@@ -0,0 +1,394 @@
|
||||
---
|
||||
description: Execute Elixir implementation plan with verification checkpoints
|
||||
argument-hint: [plan-name or path]
|
||||
allowed-tools: Read, Write, Edit, Grep, Glob, Task, Bash, TodoWrite, AskUserQuestion
|
||||
---
|
||||
|
||||
# Implement
|
||||
|
||||
Execute an approved Elixir implementation plan with built-in verification and progress tracking.
|
||||
|
||||
## Purpose
|
||||
|
||||
Follow implementation plans phase-by-phase while maintaining quality through automated verification at each checkpoint.
|
||||
|
||||
## Steps to Execute:
|
||||
|
||||
### Step 1: Locate and Read Plan
|
||||
|
||||
**If user provides plan name:**
|
||||
```bash
|
||||
# Search for plan file
|
||||
find {{DOCS_LOCATION}}/plans -name "*[plan-name]*.md" -type f
|
||||
```
|
||||
|
||||
**If user provides path:**
|
||||
- Read the file directly
|
||||
|
||||
**If no argument provided:**
|
||||
- List available plans:
|
||||
```bash
|
||||
ls -t {{DOCS_LOCATION}}/plans/*.md | head -5
|
||||
```
|
||||
- Ask user which plan to implement
|
||||
|
||||
**Read plan completely:**
|
||||
- Use Read tool WITHOUT limit/offset
|
||||
- Parse the full plan structure
|
||||
- Identify all phases/tasks/milestones
|
||||
- Note the success criteria
|
||||
|
||||
### Step 2: Check Existing Progress
|
||||
|
||||
**Look for checkmarks in the plan:**
|
||||
- Identify which phases/tasks are already completed (checked)
|
||||
- Identify current phase/task (first unchecked item)
|
||||
- Verify completed items are actually done (spot check)
|
||||
|
||||
**If resuming work:**
|
||||
- Trust completed checkmarks unless evidence suggests otherwise
|
||||
- Start from first unchecked phase/task
|
||||
- Confirm with user if multiple checkmarks exist but work seems incomplete
|
||||
|
||||
**If starting fresh:**
|
||||
- All items should be unchecked
|
||||
- Begin with Phase 1 / Task 1 / Milestone 1
|
||||
|
||||
### Step 3: Review Original Context
|
||||
|
||||
**Before implementing, review:**
|
||||
- Original research that informed the plan
|
||||
- Related tickets or documentation
|
||||
- Files that will be modified
|
||||
|
||||
**Read referenced files:**
|
||||
- Read any files mentioned in the current phase/task
|
||||
- Understand current implementation
|
||||
- Identify exact changes needed
|
||||
|
||||
### Step 4: Execute Phase-by-Phase
|
||||
|
||||
**For each phase/task/milestone:**
|
||||
|
||||
1. **Mark as in-progress** in TodoWrite
|
||||
```
|
||||
1. [in_progress] Implementing Phase 1: Database Layer
|
||||
2. [pending] Implementing Phase 2: Context Functions
|
||||
3. [pending] Implementing Phase 3: Web Layer
|
||||
```
|
||||
|
||||
2. **Follow the plan's core intent** while remaining flexible:
|
||||
- Stick to the planned approach
|
||||
- Use the code examples as guides
|
||||
- Adapt if you discover better patterns in the codebase
|
||||
- If reality diverges from plan, surface the discrepancy (see Mismatches section)
|
||||
|
||||
3. **Make the changes:**
|
||||
- Create new modules as specified
|
||||
- Modify existing modules as specified
|
||||
- Add tests as specified
|
||||
- Update configuration if needed
|
||||
|
||||
4. **Run verification** after completing the phase:
|
||||
{{VERIFICATION_COMMANDS}}
|
||||
|
||||
5. **Update the plan file** with checkmarks:
|
||||
- Use Edit tool to add `[x]` to completed items in the plan
|
||||
- Example: Change `- [ ] Create schema` to `- [x] Create schema`
|
||||
|
||||
6. **Pause for confirmation:**
|
||||
- Present verification results
|
||||
- Show what was completed
|
||||
- Show test output if relevant
|
||||
- Ask: "Phase N complete. Proceed to Phase N+1?"
|
||||
- Wait for user approval before continuing
|
||||
|
||||
### Step 5: Handle Plan vs Reality Mismatches
|
||||
|
||||
**When reality diverges from the plan:**
|
||||
|
||||
**State the discrepancy explicitly:**
|
||||
- "The plan expects X to exist at path/to/file.ex:10"
|
||||
- "But I found Y instead"
|
||||
- "This matters because Z"
|
||||
|
||||
**Explain why it matters:**
|
||||
- How does this affect the current phase?
|
||||
- Can we proceed or must we adjust?
