Plan Command
Description: Create a detailed modernization strategy and execution plan, utilizing ASSESSMENT.md if available, with phase breakdown, timeline, and resource allocation
Project Modernization Planning Protocol
Version: 1.0
Purpose: Create a comprehensive, actionable modernization plan
Input: Optional ASSESSMENT.md from /modernize-assess
Output: PLAN.md with detailed execution strategy
Duration: 3-6 hours
Note: Time estimates are based on typical human execution times and may vary significantly based on project complexity, team experience, and AI assistance capabilities.
Overview
This protocol creates a detailed modernization execution plan that serves as the blueprint for the /modernize-project command. The plan includes:
- ✅ Detailed phase breakdown with tasks
- ✅ Timeline and milestone schedule
- ✅ Resource allocation and team assignments
- ✅ Risk mitigation strategies
- ✅ Quality gates and success criteria
- ✅ Contingency plans
Core Principle: Proper planning prevents poor performance - plan before you execute.
Planning Process
Step 1: Load Assessment (if available)
# Check for ASSESSMENT.md
if [ -f "ASSESSMENT.md" ]; then
echo "✅ Found ASSESSMENT.md - using as input"
# Extract: scores, risks, estimates, recommendations
else
echo "⚠️ No ASSESSMENT.md found - will create basic assessment"
# Run abbreviated assessment inline
fi
If assessment exists:
- Use technical viability score
- Use identified risks
- Use effort estimates
- Use team capacity analysis
- Use dependency analysis
If no assessment:
- Create quick assessment (30 min)
- Gather basic project info
- Identify major risks
- Rough effort estimate
Step 2: Define Modernization Scope (30 minutes)
2.1 Objectives
Primary Objectives (MUST achieve):
- Upgrade to [Target Framework/Version]
- Eliminate CRITICAL/HIGH security vulnerabilities
- Achieve 100% test pass rate
- [Other must-have objective]
Secondary Objectives (SHOULD achieve):
- Improve code coverage to ≥85%
- Optimize performance (≥10% improvement)
- Modernize APIs and patterns
- [Other desirable objective]
Out of Scope (explicitly NOT doing):
- UI/UX redesign
- Feature additions
- Complete rewrite
- [Other exclusions]
2.2 Success Criteria
Technical Success:
- Framework upgraded to [Version]
- Security score ≥45
- Zero CRITICAL/HIGH vulnerabilities
- 100% test pass rate
- Code coverage ≥85%
- No performance regression >10%
Business Success:
- Delivered within [X weeks]
- Cost within $[Budget] ±10%
- Zero production incidents caused by migration
- Team trained on new framework
- Documentation complete
Step 3: Phase Planning (60-90 minutes)
For each of the 7 phases, define:
Phase 0: Discovery & Assessment
Duration: [X-Y days] Team: [Names/Roles] Agent: Migration Coordinator + Security Agent + Architect Agent
Tasks:
-
Project Inventory (4 hours)
- Map all projects/modules
- Identify dependencies
- Document current architecture
- Deliverable: Project inventory spreadsheet
-
Security Baseline (4 hours)
- Run vulnerability scan
- Categorize vulnerabilities
- Calculate security score
- Deliverable: Security baseline report
-
Test Baseline (4 hours)
- Run all existing tests
- Capture pass rates and coverage
- Document test infrastructure
- Deliverable: Test baseline report
-
Technology Assessment (4 hours)
- Research target framework
- Document breaking changes
- Identify obsolete APIs
- Deliverable: Technology assessment document
-
Effort Estimation (2 hours)
