||||
"symptom": "Managing wrong tasks as critical, actual delays surprise team",
|
||||
"root_cause": "Intuition-based not calculation-based, didn't account for all dependencies",
|
||||
"fix": "Use CPM forward/backward pass, calculate slack, validate with project management tool"
|
||||
},
|
||||
"scope_creep_invalidates_plan": {
|
||||
"symptom": "Milestones slip because scope expanded mid-project",
|
||||
"root_cause": "No requirements freeze, stakeholder says 'just one more feature', change control missing",
|
||||
"fix": "Requirements freeze milestone, change control process (cost/timeline impact analysis before approving), stakeholder alignment on must-haves vs nice-to-haves"
|
||||
},
|
||||
"ignoring_resource_constraints": {
|
||||
"symptom": "Plan shows 10 engineers needed, only have 5, tasks over-allocated",
|
||||
"root_cause": "Assumed can parallelize everything, didn't check capacity",
|
||||
"fix": "Resource leveling (delay non-critical tasks), resource smoothing (steady demand), hire/contract to fill gaps"
|
||||
},
|
||||
"no_feasibility_check": {
|
||||
"symptom": "Backcast reaches before today, team commits anyway, fails predictably",
|
||||
"root_cause": "Sunk cost fallacy, pressure to commit, hope over reality",
|
||||
"fix": "Honest feasibility assessment, if infeasible present options (extend date, reduce scope, add resources), escalate to leadership for decision"
|
||||
}
|
||||
},
|
||||
"excellence_indicators": [
|
||||
"Target outcome is specific, measurable, with fixed date and quantified success criteria",
|
||||
"5-10 milestones working backward from target, each with clear deliverable",
|
||||
"Milestones sequenced using 'what must be true before' logic",
|
||||
"Dependencies explicitly mapped (sequential, parallel, converging, diverging)",
|
||||
"Critical path identified using CPM or visual dependency graph",
|
||||
"Slack calculated for non-critical milestones",
|
||||
"Buffers calibrated by uncertainty (20-50% range based on risk)",
|
||||
"Feasibility rigorously assessed: required time (with buffer) ≤ available time",
|
||||
"Resource constraints analyzed (team capacity vs requirements)",
|
||||
"If infeasible, clear options provided with trade-offs (extend deadline, reduce scope, add resources)",
|
||||
"Risk register for timeline threats with mitigation/contingency",
|
||||
"Owners assigned to each milestone",
|
||||
"Communication plan defined (weekly updates, milestone reviews, escalation path)",
|
||||
"Assumptions and constraints explicitly documented",
|
||||
"Honest assessment not wishful thinking (acknowledges tight timelines, risks)"
|
||||
]
|
||||
}
|
||||
387
skills/roadmap-backcast/resources/methodology.md
Normal file
387
skills/roadmap-backcast/resources/methodology.md
Normal file
@@ -0,0 +1,387 @@
|
||||
# Roadmap Backcast: Advanced Methodologies
|
||||
|
||||
## Table of Contents
|
||||
1. [Critical Path Method (CPM) Mathematics](#1-critical-path-method-cpm-mathematics)
|
||||
2. [Advanced Dependency Patterns](#2-advanced-dependency-patterns)
|
||||
3. [Buffer Management Techniques](#3-buffer-management-techniques)
|
||||
4. [Multi-Track Roadmaps](#4-multi-track-roadmaps)
|
||||
5. [Risk-Adjusted Timeline Planning](#5-risk-adjusted-timeline-planning)
|
||||
6. [Resource Optimization](#6-resource-optimization)
|
||||
|
||||
## 1. Critical Path Method (CPM) Mathematics
|
||||
|
||||
### Forward Pass (Earliest Start/Finish)
|
||||
|
||||
**Process**:
|
||||
1. Start at beginning, assign ES=0 to first milestone
|
||||
2. For each milestone: EF = ES + Duration
|
||||
3. For dependent milestones: ES = max(EF of all prerequisites)
|
||||
4. Continue until end milestone
|
||||
|
||||
**Example**:
|
||||
```
|
||||
Milestone A: ES=0, Duration=4, EF=4
|
||||
Milestone B (depends on A): ES=4, Duration=6, EF=10
|
||||
Milestone C (depends on A): ES=4, Duration=3, EF=7
|
||||
Milestone D (depends on B, C): ES=max(10,7)=10, Duration=2, EF=12
|
||||
```
|
||||
|
||||
**Project duration**: EF of final milestone = 12 weeks
|
||||
|
||||