|
||||
|
||||
**Request clarity:**
|
||||
- "Should I:"
|
||||
- "A) Adapt the plan to match reality"
|
||||
- "B) Update reality to match the plan"
|
||||
- "C) Something else"
|
||||
|
||||
**Do not guess** - always surface mismatches and get user input.
|
||||
|
||||
### Step 6: Complete Implementation
|
||||
|
||||
**After all phases/tasks complete:**
|
||||
|
||||
1. **Run full verification suite:**
|
||||
{{FULL_VERIFICATION_SUITE}}
|
||||
|
||||
2. **Mark plan as complete:**
|
||||
- Edit plan file frontmatter: `status: completed`
|
||||
- Add completion date to frontmatter
|
||||
|
||||
3. **Present final summary:**
|
||||
```markdown
|
||||
✅ Implementation Complete: [Plan Name]
|
||||
|
||||
**Phases Completed**: [N]
|
||||
**Files Modified**: [list key files]
|
||||
**Tests Added**: [N]
|
||||
|
||||
**Final Verification**:
|
||||
- ✅ Compilation: Success
|
||||
- ✅ Tests: [N] passed
|
||||
{{QUALITY_TOOLS_SUMMARY}}
|
||||
|
||||
**Next Steps**:
|
||||
- Run QA validation: `/qa "[plan-name]"`
|
||||
- Manual testing recommended
|
||||
- Ready for code review
|
||||
```
|
||||
|
||||
## Verification Commands
|
||||
|
||||
### Per-Phase Verification
|
||||
|
||||
After each phase, run:
|
||||
|
||||
```bash
|
||||
# Compile with warnings as errors
|
||||
mix compile --warnings-as-errors
|
||||
|
||||
# Run tests
|
||||
{{TEST_COMMAND}}
|
||||
|
||||
# Format check
|
||||
mix format --check-formatted
|
||||
```
|
||||
|
||||
{{OPTIONAL_QUALITY_CHECKS}}
|
||||
|
||||
### Full Verification Suite
|
||||
|
||||
After completing all phases:
|
||||
|
||||
```bash
|
||||
# Clean compile
|
||||
mix clean && mix compile --warnings-as-errors
|
||||
|
||||
# Full test suite
|
||||
{{TEST_COMMAND}}
|
||||
|
||||
# Format check
|
||||
mix format --check-formatted
|
||||
|
||||
{{FULL_QUALITY_SUITE}}
|
||||
```
|
||||
|
||||
## Handling Failures
|
||||
|
||||
### If Compilation Fails
|
||||
|
||||
1. **Show the error**
|
||||
2. **Identify the issue** (missing import, typo, etc.)
|
||||
3. **Fix the issue**
|
||||
4. **Re-run compilation**
|
||||
5. **Do not proceed** until compilation succeeds
|
||||
|
||||
### If Tests Fail
|
||||
|
||||
1. **Show the test output**
|
||||
2. **Analyze the failure**:
|
||||
- Is it expected based on incomplete implementation?
|
||||
- Is it a real bug in the new code?
|
||||
- Is it a pre-existing test that needs updating?
|
||||
3. **Fix or update as needed**
|
||||
4. **Re-run tests**
|
||||
5. **Do not proceed** until tests pass
|
||||
|
||||
### If Pre-Commit Hook Triggers
|
||||
|
||||
Some projects have pre-commit hooks (format, Credo, etc.):
|
||||
|
||||
1. **Read the hook output**
|
||||
2. **Apply automatic fixes** if available:
|
||||
```bash
|
||||
mix format
|
||||
```
|
||||
3. **Address issues** manually if needed
|
||||
4. **Re-run verification**
|
||||
|
||||
## Progress Tracking
|
||||
|
||||
### TodoWrite Usage
|
||||
|
||||
Maintain a todo list throughout implementation:
|
||||
|
||||
```
|
||||
1. [completed] Read and parse plan
|
||||
2. [completed] Phase 1: Database Layer
|
||||
3. [in_progress] Phase 2: Context Functions
|
||||
4. [pending] Phase 3: Web Layer
|
||||
5. [pending] Phase 4: Tests
|
||||
6. [pending] Final verification
|
||||
```
|
||||
|
||||
**Update frequently:**
|
||||
- Mark completed when phase finishes
|
||||
- Mark in-progress when starting new phase
|
||||
- Keep user informed of progress
|
||||
|
||||
### Plan File Updates
|
||||
|
||||
The plan file is the source of truth:
|
||||
|
||||
- **Add checkmarks** as phases complete
|
||||
- **Update status** in frontmatter
|
||||
- **Add notes** if implementation deviates
|
||||
- **Preserve history** (don't delete content)
|
||||
|
||||
## Flexibility vs Adherence
|
||||
|
||||
### Stick to the Plan When:
|
||||
- Code examples are clear and correct
|
||||
- Planned approach matches codebase patterns
|
||||
- No new information contradicts the plan