- Estimate each phase duration
- Identify parallel opportunities
- Calculate total timeline
- Deliverable: Detailed timeline
Exit Criteria:
- All assessments complete
- Security score calculated
- Timeline approved
- Budget approved
Risks:
Phase 1: Security Remediation
Duration: [X-Y days] Team: [Names/Roles] Agent: Security Agent (lead) + Coder Agent + Tester Agent
Tasks:
-
Fix CRITICAL Vulnerabilities (XX hours)
- CVE-XXXX-XXXX: [Package] → [Action]
- CVE-YYYY-YYYY: [Package] → [Action]
- Deliverable: Zero CRITICAL CVEs
-
Fix HIGH Vulnerabilities (YY hours)
- CVE-ZZZZ-ZZZZ: [Package] → [Action]
- [List all HIGH CVEs with remediation plan]
- Deliverable: Zero HIGH CVEs
-
Update Security Dependencies (ZZ hours)
- [Package 1]: v[Old] → v[New]
- [Package 2]: v[Old] → v[New]
- Deliverable: All security patches applied
-
Validation Testing (WW hours)
- Re-run security scan
- Run full test suite
- Verify no regressions
- Deliverable: Security score ≥45
Exit Criteria:
- ✅ Security score ≥45
- ✅ Zero CRITICAL vulnerabilities
- ✅ Zero HIGH vulnerabilities
- ✅ 100% test pass rate maintained
Risks:
Contingency:
- If unable to fix all HIGH: Document exceptions, get approval
- If tests fail: Allocate +XX hours for fixes
Phase 2: Architecture & Design
Duration: [X-Y days] Team: [Names/Roles] Agent: Architect Agent (lead) + Migration Coordinator
Tasks:
-
Create Migration ADRs (8 hours)
- ADR 0001: [Target Framework Selection]
- ADR 0002: [Dependency Strategy]
- ADR 0003: [Migration Approach]
- Deliverable: 3-5 ADRs in MADR format
-
Dependency Migration Matrix (6 hours)
- Map all dependencies to target versions
- Identify conflicts
- Define resolution strategy
- Deliverable: Dependency migration matrix
-
Breaking Changes Analysis (8 hours)
- Enumerate all breaking changes
- Estimate code impact %
- Create remediation guide
- Deliverable: Breaking changes guide
-
Module Migration Order (4 hours)
- Analyze dependencies
- Define migration sequence
- Identify parallel opportunities
- Deliverable: Module migration plan
Exit Criteria:
- ✅ All ADRs approved
- ✅ Dependency strategy defined
- ✅ Migration order established
- ✅ Team aligned on approach
Risks:
Phase 3: Framework & Dependency Modernization
Duration: [X-Y days] Team: [Names/Roles] Agent: Coder Agent (multiple) + Tester Agent
Parallel Execution Strategy:
Module A: [Dev 1] → [X days]
Module B: [Dev 2] → [Y days]
Module C: [Dev 3] → [Z days]
Tasks by Module:
Module A: [Name] (XX hours)
- Update framework target
- Update package references
- Fix compilation errors
- Run tests (100% pass required)
- Code review
- Deliverable: Module A migrated
Module B: [Name] (YY hours) [Similar breakdown]
Module C: [Name] (ZZ hours) [Similar breakdown]
Integration (WW hours)
- Merge all modules
- Resolve conflicts
- Full solution build
- Complete test suite
- Deliverable: All modules integrated
Exit Criteria:
- ✅ All modules migrated
- ✅ Solution builds successfully
- ✅ 100% test pass rate
- ✅ Zero P0/P1 issues
Risks:
Phase 4: API Modernization & Code Quality
Duration: [X-Y days] Team: [Names/Roles] Agent: Coder Agent + Tester Agent + Architect Agent
Tasks:
-
Replace Obsolete APIs (XX hours)
- [Old API 1] → [New API 1] (YY instances)
- [Old API 2] → [New API 2] (ZZ instances)
- Deliverable: Zero obsolete API warnings
-
Apply Modern Patterns (YY hours)
- async/await conversion
- Pattern matching
- Record types
- Deliverable: Modern code patterns applied
-