### Backward Pass (Latest Start/Finish)
|
||||
|
||||
**Process**:
|
||||
1. Start at end, assign LF = EF of final milestone
|
||||
2. For each milestone: LS = LF - Duration
|
||||
3. For prerequisites: LF = min(LS of all dependents)
|
||||
4. Continue until start milestone
|
||||
|
||||
**Example** (working backward from D):
|
||||
```
|
||||
Milestone D: LF=12, Duration=2, LS=10
|
||||
Milestone B (enables D): LF=10, Duration=6, LS=4
|
||||
Milestone C (enables D): LF=10, Duration=3, LS=7
|
||||
Milestone A (enables B, C): LF=min(4,7)=4, Duration=4, LS=0
|
||||
```
|
||||
|
||||
### Slack Calculation
|
||||
|
||||
**Slack** (or Float) = LS - ES = LF - EF
|
||||
|
||||
**Milestones with zero slack are on critical path**:
|
||||
- Milestone A: 0-0=0 ✓ Critical
|
||||
- Milestone B: 4-4=0 ✓ Critical
|
||||
- Milestone C: 7-4=3 (3 weeks slack, non-critical)
|
||||
- Milestone D: 10-10=0 ✓ Critical
|
||||
|
||||
**Critical path**: A → B → D (12 weeks)
|
||||
|
||||
### Using Slack for Scheduling
|
||||
|
||||
**Milestones with slack**:
|
||||
- Can be delayed up to slack amount without impacting project
|
||||
- Use slack to smooth resource utilization
|
||||
- Delay non-critical work to free resources for critical path
|
||||
|
||||
**Example**: Milestone C has 3 weeks slack
|
||||
- Can start as early as week 4 (ES=4)
|
||||
- Must start no later than week 7 (LS=7)
|
||||
- Flexibility to schedule based on resource availability
|
||||
|
||||
## 2. Advanced Dependency Patterns
|
||||
|
||||
### Soft Dependencies vs Hard Dependencies
|
||||
|
||||
**Hard dependency** (cannot proceed without):
|
||||
- Example: Cannot test code until code is written
|
||||
- Enforce strictly in schedule
|
||||
|
||||
**Soft dependency** (preferable but not required):
|
||||
- Example: Prefer to have design complete before engineering, but can start with partial design
|
||||
- Allow overlap if timeline pressure, accept rework risk
|
||||
|
||||
### Lag and Lead Time
|
||||
|
||||
**Lag**: Mandatory delay between dependent tasks
|
||||
- Example: "Concrete must cure 7 days after pouring before building on it"
|
||||
- Add lag to dependency: A → [+7 days lag] → B
|
||||
|
||||
**Lead**: Task can start before prerequisite fully completes
|
||||
- Example: "Can start integration testing when 80% of code complete"
|
||||
- Negative lag or start-to-start dependency with offset
|
||||
|
||||
### Conditional Dependencies
|
||||
|
||||
**Branching dependencies**:
|
||||
```
|
||||
Design Complete → [If design approved] → Engineering
|
||||
→ [If design rejected] → Redesign → Engineering
|
||||
```
|
||||
|
||||
**Include in backcast**: Plan for expected path, note contingency branches
|
||||
|
||||
### External Dependencies (Outside Team Control)
|
||||
|
||||
**Vendor deliveries, regulatory approvals, partner integration**:
|
||||
- Identify early (longest lead time often on critical path)
|
||||
- Add extra buffer (40-50% for external dependencies)
|
||||
- Establish contract penalties for delays
|
||||
- Plan alternative paths where possible
|
||||
|
||||
**Example**:
|
||||
- Primary path: Vendor delivers component → Integration (4 weeks lead time, +50% buffer = 6 weeks)
|
||||
- Backup path: Build in-house (8 weeks, more reliable) - evaluate cost/benefit
|
||||
|
||||
## 3. Buffer Management Techniques
|
||||
|
||||
### Critical Chain Project Management (CCPM)
|
||||
|
||||
**Concept**: Remove buffers from individual tasks, aggregate into project buffer at end
|
||||
|
||||
**Traditional approach**:
|
||||
- Task A: 4 weeks + 20% buffer = 4.8 weeks
|
||||
- Task B: 6 weeks + 30% buffer = 7.8 weeks
|
||||
- Total: 12.6 weeks
|
||||
|
||||
**CCPM approach**:
|
||||
- Task A: 4 weeks (aggressive estimate)
|
||||
- Task B: 6 weeks (aggressive estimate)
|
||||
- Project buffer: 50% of critical path = 5 weeks
|
||||
- Total: 15 weeks (4+6+5)
|
||||
|
||||
**Benefits**: Prevents Parkinson's Law (work expands to fill time), focuses on project completion not task completion
|
||||
|
||||
### Buffer Placement
|
||||
|
||||