|
||||
|
||||
### Adapt When:
|
||||
- You discover better existing patterns
|
||||
- File structure has changed
|
||||
- Dependencies have been updated
|
||||
- Tests reveal issues with planned approach
|
||||
|
||||
### Always Surface When:
|
||||
- Plan expects something that doesn't exist
|
||||
- Existing code contradicts planned changes
|
||||
- Uncertainty about how to proceed
|
||||
|
||||
## Elixir-Specific Guidelines
|
||||
|
||||
### Module Creation
|
||||
|
||||
When creating new modules:
|
||||
|
||||
```elixir
|
||||
defmodule MyApp.Context.Feature do
|
||||
@moduledoc """
|
||||
[Description of module purpose]
|
||||
"""
|
||||
|
||||
# Clear module structure
|
||||
# Use statements at top
|
||||
# Group related functions
|
||||
# Add @doc for public functions
|
||||
end
|
||||
```
|
||||
|
||||
### Test Organization
|
||||
|
||||
```elixir
|
||||
defmodule MyApp.FeatureTest do
|
||||
use MyApp.DataCase # or ConnCase for controllers
|
||||
|
||||
describe "function_name/1" do
|
||||
test "success case" do
|
||||
# Arrange
|
||||
# Act
|
||||
# Assert
|
||||
end
|
||||
|
||||
test "error case" do
|
||||
# Test error handling
|
||||
end
|
||||
end
|
||||
end
|
||||
```
|
||||
|
||||
### Migration Files
|
||||
|
||||
When creating migrations:
|
||||
|
||||
```elixir
|
||||
defmodule MyApp.Repo.Migrations.CreateFeature do
|
||||
use Ecto.Migration
|
||||
|
||||
def change do
|
||||
create table(:features) do
|
||||
add :name, :string, null: false
|
||||
# ...
|
||||
|
||||
timestamps()
|
||||
end
|
||||
|
||||
# Indexes
|
||||
create index(:features, [:name])
|
||||
end
|
||||
end
|
||||
```
|
||||
|
||||
**Run migration after creation:**
|
||||
```bash
|
||||
mix ecto.migrate
|
||||
```
|
||||
|
||||
## Resume Capability
|
||||
|
||||
### If Implementation is Interrupted
|
||||
|
||||
The plan file preserves state:
|
||||
|
||||
1. **Read the plan** - checkmarks show progress
|
||||
2. **Verify checkmarks** - spot check completed work
|
||||
3. **Continue** from first unchecked item
|
||||
4. **No need to restart** - trust the checkmarks
|
||||
|
||||
### If Tests Break Later
|
||||
|
||||
Sometimes completed phases have tests that break:
|
||||
|
||||
1. **Identify which phase's tests broke**
|
||||
2. **Analyze the root cause**
|
||||
3. **Fix the issue**
|
||||
4. **Re-verify that phase**
|
||||
5. **Continue with current phase**
|
||||
|
||||
## Example Session
|
||||
|
||||
**User**: `/implement user-authentication`
|
||||
|
||||
**Process**:
|
||||
1. Find plan: `{{DOCS_LOCATION}}/plans/2025-01-23-user-authentication.md`
|
||||
2. Read plan: 4 phases, all unchecked
|
||||
3. Phase 1: Create User schema
|
||||
- Create `lib/my_app/accounts/user.ex`
|
||||
- Create migration
|
||||
- Run `mix ecto.migrate`
|
||||
- Verify: `mix compile && {{TEST_COMMAND}}`
|
||||
- Update plan: `[x] Phase 1: Database Layer`
|
||||
- Pause: "Phase 1 complete. Proceed to Phase 2?"
|
||||
4. User: "yes"
|
||||
5. Phase 2: Add context functions
|
||||
- Implement in `lib/my_app/accounts.ex`
|
||||
- Add tests
|
||||
- Verify: `mix compile && {{TEST_COMMAND}}`
|
||||
- Update plan: `[x] Phase 2: Context Functions`
|
||||
- Pause: "Phase 2 complete. Proceed to Phase 3?"
|
||||
6. Continue until all phases complete
|
||||
7. Final verification suite
|
||||
8. Mark plan status: completed
|
||||
9. Present summary
|
||||
|
||||
## Important Reminders
|
||||
|
||||
- **One phase at a time**: Complete and verify before moving on
|
||||
- **Checkpoints matter**: Don't skip verification
|
||||
- **Update the plan**: Keep checkmarks current
|
||||
- **Pause for confirmation**: Let user track progress
|
||||
- **Surface mismatches**: Don't guess when plan diverges from reality
|
||||
- **Trust completions**: Checkmarks indicate done work (unless evidence suggests otherwise)
|
||||
- **Maintain quality**: All verifications must pass
|
||||
Reference in New Issue
Block a user