Enhance Test Coverage (ZZ hours)
- Add missing unit tests
- Add integration tests
- Target ≥85% coverage
- Deliverable: 85% code coverage
-
Code Quality (WW hours)
- Reduce complexity
- Fix code smells
- Improve naming
- Deliverable: Quality metrics improved
Exit Criteria:
- ✅ Zero obsolete APIs
- ✅ Code coverage ≥85%
- ✅ 100% test pass rate
- ✅ Code quality score improved
Risks:
Phase 5: Performance Optimization
Duration: [X-Y days] Team: [Names/Roles] Agent: Coder Agent + Tester Agent
Tasks:
-
Baseline Benchmarks (4 hours)
- Define performance tests
- Capture baseline metrics
- Set improvement targets
- Deliverable: Baseline report
-
Identify Bottlenecks (8 hours)
- Run profiler
- Analyze hot paths
- Prioritize optimizations
- Deliverable: Optimization backlog
-
Implement Optimizations (XX hours)
- [Optimization 1]
- [Optimization 2]
- [Optimization 3]
- Deliverable: Performance improvements
-
Validate Performance (6 hours)
- Re-run benchmarks
- Compare vs baseline
- Document gains
- Deliverable: Performance report
Exit Criteria:
- ✅ Performance ≥baseline (no regressions)
- ✅ Target improvements achieved OR justified
- ✅ Benchmarks documented
Risks:
Phase 6: Comprehensive Documentation
Duration: [X-Y days] Team: [Names/Roles] Agent: Documentation Agent (lead)
Tasks:
-
CHANGELOG.md (6 hours)
- Document breaking changes
- New features/improvements
- Bug fixes
- Security updates
- Deliverable: Complete CHANGELOG
-
MIGRATION-GUIDE.md (12 hours)
- Step-by-step upgrade guide
- Breaking changes details
- Before/after examples
- Troubleshooting
- Deliverable: Comprehensive migration guide (800+ lines)
-
Update Documentation (8 hours)
- Update README
- Update architecture docs
- Update API docs
- Deliverable: All docs current
-
ADR Summaries (4 hours)
- Compile all ADRs
- Create decision log
- Link to relevant docs
- Deliverable: ADR index
Exit Criteria:
- ✅ CHANGELOG complete
- ✅ Migration guide ≥800 lines
- ✅ All docs updated
- ✅ Documentation reviewed
Phase 7: Final Validation & Release
Duration: [X-Y days] Team: [Names/Roles] Agent: Tester Agent (lead) + Security Agent + Coordinator
Tasks:
-
Complete Test Execution (12 hours)
- Unit tests (100% pass)
- Integration tests (100% pass)
- Component tests (100% pass)
- E2E tests (100% pass)
- Performance tests (validation)
- Deliverable: All tests passing
-
Final Security Scan (4 hours)
- Run vulnerability scan
- Verify security score ≥45
- Document any LOW/MEDIUM issues
- Deliverable: Security approval
-
Release Preparation (8 hours)
- Create release notes
- Tag release version
- Package artifacts
- Deployment checklist
- Deliverable: Release package
-
GO/NO-GO Decision (2 hours)
- Review all quality gates
- Production readiness assessment
- Final approval
- Deliverable: GO or NO-GO
Exit Criteria:
- ✅ 100% test pass rate (all types)
- ✅ Security score ≥45
- ✅ Zero CRITICAL/HIGH vulnerabilities
- ✅ All documentation complete
- ✅ Release approved
Step 4: Timeline & Milestones (30 minutes)
Gantt Chart
Week 1-2: Phase 0 (Discovery) ████████
Week 3-4: Phase 1 (Security) ████████████
Week 5-6: Phase 2 (Arch) ████████
Week 7-10: Phase 3 (Framework) ████████████████████
Module A ████████
Module B ████████
Module C ████████
Week 11-13: Phase 4 (API Mod) ████████████
Week 14-15: Phase 5 (Perf) ████████
Week 16-17: Phase 6 (Docs) ████████
Week 18: Phase 7 (Validate) ████
Milestones
| Milestone | Date | Deliverables | Success Criteria |
|---|---|---|---|