**Project buffer**: At end of critical path (protects project deadline)
|
||||
|
||||
**Feeding buffer**: Where non-critical path joins critical path (prevents non-critical delays from impacting critical)
|
||||
|
||||
**Example**:
|
||||
```
|
||||
Critical: A (4w) → B (6w) → D (2w) → [Project Buffer: 3w]
|
||||
Non-critical: C (3w) → [Feeding Buffer: 1w] → D
|
||||
```
|
||||
|
||||
**Feeding buffer protects against C delaying D's start**
|
||||
|
||||
### Buffer Consumption Monitoring
|
||||
|
||||
**Traffic light system**:
|
||||
- **Green** (0-33% buffer consumed): On track
|
||||
- **Yellow** (33-67% buffer consumed): Warning, monitor closely
|
||||
- **Red** (67-100% buffer consumed): Crisis, corrective action needed
|
||||
|
||||
**Example**: 12-week critical path, 3-week buffer
|
||||
- Week 8 complete, 1 week delay → 1/3 buffer consumed → Green
|
||||
- Week 10 complete, 3 weeks delay → 3/3 buffer consumed → Red (need to accelerate or extend deadline)
|
||||
|
||||
## 4. Multi-Track Roadmaps
|
||||
|
||||
### Parallel Workstreams
|
||||
|
||||
**Identify independent tracks**:
|
||||
- Track 1 (Frontend): Design → Frontend dev → Frontend testing
|
||||
- Track 2 (Backend): API design → Backend dev → Backend testing
|
||||
- Track 3 (Infrastructure): Cloud setup → CI/CD → Monitoring
|
||||
|
||||
**Synchronization points** (all tracks must converge):
|
||||
- Integration testing (requires all 3 tracks complete)
|
||||
- Deploy to production (requires integration testing + infrastructure ready)
|
||||
|
||||
**Managing multi-track**:
|
||||
- Assign clear owners to each track
|
||||
- Identify longest track (determines overall timeline)
|
||||
- Monitor convergence points closely (often become critical)
|
||||
|
||||
### Portfolio Backcasting (Multiple Initiatives)
|
||||
|
||||
**Scenario**: Launch Products A, B, C by Q4 2025
|
||||
|
||||
**Approach**:
|
||||
1. Backcast each product independently
|
||||
2. Identify resource conflicts (same people/budget needed)
|
||||
3. Sequence to resolve conflicts (stagger starts, prioritize critical path work)
|
||||
4. Re-assess portfolio feasibility
|
||||
|
||||
**Resource smoothing**: Adjust non-critical task timing to avoid resource over-allocation
|
||||
|
||||
## 5. Risk-Adjusted Timeline Planning
|
||||
|
||||
### Monte Carlo Simulation for Timelines
|
||||
|
||||
**Process**:
|
||||
1. For each milestone, estimate optimistic/likely/pessimistic duration (3-point estimate)
|
||||
2. Run 1000+ simulations, randomly sampling from distributions
|
||||
3. Generate probability distribution of project completion dates
|
||||
|
||||
**Example**:
|
||||
```
|
||||
Milestone A: Optimistic=3w, Likely=4w, Pessimistic=6w
|
||||
Milestone B: Optimistic=4w, Likely=6w, Pessimistic=10w
|
||||
Milestone D: Optimistic=1w, Likely=2w, Pessimistic=4w
|
||||
```
|
||||
|
||||
**Simulation results**:
|
||||
- P50 (median): 12 weeks (50% chance complete by week 12)
|
||||
- P80: 15 weeks (80% chance complete by week 15)
|
||||
- P95: 18 weeks (95% chance complete by week 18)
|
||||
|
||||
**Use P80 or P90 for deadline setting** (realistic buffer)
|
||||
|
||||
### PERT (Program Evaluation and Review Technique)
|
||||
|
||||
**Expected duration formula**:
|
||||
```
|
||||
Expected = (Optimistic + 4×Likely + Pessimistic) / 6
|
||||
```
|
||||
|
||||
**Example**:
|
||||
```
|
||||
Milestone A: (3 + 4×4 + 6) / 6 = 4.17 weeks
|
||||
Milestone B: (4 + 4×6 + 10) / 6 = 6.33 weeks
|
||||
Milestone D: (1 + 4×2 + 4) / 6 = 2.17 weeks
|
||||
Critical path: 4.17 + 6.33 + 2.17 = 12.67 weeks
|
||||
```
|
||||
|
||||
**Standard deviation** (measures uncertainty):
|
||||
```
|
||||
σ = (Pessimistic - Optimistic) / 6
|
||||
```
|
||||
|
||||
**Example**:
|
||||
```
|
||||
Milestone B: σ = (10 - 4) / 6 = 1 week
|
||||
```
|
||||
|
||||
**68% chance B completes within 6.33 ± 1 week = 5.33 to 7.33 weeks**
|
||||
|
||||
### Risk-Driven Milestone Sequencing
|
||||
|
||||
**Identify highest-risk milestones** (technical unknowns, novel work, external dependencies)
|
||||
|
||||
