name: technical-planning
|
||||
description: Plans technical projects with risk-first development, milestone structuring, and managed deferral. Use when planning software projects, defining milestones, structuring development phases, or breaking down complex tasks into manageable iterations.
|
||||
---
|
||||
|
||||
# Technical Planning
|
||||
|
||||
## Core Principles
|
||||
|
||||
**Focus on "What" Not "How"**: Define deliverable outcomes, not implementation details. Specify constraints and success criteria, but leave implementation choices flexible.
|
||||
|
||||
**Last Responsible Moment**: Defer decisions until you have enough information to make them well, but not so late that they block progress. Make reversible decisions quickly; delay irreversible ones until necessary.
|
||||
|
||||
**Risk-First Development**: Address highest-risk technical challenges first. Build proof-of-concepts before full implementation. Ship working but imperfect solutions to validate core assumptions early.
|
||||
|
||||
**Managed Deferral**: Explicitly document what's being deferred and when it will be addressed. Distinguish between core value delivery and polish/optimization.
|
||||
|
||||
### Progress Tracking with TodoWrite
|
||||
|
||||
Use TodoWrite to track planning progress through the four phases:
|
||||
|
||||
1. **At start**: Create todos for each phase:
|
||||
```
|
||||
☐ Phase 1: Requirements & Risk Analysis
|
||||
☐ Phase 2: Milestone Planning
|
||||
☐ Phase 3: Implementation Strategy
|
||||
☐ Phase 4: Execution Framework
|
||||
```
|
||||
|
||||
2. **During planning**: Mark phases in_progress → completed as you work through them. Add sub-todos for key deliverables:
|
||||
```
|
||||
☐ Extract core requirements (2-3 user journeys)
|
||||
☐ Identify technical risks (high/integration/performance/architecture)
|
||||
☐ Define milestones with success criteria
|
||||
☐ Document deferred items with rationale
|
||||
```
|
||||
|
||||
3. **For complex projects**: Track clarifying questions and their resolutions as todos - prevents proceeding with incomplete information
|
||||
|
||||
### Decision Timing Framework
|
||||
|
||||
**Decide Early (Requirements Phase)**:
|
||||
- User problems being solved
|
||||
- Success criteria and measurement
|
||||
- Hard constraints (security, compliance, performance SLAs)
|
||||
- Critical integrations and dependencies
|
||||
- Technology choices that affect architecture
|
||||
|
||||
**Defer to Implementation (Execution Phase)**:
|
||||
- Specific algorithms or data structures
|
||||
- Internal API design details
|
||||
- Code organization patterns
|
||||
- Library choices (when multiple options work)
|
||||
- Performance optimizations (until proven necessary)
|
||||
- UI/UX details (until user testing)
|
||||
|
||||
**Why**: Early decisions should enable work without locking in details. Implementation decisions become clearer with hands-on experience and often reveal better alternatives than upfront planning suggests.
|
||||
|
||||
## Agent Guidelines
|
||||
|
||||
**Seek Clarity Before Proceeding**: Never assume unclear requirements, technical constraints, or business priorities. Only proceed when you have 80%+ confidence on critical aspects. Ask specific questions about:
|
||||
|
||||
- User problems being solved (not just features requested)
|
||||
- Success criteria and measurement approaches
|
||||
- Technical constraints and existing system dependencies
|
||||
- Team capabilities and technology preferences
|
||||
- Timeline constraints and priority trade-offs
|
||||
- Performance and scalability requirements
|
||||
|
||||
## Phase 1: Requirements & Risk Analysis
|
||||
|
||||
### Prerequisites Check
|
||||
|
||||
Verify:
|
||||
|
||||
- What user problems are being solved?
|
||||
- Who are the primary users and their workflows?
|
||||
- How will success be measured?
|
||||
- What are the technical and business constraints?