| M1: Assessment Complete | Week 2 | Security baseline, test baseline, plan | All baselines captured |
| M2: Security Remediated | Week 4 | Security score ≥45, CVEs fixed | Zero CRITICAL/HIGH |
| M3: Architecture Approved | Week 6 | ADRs, migration strategy | Team aligned |
| M4: Framework Migrated | Week 10 | All modules on new framework | Builds, 100% tests |
| M5: Code Modernized | Week 13 | Modern APIs, ≥85% coverage | Quality improved |
| M6: Performance Validated | Week 15 | Benchmarks, optimizations | No regressions |
| M7: Documentation Complete | Week 17 | CHANGELOG, migration guide | All docs done |
| M8: Production Ready | Week 18 | Final validation, approval | GO decision |
Step 5: Resource Allocation (30 minutes)
Team Assignments
Phase 0: Discovery
- Lead: [Name] (Architect/Coordinator)
- Support: [Name] (Security)
- Hours: XX total
Phase 1: Security
- Lead: [Name] (Security specialist)
- Devs: [Name1, Name2]
- Tester: [Name]
- Hours: YY total
Phase 2: Architecture
- Lead: [Name] (Architect)
- Support: [Coordinator]
- Hours: ZZ total
Phase 3: Framework (PARALLEL)
- Module A: [Dev1] (WW hours)
- Module B: [Dev2] (VV hours)
- Module C: [Dev3] (UU hours)
- Tester: [Name] (TT hours)
- Hours: XX total
Phase 4-7: [Similar breakdown]
Capacity Planning
| Week | Available Hours | Allocated Hours | Buffer | Utilization |
|---|---|---|---|---|
| 1-2 | 160 | 120 | 40 | 75% |
| 3-4 | 160 | 140 | 20 | 88% |
| ... | ... | ... | ... | ... |
Total Project:
- Available: XX hours
- Allocated: YY hours
- Buffer (30%): ZZ hours
- Utilization: WW%
Step 6: Risk Management (45 minutes)
Risk Register
| ID | Risk | Probability | Impact | Severity | Mitigation | Owner |
|---|---|---|---|---|---|---|
| R01 | Dependency conflicts unresolvable | Medium | High | HIGH | Upfront analysis, alternatives ready | [Name] |
| R02 | Timeline overrun >30% | Medium | High | HIGH | Phased approach, weekly reviews | [Coordinator] |
| R03 | Critical bug in production | Low | Critical | HIGH | Comprehensive testing, rollback plan | [Tester] |
| R04 | Team member leaves | Low | Medium | MEDIUM | Knowledge sharing, documentation | [Manager] |
| R05 | Breaking changes missed | Medium | High | HIGH | Thorough analysis, peer review | [Architect] |
Mitigation Strategies
For High-Priority Risks:
R01: Dependency Conflicts
- Prevention: Analyze all dependencies upfront (Phase 0)
- Detection: Test builds daily
- Response: Have alternative packages researched
- Contingency: +2 weeks for rewrites if needed
R02: Timeline Overrun
- Prevention: 30% buffer, conservative estimates
- Detection: Weekly status reviews, burn-down charts
- Response: Descope secondary objectives
- Contingency: Defer Phase 4-5 to post-launch
R03: Production Bug
- Prevention: 100% test pass rate, comprehensive E2E
- Detection: Staged rollout, monitoring
- Response: Immediate rollback procedure
- Contingency: Rollback plan tested, backup ready
Step 7: Quality Gates & Decision Points (20 minutes)
Gate Criteria
Gate 1: Post-Assessment (End of Phase 0)
- GO if: Assessment score ≥60/100, budget approved
- NO-GO if: Score <60, CRITICAL risks, no budget
- Decision Maker: Executive sponsor
Gate 2: Post-Security (End of Phase 1)
- GO if: Security score ≥45, zero CRITICAL/HIGH
- NO-GO if: Unable to remediate critical CVEs
- Decision Maker: Security lead + Coordinator
Gate 3: Post-Architecture (End of Phase 2)
- GO if: All ADRs approved, team aligned