**De-risk early**: Sequence high-risk work toward beginning of roadmap
|
||||
- Learn quickly if infeasible
|
||||
- Maximize time to pivot if needed
|
||||
- Avoid sunk cost trap (months invested before discovering blocker)
|
||||
|
||||
**Example**:
|
||||
- High risk: "Integrate with Partner X API" (never done before, unknown technical constraints)
|
||||
- **Do early**: Spike integration in month 1, not month 6 (discover blockers sooner)
|
||||
|
||||
## 6. Resource Optimization
|
||||
|
||||
### Resource Leveling
|
||||
|
||||
**Problem**: Resource over-allocation (need 10 engineers, have 5)
|
||||
|
||||
**Solution**:
|
||||
1. Identify over-allocated periods
|
||||
2. Delay non-critical tasks (use slack)
|
||||
3. If still over-allocated, extend critical path
|
||||
|
||||
**Example**:
|
||||
```
|
||||
Weeks 1-4: Tasks A + C = 10 engineers needed, have 5
|
||||
Task C has 3 weeks slack → Delay C to weeks 5-7
|
||||
Result: Weeks 1-4 (Task A: 5 engineers), Weeks 5-7 (Task C: 5 engineers)
|
||||
```
|
||||
|
||||
### Resource Smoothing
|
||||
|
||||
**Goal**: Minimize resource fluctuations (avoid hire/fire cycles)
|
||||
|
||||
**Approach**: Shift non-critical tasks within slack to create steady resource demand
|
||||
|
||||
**Example**:
|
||||
```
|
||||
Original: Weeks 1-4 (10 eng), Weeks 5-8 (2 eng), Weeks 9-12 (8 eng)
|
||||
Smoothed: Weeks 1-4 (6 eng), Weeks 5-8 (6 eng), Weeks 9-12 (6 eng)
|
||||
```
|
||||
|
||||
### Fast-Tracking (Overlapping Phases)
|
||||
|
||||
**Concept**: Start dependent task before prerequisite fully completes
|
||||
|
||||
**Example**:
|
||||
- Traditional: Design complete (week 4) → Engineering starts (week 5)
|
||||
- Fast-track: Engineering starts week 3 with 75% design complete → Risk of rework if design changes
|
||||
|
||||
**When to fast-track**:
|
||||
- Timeline pressure, small slack margin
|
||||
- Low risk of design changes (stable requirements)
|
||||
- Acceptable rework cost (10-20% likely)
|
||||
|
||||
**When NOT to fast-track**:
|
||||
- High design uncertainty (rework >50% likely)
|
||||
- Regulatory work (cannot afford rework)
|
||||
- Critical path already has adequate buffer
|
||||
|
||||
### Crashing (Adding Resources)
|
||||
|
||||
**Concept**: Shorten critical path by adding resources
|
||||
|
||||
**Example**: Task B (6 weeks, 1 engineer) → Add 2nd engineer → Completes in 4 weeks
|
||||
|
||||
**Constraints**:
|
||||
- **Diminishing returns**: 9 women can't make a baby in 1 month (Brooks's Law)
|
||||
- **Communication overhead**: Adding people initially slows down (ramp-up time)
|
||||
- **Indivisible tasks**: Some work cannot be parallelized
|
||||
|
||||
**When to crash**:
|
||||
- Critical path task, high priority to accelerate
|
||||
- Task is parallelizable (coding yes, architecture design harder)
|
||||
- Resources available (budget, hiring pipeline)
|
||||
- Early in project (time to onboard)
|
||||
|
||||
**Cost-benefit**:
|
||||
```
|
||||
Crashing cost: 2nd engineer for 4 weeks = $40K
|
||||
Benefit: 2 weeks earlier → Capture market window worth $200K
|
||||
ROI: ($200K - $40K) / $40K = 400% → Crash
|
||||
```
|
||||
|
||||
---
|
||||
|
||||
## Workflow Integration
|
||||
|
||||
**When to use advanced techniques**:
|
||||
|
||||
**CPM mathematics** → Complex roadmaps (>10 milestones), need precise critical path
|
||||
**Advanced dependencies** → Multi-team coordination, conditional paths, external dependencies
|
||||
**Buffer management** → High-uncertainty projects, regulatory timelines, want buffer visibility
|
||||
**Multi-track roadmaps** → Cross-functional initiatives, parallel product development
|
||||
**Risk-adjusted planning** → Novel work, high stakes, leadership wants confidence intervals
|
||||
**Resource optimization** → Constrained resources, want to minimize hiring/layoffs
|
||||
|
||||
**Start simple, add complexity as needed**:
|
||||
1. **Basic backcast**: Target → Milestones → Dependencies → Critical path (visual/intuitive)
|
||||
2. **Moderate complexity**: Add buffers, resource constraints, risk register