|
||||
|
||||
### Extract Core Requirements
|
||||
|
||||
1. Identify fundamental user problems being solved
|
||||
2. Map primary user journeys (focus on 2-3 critical paths)
|
||||
3. Define project success metrics
|
||||
|
||||
### Identify Technical Risks
|
||||
|
||||
1. **High-Impact Risks**: Technical unknowns that could invalidate the approach
|
||||
2. **Integration Risks**: External system dependencies and compatibility concerns
|
||||
3. **Performance Risks**: Scalability bottlenecks and algorithmic challenges
|
||||
4. **Architecture Risks**: Fundamental design decisions with broad implications
|
||||
|
||||
### Risk Prioritization Matrix
|
||||
|
||||
- **Critical + Unknown**: Must be addressed in Milestone 1 with proof-of-concepts
|
||||
- **Critical + Known**: Address in early milestones with established patterns
|
||||
- **Non-Critical**: Defer to later milestones or eliminate
|
||||
|
||||
## Phase 2: Milestone Planning
|
||||
|
||||
### Prerequisites Check
|
||||
|
||||
Verify:
|
||||
|
||||
- Priority order of technical risks identified in Phase 1
|
||||
- Team capacity and available timeline
|
||||
- Dependencies between different components
|
||||
- Definition of "working functionality" for this project
|
||||
|
||||
### Milestone Structure
|
||||
|
||||
- **Timeline**: 4-8 week cycles based on project complexity
|
||||
- **Deliverable**: Each milestone must produce working, testable functionality
|
||||
- **Risk Focus**: Sequence milestones to tackle highest-risk items first
|
||||
|
||||
### For Each Milestone, Define:
|
||||
|
||||
**Goal**: One-sentence description of milestone outcome
|
||||
|
||||
**Core Tasks**: 4-6 main implementation tasks following Last Responsible Moment principle:
|
||||
- Define clear outcomes and constraints
|
||||
- Identify dependencies and integration points
|
||||
- Provide context and considerations (not step-by-step instructions)
|
||||
- Leave implementation details flexible
|
||||
- Flag questions to resolve during execution
|
||||
|
||||
**Success Criteria**:
|
||||
- Minimum Viable Success (must achieve for milestone completion)
|
||||
- Complete Success (ideal outcome including polish)
|
||||
|
||||
**Risk Mitigation**: Specific unknowns to be resolved in this milestone
|
||||
|
||||
**Deferred Items**: What's intentionally left out and target milestone for inclusion
|
||||
|
||||
### Task Breakdown Guidelines
|
||||
|
||||
When breaking down tasks, provide **guidance not prescription**:
|
||||
|
||||
**✓ Good Task Definition** (outcome-focused):
|
||||
- Goal: "Enable users to authenticate securely"
|
||||
- Constraints: "Must integrate with existing session middleware; <100ms response time"
|
||||
- Guidance: "Consider session vs. token auth; review existing patterns in src/middleware/"
|
||||
- Validation: "Users can log in, sessions persist, tests pass"
|
||||
|
||||
**✗ Poor Task Definition** (overly prescriptive):
|
||||
- Step 1: "Create file auth.js with bcrypt import"
|
||||
- Step 2: "Write hashPassword function using bcrypt.hash with 10 rounds"
|
||||
- Step 3: "Create Express middleware checking req.session.userId"
|
||||
|
||||
**Why**: Good definitions let the implementer choose the best approach based on what they learn. Poor definitions lock in choices before understanding the context, often leading to rework.