- NO-GO if: No viable migration path
- Decision Maker: Tech lead + Architect
Gate 4: Post-Framework (End of Phase 3)
- GO if: 100% tests pass, builds clean
- NO-GO if: <100% pass rate, build issues
- Decision Maker: Coordinator + Tester
Gate 5: Post-API Modernization (End of Phase 4)
- GO if: Coverage ≥85%, quality improved
- NO-GO if: Major quality regression
- Decision Maker: Tech lead
Gate 6: Post-Performance (End of Phase 5)
- GO if: No regression >10%, targets met
- NO-GO if: Critical regression
- Decision Maker: Tech lead + Architect
Gate 7: Post-Documentation (End of Phase 6)
- GO if: All docs complete and reviewed
- NO-GO if: Major gaps in documentation
- Decision Maker: Documentation lead
Gate 8: Final GO/NO-GO (End of Phase 7)
- GO if: All gates passed, production ready
- NO-GO if: Any blocker remaining
- Decision Maker: Executive sponsor
Step 8: Contingency Planning (30 minutes)
What-If Scenarios
Scenario 1: Critical Dependency Has No Compatible Version
- Impact: Cannot complete Phase 3
- Response:
- Research alternative packages
- Evaluate rewrite of dependent code
- Consider staying on current framework with security patches
- Timeline Impact: +2-4 weeks
- Effort Impact: Additional development and testing required
Scenario 2: Test Pass Rate Drops Below 80%
- Impact: Quality gate failure
- Response:
- Halt further changes
- Analyze all failures
- Dedicate team to fixes
- Re-run complete suite
- Timeline Impact: +1-2 weeks
- Effort Impact: Dedicated testing and bug fixing resources
Scenario 3: Performance Regression >20%
- Impact: Unacceptable for production
- Response:
- Roll back changes
- Profile and identify bottleneck
- Architect review optimization strategy
- Implement targeted fixes
- Timeline Impact: +2-3 weeks
- Effort Impact: Performance analysis and optimization work
Scenario 4: Key Team Member Leaves
- Impact: Knowledge loss, capacity reduction
- Response:
- Knowledge transfer session (if notice given)
- Redistribute work
- Consider contractor/consultant
- Extend timeline if needed
- Timeline Impact: +1-3 weeks
- Effort Impact: Onboarding and knowledge transfer overhead
PLAN.md Output Template
# Project Modernization Plan
**Project**: [Name]
**Current Version**: [Version]
**Target Version**: [Version]
**Plan Created**: [Date]
**Plan Owner**: [Name]
**Executive Sponsor**: [Name]
---
## Executive Summary
### Objectives
[Primary and secondary objectives]
### Timeline
- **Start Date**: [Date]
- **End Date**: [Date]
- **Duration**: XX weeks (YY calendar months)
- **Contingency Buffer**: 30% additional time
### Team
- **Team Size**: X developers
- **Key Roles**: [List]
- **External Resources**: [If any]
### Success Criteria
[Top 5 success criteria]
---
## Assessment Summary
[If ASSESSMENT.md exists, summarize key findings]
**Overall Assessment Score**: XX/100
**Recommendation**: [PROCEED/CAUTION/DEFER/DO NOT]
**Key Risks**:
1. [Risk 1]
2. [Risk 2]
**Mitigation Strategies**:
[Summary of how risks will be addressed]
---
## Scope
### In Scope
✅ [Item 1]
✅ [Item 2]
✅ [Item 3]
### Out of Scope
❌ [Item 1]
❌ [Item 2]
### Success Criteria
**Technical**:
- [Criterion 1]
- [Criterion 2]
**Business**:
- [Criterion 1]
- [Criterion 2]
---
## Phase Breakdown
[Include all 7 phases with tasks, durations, teams, deliverables, exit criteria]
### Phase 0: Discovery & Assessment
[Detailed breakdown as created above]
### Phase 1: Security Remediation
[Detailed breakdown]
[... Phases 2-7 ...]