|
||||
3. **Advanced**: CPM calculations, Monte Carlo, CCPM, resource leveling
|
||||
|
||||
**Tools**:
|
||||
- **Simple** (5-10 milestones): Spreadsheet, Gantt chart, whiteboard
|
||||
- **Moderate** (10-30 milestones): Asana, Monday.com, Jira with dependencies
|
||||
- **Complex** (30+ milestones): MS Project, Primavera, dedicated project management software with CPM/PERT
|
||||
|
||||
---
|
||||
|
||||
## Case Study: Product Launch Backcast
|
||||
|
||||
**Target**: SaaS product live with 1000 paying customers by Dec 31, 2024
|
||||
|
||||
**Milestones** (working backward):
|
||||
1. **Dec 31**: 1000 customers (Target)
|
||||
2. **Dec 1**: GA launch, marketing campaign, 100 customers
|
||||
3. **Nov 1**: Beta complete, pricing finalized, sales ready
|
||||
4. **Oct 1**: Feature complete, QA passed, beta started (50 users)
|
||||
5. **Sep 1**: MVP built, alpha testing with 10 users
|
||||
6. **Aug 1**: Design finalized, APIs defined, engineering staffed
|
||||
7. **Jul 1**: Requirements locked, design started
|
||||
8. **Jun 1** (Today): Project approved, team forming
|
||||
|
||||
**Dependencies**:
|
||||
- Sequential: Requirements → Design → Engineering → QA → Beta → GA
|
||||
- Parallel: Marketing (starts Sep 1) ∥ Sales training (starts Oct 1)
|
||||
|
||||
**Critical path**: Requirements → Design → Engineering → QA → Beta → GA = 30 weeks
|
||||
- Requirements: 4 weeks
|
||||
- Design: 4 weeks
|
||||
- Engineering: 12 weeks
|
||||
- QA: 4 weeks
|
||||
- Beta: 4 weeks
|
||||
- GA ramp: 4 weeks
|
||||
- **Total**: 32 weeks
|
||||
|
||||
**Feasibility**:
|
||||
- Available: Jun 1 to Dec 31 = 30 weeks
|
||||
- Required (with 20% buffer): 32 × 1.2 = 38 weeks
|
||||
- **Verdict**: Infeasible by 8 weeks
|
||||
|
||||
**Options**:
|
||||
1. **Extend deadline**: Launch Feb 28, 2025 (+8 weeks)
|
||||
2. **Reduce scope**: Cut features, launch MVP-only → Engineering 8 weeks instead of 12 → Saves 4 weeks, still need +4
|
||||
3. **Accelerate**: Add 2 engineers to shorten Engineering 12→10 weeks → Costs $80K, saves 2 weeks, still need +6
|
||||
4. **Combination**: Reduce scope (-4 weeks) + Accelerate (-2 weeks) + 10% risk acceptance (+2 weeks buffer removed) = 30 weeks → **Feasible**
|
||||
|
||||
**Decision**: Reduce scope to MVP, add 1 engineer, accept 10% risk → Launch Dec 31 with 70% confidence
|
||||
362
skills/roadmap-backcast/resources/template.md
Normal file
362
skills/roadmap-backcast/resources/template.md
Normal file
@@ -0,0 +1,362 @@
|
||||
# Roadmap Backcast Template
|
||||
|
||||
## Workflow
|
||||
|
||||
Copy this checklist and track your progress:
|
||||
|
||||
```
|
||||
Roadmap Backcast Progress:
|
||||
- [ ] Step 1: Define target outcome
|
||||
- [ ] Step 2: Work backward to milestones
|
||||
- [ ] Step 3: Map dependencies
|
||||
- [ ] Step 4: Identify critical path
|
||||
- [ ] Step 5: Assess feasibility
|
||||
```
|
||||
|
||||
**Step 1: Define target outcome**
|
||||
|
||||
State specific outcome, date, success criteria. See [Target Definition](#target-definition).
|
||||
|
||||
**Step 2: Work backward to milestones**
|
||||
|
||||
Ask "what must be true just before?" iteratively. See [Milestone Backcasting](#milestone-backcasting-process).
|
||||
|
||||
**Step 3: Map dependencies**
|
||||
|
||||
Identify sequential vs parallel work. See [Dependency Mapping](#dependency-mapping).
|
||||
|
||||
**Step 4: Identify critical path**
|
||||
|
||||
Find longest dependent chain. See [Critical Path](#critical-path-identification).
|
||||
|
||||
**Step 5: Assess feasibility**
|
||||
|
||||
Check time available, add buffers, identify risks. See [Feasibility Assessment](#feasibility-assessment).
|
||||
|
||||
---
|
||||
|
||||
## Roadmap Backcast Template
|
||||
|
||||
### Target Definition
|
||||
|
||||
**Target Outcome**: [Specific, measurable end state]
|
||||
|
||||
**Target Date**: [Fixed deadline - DD/MM/YYYY]
|
||||
|
||||
**Success Criteria**:
|
||||
- [Criterion 1]: [Quantifiable measure of success]
|
||||
- [Criterion 2]: [...]
|
||||
- [Criterion 3]: [...]