|
||||
|
||||
### Example Milestone Definition
|
||||
|
||||
**Goal**: Validate user authentication and basic data retrieval from external API
|
||||
|
||||
**Core Tasks**:
|
||||
1. Implement OAuth flow with provider
|
||||
2. Create user session management
|
||||
3. Build API client with error handling
|
||||
4. Add basic user profile display
|
||||
|
||||
**Success Criteria**:
|
||||
- Minimum: Users can log in and see their profile data
|
||||
- Complete: Include profile editing and session persistence
|
||||
|
||||
**Risk Mitigation**: Confirm API rate limits and response time under load
|
||||
|
||||
**Deferred**: Advanced profile features, password reset flow (Milestone 3)
|
||||
|
||||
## Phase 3: Implementation Strategy
|
||||
|
||||
### Development Approach
|
||||
|
||||
- **Prototype First**: Build throwaway versions to test risky assumptions
|
||||
- **Core Before Polish**: Implement functional features before UI refinements
|
||||
- **Integration Early**: Test external system connections in first milestone
|
||||
- **Measure Continuously**: Track performance and user metrics from day one
|
||||
|
||||
### Technology Selection Criteria
|
||||
|
||||
1. **Team Expertise**: Prefer technologies your team knows well
|
||||
2. **Proven Reliability**: Choose mature, battle-tested options for core systems
|
||||
3. **Integration Capability**: Ensure compatibility with existing tools/systems
|
||||
4. **Scalability Path**: Technology should support anticipated growth
|
||||
|
||||
### Quality Gates
|
||||
|
||||
- All code must have basic test coverage
|
||||
- Performance benchmarks must be met for core user journeys
|
||||
- Security review required for authentication and data handling
|
||||
- Accessibility standards met for user-facing features
|
||||
|
||||
## Phase 4: Execution Framework
|
||||
|
||||
### Sprint Planning
|
||||
|
||||
1. **Risk Assessment**: Identify unknowns in upcoming work
|
||||
2. **Exploration Time**: Reserve 20-30% of sprint for prototyping/learning
|
||||
3. **Definition of Done**: Must include working functionality, not just completed code
|
||||
4. **Continuous Validation**: Regular stakeholder feedback on core user journeys
|
||||
|
||||
### Deferral Management
|
||||
|
||||
- **Regular Review**: Evaluate deferred items each milestone for continued relevance
|
||||
- **Categories**: Technical debt, UX polish, edge cases, performance optimization, advanced features
|
||||
- **Scheduling**: Plan deferred items into appropriate future milestones
|
||||
- **Elimination**: Some deferred items may become unnecessary
|
||||
|
||||
### Documentation Requirements
|
||||
|
||||
- Technical specification focusing on deliverable outcomes
|
||||
- Risk register with mitigation plans
|
||||
- Deferred items registry with target scheduling
|
||||
- Architecture decision records for major choices
|
||||
|
||||
## Decision Framework for Agents
|
||||
|
||||
**IF** project has unknown technical feasibility → Schedule proof-of-concept in Milestone 1
|
||||
**IF** project requires external integrations → Test minimal integration in first milestone
|
||||
**IF** project has performance requirements → Establish benchmarks and test core algorithms early
|
||||
**IF** team lacks expertise in chosen technology → Include learning/exploration time in early milestones
|
||||
**IF** project has tight deadlines → Focus on minimum viable success criteria and defer polish
|
||||
**IF** project is greenfield → Spend extra time on architecture decisions and foundational setup
|
||||
**IF** project is enhancement → Focus on integration points and backward compatibility
|
||||
|
||||
### When Unclear - Ask These Questions
|
||||
|
||||
**WHEN** requirements are vague → "What specific user problem does this solve? How will we measure success?"
|
||||
**WHEN** technical scope is undefined → "What are the must-have vs. nice-to-have technical capabilities?"
|
||||
**WHEN** timeline is unrealistic → "What are the non-negotiable deadlines and what flexibility exists?"
|
||||
**WHEN** team capabilities are unknown → "What technologies does the team have experience with? What are the skill gaps?"
|
||||
**WHEN** integration points are unclear → "What existing systems must this connect to? What are the data formats and API constraints?"
|
||||
**WHEN** performance needs are unspecified → "What are the expected user loads and response time requirements?"
|
||||
**WHEN** success criteria are missing → "How will we know this milestone is complete and successful?"
|
||||
|
||||
## Common Pitfalls to Avoid
|
||||
|
||||
- **Making assumptions instead of asking clarifying questions** when requirements are unclear
|
||||
- **Proceeding with incomplete information** rather than requesting necessary details
|
||||
- **Creating overly prescriptive task definitions** with step-by-step instructions instead of outcome-focused guidance
|
||||
- **Making implementation decisions too early** when they could be deferred to execution
|
||||
- Spending time on low-risk features while deferring critical unknowns
|
||||
- Over-engineering solutions before validating core assumptions
|
||||
- Planning implementation details instead of focusing on deliverable outcomes
|
||||
- **Guessing at user needs** instead of understanding specific problems being solved
|
||||
- Failing to document deferral decisions and rationale
|
||||
- Optimizing prematurely instead of proving core functionality first
|
||||
- **Locking in technology choices** before understanding the full context
|
||||