---
## Timeline & Milestones
[Gantt chart and milestone table]
---
## Resource Allocation
[Team assignments and capacity planning]
---
## Risk Management
[Risk register and mitigation strategies]
---
## Quality Gates
[All 8 quality gates with criteria]
---
## Contingency Plans
[What-if scenarios and responses]
---
## Communication Plan
### Status Reporting
- **Daily**: Stand-up (15 min)
- **Weekly**: Status report to stakeholders
- **Bi-weekly**: Executive update
- **Monthly**: Board update (if applicable)
### Escalation Path
1. Team Lead
2. Tech Lead / Coordinator
3. Engineering Manager
4. CTO
5. Executive Sponsor
---
## Appendices
### A. Dependency Migration Matrix
[Detailed dependency upgrade plan]
### B. Breaking Changes Guide
[All breaking changes with remediation]
### C. Test Strategy
[Testing approach for each phase]
### D. Deployment Strategy
[How changes will be deployed]
---
**Plan Version**: 1.0
**Last Updated**: [Date]
**Next Review**: [Every 2 weeks during execution]
Usage Examples
Example 1: With Assessment
User: /modernize-plan
Claude: Checking for ASSESSMENT.md...
✅ Found ASSESSMENT.md (score: 78/100, PROCEED WITH CAUTION)
Using assessment findings:
- Technical Viability: 82/100
- Business Value: 74/100
- Risk Profile: MEDIUM (3 HIGH risks)
- Estimated Effort: 22-28 days
Creating detailed plan...
[Generates comprehensive plan based on assessment]
Phase 0: Discovery (2 days)
- Already have baseline from assessment
- Focus on detailed breaking changes
- Estimated: 2 days vs 1-2 days typical
Phase 1: Security (3-5 days)
- Assessment identified 3 CRITICAL, 12 HIGH CVEs
- [Detailed remediation plan]
[Continues through all phases]
✅ PLAN.md created (47 pages)
Summary:
- Duration: 24 weeks
- Team: 3 developers
- Milestones: 8 quality gates
- Timeline includes 30% contingency buffer
Example 2: Without Assessment
User: /modernize-plan
Claude: No ASSESSMENT.md found.
Running quick assessment first...
[30-minute abbreviated assessment]
Quick Assessment Results:
- Project Size: Medium (~35k LOC)
- Current: .NET 6
- Target: .NET 9
- Rough Estimate: 25-35 days
⚠️ Recommendation: Run full /modernize-assess for better accuracy
Creating plan with conservative estimates...
[Generates plan with wider ranges]
✅ PLAN.md created
Note: This plan has wider time/cost ranges due to limited assessment.
Consider running /modernize-assess for refined planning.
Best Practices
- Use Assessment - Always run
/modernize-assessfirst - Be Realistic - Conservative estimates prevent disappointment
- Include Buffer - 30% contingency is standard
- Define Gates - Clear decision points prevent drift
- Plan Contingencies - Murphy's law applies
- Get Buy-in - Review plan with all stakeholders before execution
Integration with /modernize-project
The plan created by this command is automatically used by /modernize-project:
User: /modernize-project
Claude: Checking for existing plan...
✅ Found PLAN.md
Using existing plan:
- 7 phases defined
- 24 weeks timeline
- 3 developers allocated
- 8 quality gates
Proceeding with execution...
[Follows plan exactly]
Document Owner: Migration Coordinator
Protocol Version: 1.0
Last Updated: 2025-10-25
Required Before: Running /modernize-project
Remember: Plans are worthless, but planning is essential. Create the plan, then adapt as needed. ✅