|
||||
|
||||
**Why this matters**: [Business impact, strategic importance, consequences if missed]
|
||||
|
||||
**Constraints**:
|
||||
- **Budget**: [Available resources]
|
||||
- **Team**: [Available capacity, FTEs]
|
||||
- **Dependencies**: [External constraints, vendor timelines, regulatory deadlines]
|
||||
- **Scope**: [Must-haves vs nice-to-haves]
|
||||
|
||||
---
|
||||
|
||||
### Milestone Backcasting Process
|
||||
|
||||
**Working backward from target date:**
|
||||
|
||||
#### Milestone 0: Target Outcome (T+0)
|
||||
**Date**: [Target date]
|
||||
**Deliverable**: [Final outcome achieved]
|
||||
**Owner**: [Name/Role]
|
||||
**Dependencies**: [What must be complete for this to happen]
|
||||
|
||||
#### Milestone 1: [Name] (T-[X weeks/months])
|
||||
**Date**: [Date]
|
||||
**Deliverable**: [Specific output, not activity]
|
||||
**Owner**: [Name/Role]
|
||||
**Duration**: [X weeks/months]
|
||||
**Dependencies**: [Requires milestone 2, 3 complete]
|
||||
**What must be true before**: [State of world needed to start this milestone]
|
||||
|
||||
#### Milestone 2: [Name] (T-[X weeks/months])
|
||||
**Date**: [Date]
|
||||
**Deliverable**: [...]
|
||||
**Owner**: [...]
|
||||
**Duration**: [...]
|
||||
**Dependencies**: [...]
|
||||
**What must be true before**: [...]
|
||||
|
||||
#### Milestone 3: [Name] (T-[X weeks/months])
|
||||
**Date**: [Date]
|
||||
**Deliverable**: [...]
|
||||
**Owner**: [...]
|
||||
**Duration**: [...]
|
||||
**Dependencies**: [...]
|
||||
**What must be true before**: [...]
|
||||
|
||||
#### Milestone N: Starting Point (Today)
|
||||
**Date**: [Today's date]
|
||||
**Deliverable**: [Current state, what we have now]
|
||||
**Owner**: [...]
|
||||
**What we need to begin**: [Resources, approvals, information to start milestone N-1]
|
||||
|
||||
---
|
||||
|
||||
### Dependency Mapping
|
||||
|
||||
**Dependency Graph**:
|
||||
|
||||
```
|
||||
[Milestone A] ──→ [Milestone B] ──→ [Milestone D] ──→ [Target]
|
||||
↑
|
||||
[Milestone C] ────────────────────────┘
|
||||
```
|
||||
|
||||
**Dependency Table**:
|
||||
|
||||
| Milestone | Depends On (Prerequisites) | Enables (Downstream) | Type | Can Parallelize? |
|
||||
|-----------|---------------------------|----------------------|------|------------------|
|
||||
| [Milestone A] | None (start) | [B] | Sequential | No (on critical path) |
|
||||
| [Milestone B] | [A] | [D] | Sequential | No (on critical path) |
|
||||
| [Milestone C] | [A] | [D] | Parallel with B | Yes (non-critical) |
|
||||
| [Milestone D] | [B, C] | [Target] | Converging | No (on critical path) |
|
||||
|
||||
**Parallel workstreams** (can happen simultaneously):
|
||||
- [Milestone X] ∥ [Milestone Y]: [Why these can be parallel]
|
||||
- [Milestone Z] ∥ [Milestone W]: [...]
|
||||
|
||||
**Converging points** (multiple prerequisites):
|
||||
- [Milestone M] requires both [A] AND [B]: [Coordination needed]
|
||||
|
||||
**Diverging points** (one enables multiple):
|
||||
- [Milestone N] enables [X], [Y], [Z]: [Handoff process]
|
||||
|
||||
---
|
||||
|
||||
### Critical Path Identification
|
||||
|
||||
**Critical path** (longest dependent chain):
|
||||
|
||||
```
|
||||
[Start] → [Milestone A: 4 weeks] → [Milestone B: 6 weeks] → [Milestone D: 2 weeks] → [Target]
|
||||
Total: 12 weeks
|
||||
```
|
||||
|
||||
**Alternative paths** (non-critical, have slack):
|
||||
|
||||
```
|
||||
[Start] → [Milestone A: 4 weeks] → [Milestone C: 3 weeks] → [Milestone D: 2 weeks] → [Target]
|
||||
Total: 9 weeks (3 weeks slack)
|
||||
```
|
||||
|
||||
**Critical path milestones** (zero slack, delays directly impact target):
|
||||
- [Milestone A]: [Why on critical path, impact if delayed]
|
||||
- [Milestone B]: [Why on critical path, impact if delayed]
|
||||
- [Milestone D]: [Why on critical path, impact if delayed]
|
||||
|
||||
**Non-critical milestones** (have slack, can absorb delays):
|
||||
- [Milestone C]: [X weeks slack, latest finish date without impacting target]
|
||||
|
||||
**Critical path management**:
|
||||
- **Monitor**: [How will we track critical path progress? Weekly reviews, dashboards]
|
||||
- **Accelerate**: [Can we add resources to shorten critical path? Cost/benefit]
|
||||
- **Buffer**: [20-30% buffer on critical path tasks built in? Where?]
|
||||
|
||||
---
|
||||
|
||||
### Feasibility Assessment
|
||||
|
||||
**Time Analysis**:
|
||||
|
||||
| Component | Estimate (weeks) | Buffer (%) | Buffered (weeks) |
|
||||
|-----------|------------------|------------|------------------|
|
||||
| [Milestone A] | [4] | [20%] | [4.8] |
|
||||
| [Milestone B] | [6] | [30%] | [7.8] |
|
||||
| [Milestone D] | [2] | [20%] | [2.4] |
|
||||
| **Total (critical path)** | **12** | - | **15** |
|
||||
|
||||
**Available time**: [Target date - Today = X weeks]
|
||||
|
||||
**Required time** (with buffer): [15 weeks]
|
||||
|
||||
**Feasibility verdict**:
|
||||
- ✓ **Feasible** if Available ≥ Required (with X weeks margin)
|
||||
- ⚠ **Tight** if Available ≈ Required (±10%)
|
||||
- ✗ **Infeasible** if Available < Required
|
||||
|
||||
**If infeasible, options**:
|
||||
1. **Extend deadline**: Move target date to [new date] (need X additional weeks)
|
||||
2. **Reduce scope**: Cut [feature Y], defer [feature Z] to post-launch
|
||||
3. **Add resources**: Hire [N contractors/FTEs], cost $[X], reduces timeline by [Y weeks]
|
||||
4. **Accept risk**: Proceed with [X%] probability of missing deadline
|
||||
|
||||
---
|
||||
|
||||
### Risk Register
|
||||
|
||||
**Risks to timeline**:
|
||||
|
||||
| Risk | Probability (H/M/L) | Impact (H/M/L) | Mitigation | Contingency |
|
||||
|------|---------------------|----------------|------------|-------------|
|
||||
| [Vendor delay on component X] | H | H | Contract penalties, alternate vendor identified | Built 4-week buffer in milestone B |
|
||||
| [Key engineer leaves] | M | H | Cross-train team, document tribal knowledge | Contractor bench available |
|
||||
| [Scope creep from stakeholder Y] | H | M | Requirements freeze by milestone 2, change control process | Reserve 2 weeks flex time |
|
||||
| [Technical unknowns in integration] | M | H | Technical spike in milestone 3, architecture review | Parallel path with simpler approach |
|
||||
|
||||
**Triggers for re-planning**:
|
||||
- Critical path milestone delayed >1 week → Escalate, re-assess feasibility
|
||||
- Scope change >20% → Re-run backcast, adjust target or timeline
|
||||
- Resource loss >25% → Revisit parallelization, extend timeline
|
||||
|
||||
---
|
||||
|
||||
### Resource Allocation
|
||||
|
||||
**Team capacity**:
|
||||
|
||||
| Role | Available FTEs | Required FTEs (peak) | Gap | Mitigation |
|
||||
|------|----------------|----------------------|-----|------------|
|
||||
| [Engineering] | [5] | [7] | [-2] | [Hire 2 contractors by milestone 2] |
|
||||
| [Design] | [2] | [2] | [0] | [Sufficient] |
|
||||
| [QA] | [1] | [3] | [-2] | [Outsource testing for milestone 4] |
|
||||
|
||||
**Budget**:
|
||||
- **Total required**: $[X]
|
||||
- **Allocated**: $[Y]
|
||||
- **Gap**: $[X-Y] → [Source: reallocation, additional funding, scope reduction]
|
||||
|
||||
---
|
||||
|
||||
### Communication Plan
|
||||
|
||||
**Stakeholder alignment**:
|
||||
- **Weekly updates**: [To whom, what format, starting when]
|
||||
- **Milestone reviews**: [After each milestone, with stakeholders X, Y, Z]
|
||||
- **Go/No-Go gates**: [At milestones A, C before committing to next phase]
|
||||
|
||||
**Escalation path**:
|
||||
- **Level 1** (delays <1 week): Team lead resolves
|
||||
- **Level 2** (delays 1-2 weeks): Product manager adjusts plan
|
||||
- **Level 3** (delays >2 weeks or feasibility threat): Executive decision on scope/date
|
||||
|
||||
---
|
||||
|
||||
## Guidance for Each Section
|
||||
|
||||
### Target Definition
|
||||
|
||||
**Good target outcomes** (specific, measurable):
|
||||
- ✓ "1000 paying customers using product by Jan 31, 2025"
|
||||
- ✓ "SOC 2 Type II certification achieved by regulatory deadline Sept 1, 2025"
|
||||
- ✓ "Conference with 500 attendees, NPS >40, on Oct 15, 2024"
|
||||
|
||||
**Bad target outcomes** (vague, unmeasurable):
|
||||
- ❌ "Launch product soon"
|
||||
- ❌ "Improve compliance"
|
||||
- ❌ "Hold successful event"
|
||||
|
||||
### Milestone Backcasting
|
||||
|
||||
**Ask iteratively**: "What must be true just before [current milestone]?"
|
||||
|
||||
**Example (Product Launch)**:
|
||||
- **Target**: 1000 customers using product
|
||||
- **T-2 weeks**: Product in production, scaling, monitoring working
|
||||
- **T-6 weeks**: Beta complete, critical bugs fixed, ready for GA
|
||||
- **T-10 weeks**: MVP feature complete, QA passed
|
||||
- **T-14 weeks**: Design finalized, APIs defined
|
||||
- **T-18 weeks**: Requirements locked, team staffed
|
||||
- **Today** (T-20 weeks): Feasible if starting now
|
||||
|
||||
**Milestone quality**:
|
||||
- **Clear deliverable**: "Design finalized" not "working on design"
|
||||
- **Verifiable**: Can objectively check if done
|
||||
- **Owned**: Named person responsible
|
||||
- **Estimated**: Duration in days/weeks/months
|
||||
|
||||
### Dependency Mapping
|
||||
|
||||
**Identify dependencies by asking**:
|
||||
- "Can this start before [X] completes?" (sequential vs parallel)
|
||||
- "What does this milestone need to begin?" (prerequisites)
|
||||
- "What can't start until this finishes?" (downstream dependencies)
|
||||
|
||||
**Common patterns**:
|
||||
- **Waterfall phases** (design → build → test): Sequential, little parallelization
|
||||
- **Workstreams** (frontend ∥ backend ∥ infrastructure): Parallel, converge for integration
|
||||
- **Approvals/Reviews**: Often converging (need multiple sign-offs)
|
||||
|
||||
### Critical Path Identification
|
||||
|
||||
**Shortcuts for small roadmaps** (<10 milestones):
|
||||
1. Draw dependency graph
|
||||
2. Visually trace longest path
|
||||
3. Sum durations on that path
|
||||
|
||||
**For complex roadmaps** (>10 milestones):
|
||||
- Use project management tools (MS Project, Asana, Jira with dependencies)
|
||||
- Critical path method (CPM) calculation (forward/backward pass)
|
||||
|
||||
**Interpreting critical path**:
|
||||
- Critical path length = minimum project duration
|
||||
- Slack on non-critical tasks = flexibility
|
||||
- Delays on critical path directly delay target
|
||||
|
||||
### Feasibility Assessment
|
||||
|
||||
**Buffer guidance by uncertainty**:
|
||||
- **Low uncertainty** (done similar work before): 10-20% buffer
|
||||
- **Medium uncertainty** (some unknowns, dependencies): 20-30% buffer
|
||||
- **High uncertainty** (novel work, many risks): 30-50% buffer
|
||||
- **Regulatory/Compliance**: 40%+ buffer (risk intolerant)
|
||||
|
||||
**Feasibility decision tree**:
|
||||
```
|
||||
Available time ≥ Required time (with buffer)?
|
||||
├─ Yes → Proceed, monitor critical path closely
|
||||
├─ Within 10% → Proceed with risk acknowledgment, escalation plan
|
||||
└─ No → Re-plan (extend date, reduce scope, or add resources)
|
||||
```
|
||||
|
||||
---
|
||||
|
||||
## Common Patterns by Context
|
||||
|
||||
**Product Launch**:
|
||||
- Critical path: Design → Engineering → Testing (usually 60-70% of timeline)
|
||||
- Buffer: 20-30% on engineering, 20% on testing
|
||||
- Risks: Scope creep, technical unknowns, vendor delays
|
||||
|
||||
**Compliance/Regulatory**:
|
||||
- Critical path: Gap analysis → Remediation → Audit
|
||||
- Buffer: 40%+ (cannot miss regulatory deadline)
|
||||
- Risks: Audit findings require rework, controls take longer than expected
|
||||
|
||||
**Event Planning**:
|
||||
- Critical path: Venue booking (long lead time), content creation, speaker coordination
|
||||
- Buffer: 10-20% (hard deadline, less flexible)
|
||||
- Risks: Speaker cancellations, venue issues, low registration
|
||||
|
||||
**Strategic Transformation**:
|
||||
- Critical path: Foundation work (pilot, learnings) before scaling
|
||||
- Buffer: 30%+ per phase (unknowns compound)
|
||||
- Risks: Organizational resistance, scope expansion, funding cuts
|
||||
|
||||
---
|
||||
|
||||
## Quality Checklist
|
||||
|
||||
- [ ] Target outcome is specific and measurable
|
||||
- [ ] Target date is fixed (not flexible)
|
||||
- [ ] Success criteria are quantifiable
|
||||
- [ ] 5-10 major milestones identified working backward
|
||||
- [ ] Each milestone has clear deliverable (not activity)
|
||||
- [ ] Each milestone has owner assigned
|
||||
- [ ] Dependencies explicitly mapped (prerequisites identified)
|
||||
- [ ] Parallel workstreams identified where possible
|
||||
- [ ] Critical path identified (longest dependent chain)
|
||||
- [ ] Duration estimates include 20-30% buffer
|
||||
- [ ] Feasibility assessed: required time ≤ available time
|
||||
- [ ] Risks to timeline documented with mitigations
|
||||
- [ ] Resource constraints identified (team, budget)
|
||||
- [ ] Communication plan for stakeholder updates
|
||||
- [ ] Escalation path defined for delays
|
||||
- [ ] If infeasible, options provided (extend date, reduce scope, add resources)
|
||||